1
1 Dredging and Disposal Summary of Proposed Activities and - - PowerPoint PPT Presentation
1 Dredging and Disposal Summary of Proposed Activities and - - PowerPoint PPT Presentation
1 Dredging and Disposal Summary of Proposed Activities and Discussion on Submissions and Impacts 20 March 2020 2 Our Presentation Today POALs 30 POALs POALs Concerns Some Year Plan Capital Disposal Raised in comments on
20 March 2020
Dredging and Disposal Summary of Proposed Activities and Discussion on Submissions and Impacts
2
Our Presentation Today
3
POAL’s Disposal Consent POAL’s Capital Dredging Consent Application Concerns Raised in Consent Submissions Some comments on Northport POAL’s 30 Year Plan
The Port may move…
4
We figure this will be at least 30 years. This is the horizon used for our 30 Year Masterplan.
Port Future Study
“Short-term pathways need to be created to enable the Port to continue to operate efficiently prior to a planned new Port being established due to the substantial lead times involved. In this regard, the CWG identifies that additional berth length needs to be provided to fulfil the short and medium term capacity requirements of the Port in response to cruise and multi-cargo requirements.”
Infrastructure Update – Complete/Underway
5
Fergusson Container Terminal
- 3rd berth FN completed
- 3 new cranes tested
- Road grids remodeled
- Hatch Lid Platforms on all 8
cranes
- Lash Platforms on all 8 cranes
- New layout, 10 hectares of
repaving
- Southern Reefer (900 plugs)
complete
- Reclamation ongoing
Automation
- All 27 A-Strads under LET
- Over 13,000 hours of testing
- approx. 500 hours per A-strad
- 30 odd Locata poles raised
- 22km of trenching for fibre optic
cabling
- Project on planned time line for
Phase 1 end March 2020
- Automation from truck grid to
Terminal stack – manual from terminal stack to/from crane
Multi-Cargo
- Building of 5 storey car handling
facility
- New tug berth completed
Infrastructure
- Demolishing of 3 cranes on
Bledisloe
- Consent obtained for disposal of
dredgings at sea
- Consenting for channel deepening
- Development of Freight Hub
infrastructure for Supply Chain strategy
Project Timeline
6
The remaining Masterplan projects: 1. Demolish Shed 51 and part of Bledisloe B1 Wharf – 2021 2. Construct North Berth at Bledisloe – 2021/2023 3. Construct roof top park on car handling building – 2022 4. Relocate ships from Captain Cook to Bledisloe north – 2023 5. Replace wharf structure at south end of Bledisloe west – 2023/2024 6. Construct new sea wall south of Marsden Wharf – 2023/2024 7. Remove Marsden Wharf and deepen Captain Cook/Bledisloe basin – 2024/2025 8. Deepen channel – within 3 years 9. Engineering Workshop – design underway
- 10. Rail Grid Automation
- 11. Extend FN Wharf
Proposed Capital Dredging
7
- 15 year consent sought for 2.5m m3
capital dredging
- Staged - dredging only when required
- Stage 1: for 6-7,000 TEU vessels
already calling in NZ – starting in 2021
- Stage 2: for new 13,000 TEU
Panamax class vessels – expected to start in 2025–2027
- Application includes maintenance
dredging within the channel
- All main Australia / NZ ports preparing
for Panamax class ships
8
Current Capital Dredging Consent Application
Capital Dredging Consent – Regulatory Framework
Consenting framework in the Unitary Plan:
1.
Capital dredging is a restricted discretionary activity
2.
Restricted matters of discretion include:
―
the effects of construction works methods, and the timing and hours of operation;
―
the effects of the location, extent, design and materials;
―
effects on coastal processes, ecological values, water quality including the release of any contaminated sediment, and natural character and landscape values;
―
effects on public access, other users of the coastal marine area, harbour traffic, and navigation and safety;
―
effects on existing uses and activities (including significant infrastructure);
―
effects on Mana Whenua values;
―
effects on historic heritage; and
―
consent duration and monitoring.
3.
Maintenance dredging activities are a controlled activity
9
Recap of Previous Dredging Activities in the Channel
10
- Ports need to dredge to maintain
safe navigation
- Channel dredged number of times
since the 50’s
- Previous capital dredging
consented to 13.0m in 2001
- Only undertaken to 12.5m 2004-
2007
- Material used to reclaim
Fergusson Terminal
- Fergusson Terminal complete by
2021
Historic Channel Dredging
Stage 1: Dredging
11
- Channel design maximises use of tidal
windows to minimise dredge volumes
- All dredging within existing precincts
- Depth of material to be removed varies
FN Berth and Approaches Location Stage 1 Stage 2 Dredged Volume (m3) Dredged Depth (CD) Dredged Depth (CD) Shipping lane – bends
- 13.5m
- 14.2m
1,105,100 Shipping lane – straights
- 13.5m
- 14m
1,149,300 Fergusson approaches
- 13m
- 13.5m
184,100 Fergusson North Berth
- 15.2m
- 15.2m
61,100 Total 2,409,600 Navigation Channel
How do we dredge?
12
- We use a barge mounted excavator
- Bottom opening hopper barge
loaded directly by excavator
- Methodology used for many years
around Auckland
- Low impact - minimises sediment
release and disturbance to other users
- Duration of works:
― Stage 1 approximately 2 years ― Stage 2 approximately 3-4 years
Dredged Material Disposal
13
Disposal Permit
14
- POAL granted (by EPA) a 35 year
disposal consent at Cuvier Disposal Site (CDS) in June 2019
- One of five designated disposal sites in
NZ, in use since the end of WWII
- POAL (and others) have used site
previously
- POAL needs at least 1 disposal option
when Fergusson Terminal is completed next year
- Consent authorises disposal of capital
and maintenance dredged material
CDS Disposal Site Location
15
Characteristics of Disposal Site
16
Behaviour of dumped material Water currents
Application found disposal will not adversely affect local environment outside designated area (or Great Barrier)
- Disposal site – 700m deep on side of
continental shelf - currents low and dominated by north-south flow
- CDS is 4 nautical miles diameter –
disposal to occur within 250m of one location in CDS
- Over 90% reaches seabed directly as a
plume
Seabed characteristics
- 10% of fines stripped on way down
and deposited in CDS or close to CDS boundary
- Contamination and toxicity levels
assessed / approved before disposal
- Assessments involves
- contaminant levels
- bioavailability (elutriate testing)
- species toxicity
- Assessment compared against
published ANZEEC guideline values
- Sediments concentrations that do not
pass assessment(s) not permitted to be disposed off at site
Characteristics of Disposal Site
17
Far field modelling output Near Field Modelling - Depth of deposition (microns) Note that the colour bar scale is a logarithm scale −1 and −2 equate to thicknesses of 0.1 and 0.01 mm, respectively.
Capital Dredging Summary of Submissions
18
Main Points Raised in Submissions
19
- Lack of Consultation
- Impacts on the Environment
- Impacts on our Food Basket (from disposal)
- Duration of Consent
- Alternatives to Disposal / Beneficial Reuse
- Transit of material through Hauraki Gulf / Emergencies
Consultation
20
- POAL has engaged with wide cross
section of mana whenua and stakeholders to date
- POAL requested notification of
dredging consent
- POAL is keen to listen to
stakeholders and address concerns where we can
Unitary Plan Port and Navigation Precincts
Environmental Concerns
21
Key topics raised:
- Nature of material and levels of contamination
- Increased sedimentation and effects on marine environment
- Effects of sediment on water clarity and on marine life (e.g. on snapper)
- Effects on coastal birds
- Effects on marine mammals
- Biosecurity
Capital Dredged Material Characteristics
22
- Material is sediment that filled the historic river
valley when sea level rose after the last ice age. All but surface sediments pre-human.
- Surface material ranges from very shelly to muddy
sand and sandy mud
- Below surface - material consolidated less water
content
- Some subsurface siltstone and Parnell grit at south
bend of channel
RC-E-236B RC-B-108B Subsurface sediments in the Rangitoto Channel
Sediment Contamination
23
- POAL has examined sediment quality in
channel in 2001 and 2019.
- Channel remote from any direct sources of
contamination.
- Most of the sediment is subsurface and
expected to be uncontaminated.
- Some common urban contaminants can be
identified (lead, PAHs etc.) in the surface sediment.
- Concentrations are all lower than ANZECC
(2018) guidance values with exception two subsamples in FN berth approaches that contained TBT.
- Consistent levels of contamination over
time - Lead levels decreasing.
Sediment Contamination
24
- No waterborne toxicity expected based on 2019 tests and previous waterfront elutriate
testing
- EPA still requires further testing for any disposal at CDS and must approve sampling plan
before sampling and testing
- Additional sampling for EPA will involve:
― Coring / samples collected randomly across full depth of dredging ― More analysis for trace elements ― Analysis for persistent organics ― Analysis for TBT particularly focused at FN berth due to results to-date ― Additional elutriate testing if required ― Toxicity testing if required
- Results reviewed by EPA prior to approving material suitable for disposal at sea
Impacts on Marine Life (sedimentation)
25
- During dredging sedimentation of coarse material
- ccurs adjacent to dredge and silt and clays settle in
the far-field.
- Much of the “adjacent” sedimentation in channel will
be dredged or will have just been dredged.
- Sedimentation plates put in for 2004-2007 dredging,
no sediment build up detected.
3 4 5 6 8 Transport path
- f fines on flood
& ebb tide Depositional zones
Inferred transport pathways and depositional zones
- f fine material (< 0.062mm)
Dredging at FNB – 1 year sedimentation Dredging at north end channel – 1 year sedimentation
Water Clarity)
26
- Water clarity in Hauraki Gulf improves with
distance from land
- Total Suspended Solids (TSS) is a good
proxy
- In lower Harbour TSS 9 mg/L. In the
Rangitoto Channel TSS median 10.6 to 11.6 mg/L at three sites (similar to average of 7.2 mg/L measured in 2003-2008)
- TSS in the channel also varies with the tide
state (velocity) with + 10 mg/L change during the spring tide
Water Clarity)
27
- Dredging releases some sediment
- Modelling of sediment plumes (examples
plots shown) showed that TSS reached +32 mg/L close to dredger and +5 mg/L 200 m down current
- TSS monitoring of 2003–2008 dredging
showed average TSS of 7.2 mg/L (range <3-18.6 mg/L)
- Monitoring range within the natural range
– 10.6-11.6 mg/L + 10mg/L spring tide
Water Clarity
28
- Snapper is a key fish in the gulf, well studied
with data on distribution of eggs and larvae
- Eggs are tolerant of TSS*
- Snapper larvae are visual and selective
feeders (copepod nauplii). Larvae settle in estuarine areas (biogenic). 12 hr LC50 = 157
- r 2,020 mg/L (open or closed mouth stage
- f development)
- TSS >50 mg/L decrease larvae feeding rates.
Prediction of a “first observable effect” on larvae feeding at 4 or 150 mg/L (however, larvae still had yolk sack). Natural concentrations + dredging at lower end of predicted threshold
* Partridge & Michael (2010) Jnl. Fish Biology 77:227-240.
Impacts on Marine Life (benthic)
- verall)
)
29
- Over the duration of dredging, a
patchwork loss of benthic fauna and recolonisation will occur
- Areas dredged early will be reforming
benthic assemblages during the dredging period
- Based on work undertaken up to
2013, the shelly areas dredged in 2004-2007 have reformed communities similar to those present before dredging started
- Effects of far-field sedimentation are
not expected as the areas (away from the channel) are depositional and muddy
Impacts on Marine Life (birds) )
30
- A range of coastal birds use the lower harbour, Rangitoto
Channel and approaches
- This area is well traversed by ships, ferries and recreation craft
- Some species breed in proximity of channel (terns, gulls etc.)
- Some are surface feeders, others plunge divers (terns, gannets
etc.) feeding on baitfish, zooplankton etc.
- Some are local breeding, some visitors.
- Areas of turbid seawater are localised
- Noise in channel from dredging not considered to be
environmentally significant
Impacts on Environment (mammals) )
31
- Marine mammals transit the Navigation Precinct.
- Marine mammal presence frequency is low.
- Higher for small mammals (dolphin species) but
very low for larger mammals (e.g. Bryde’s whale, Orca).
- Dredging undertaken while stationary (minimal
moving collision risk as vessel speeds are low).
- Same method of dredging has been carried out
without spotters for many years with no incidents.
- Spotters will be used during disposal at the CDS.
- Noise in channel from dredging minimal. Not
considered to be environmentally significant.
Impacts on Environment (biosecurity) )
32
- Channel precinct is surveyed every six months.
- Extended sampling done for application.
- There are fewer invasive species within the channel
than in inshore/intertidal areas of the Waitematā.
- MPI reviewed biosecurity assessment (as part of
disposal application to EPA).
- Any factors that change species present/biosecurity risk
require reassessment and communication with EPA (Disposal condition).
- Re-assessment is required as part of each approved
sampling plan.
- MPI review every assessment and need to give their
approval.
Impacts on Environment (biosecurity)
Re-use of shell hash
- There are potential re-use options for shell
hash for biogenic habitat creation.
- The hash is intended for use primarily
within the Waitematā Harbour.
- Sabella (fan worm) is a notifiable organism
(Biosecurity Notifiable organism) order 2016).
- This controls the movement of shell hash
- ut of the Waitemata Harbour (Section 46
- f the Biosecurity Act).
33
Duration of Consent )
34
- Capital Dredging consent sought for 15 years
- Maintenance dredging to maintain new depths sought for 35 years
- Dredging only to be undertaken as needed.
- Staged to reduce impacts, cost and provide flexibility.
- Timed to meet expected deployment of larger ships to NZ market.
- Duration consistent with previous capital dredging consent.
Alternative Disposal Options
35
- POAL has experience with dredge
material reuse (past 20 years)
- Successfully developed “mudcrete”
product used in Viaduct and Fergusson reclamations.
- Established Disposal Options Advisory
Group (DOAG) in 1990s.
- Involved wide variety of stakeholders.
- Canvassed all available options at the
time. DOAG Recommendations:
- Preferred option - use in land reclamation
- Second option – disposal in waters
deeper that 100m
Alternative Disposal Options
36
- POAL reviewed options again for EPA
disposal application
- DOAG options still valid but along with
sea disposal POAL looking for alternatives
- Opportunities for reuse include:
- Reclamation (by others), marine
stabilisation, shore stabilisation, shore protection, land uplift (sea level rise), infill and ground engineering.
- Unsuitable material (for marine disposal)
can be mudcreted for infill or go to landfill.
- POAL discussing options with number
- f potential users
37
Any new location will require major development with significant environmental impact:
- Dredging & disposal
- Reclamation and new berths
- New roads
- New rail
- New township & business park
around port Northport a particularly poor option:
- Too small to accommodate POAL’s
existing cargo streams
- 570 metre berth vs 3,000 metres
- Extensive development required in
harbour with high ecological value
- Remote location: very high carbon
footprint for transport of freight to Auckland ~10x existing emissions.
Dredging POAL (Mm3) Northport1
(Mm3)
Channel 2.25 3.7 Approaches / Berths 0.25 1.2 Maintenance Dredging 75,000 m3 over 5 years 120,000 m3
- ver 2 years
1 Preliminary volumes based on Refinery NZ channel deepening consent
and calculation of dredging required for existing Northport expansion plan.
Future Port Location
38
- Current limit is lightly laden Suezmax – 275m long, 14.5m draft.
- Northport needs significant under keel clearance due to swells
- Northport’s website states ‘a few vessels have been loading to deeper drafts (approximately 14.5m /
14.7m) but have been waiting at anchor, sometimes up to a week for windows of opportunity based
- n favourable weather / swell conditions, before being able to berth’.
- 3.7 million m3 of dredging required for deeper draft Suezmax tankers to the Oil Refinery. Likely to
be >5 million m3 for Post Panamax containerships to Northport.
Northport / Marsden Refinery
Questions and Answers
39