zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA Airport Sponsor - - PowerPoint PPT Presentation

zyxwvutsrqponmlkjihgfedcbazyxwvutsrqponmlkjihgfedcba
SMART_READER_LITE
LIVE PREVIEW

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA Airport Sponsor - - PowerPoint PPT Presentation

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA Airport Sponsor Informational Briefing New York Airport Sponsors Presented to: New York Airports District Office By: October 15, 2019 Date:


slide-1
SLIDE 1

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

Presented to: By: Date:

Airport Sponsor Informational Briefing

New York Airport Sponsors

New York Airports District Office October 15, 2019

slide-2
SLIDE 2

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

Overview

  • Introduction
  • FY 2020 AIP Funding
  • Grant Activity
  • SAM’s/Delphi
  • FAA Order 5090.5

Update

October 15, 2019 Airport Sponsor Informational Briefing

2

slide-3
SLIDE 3

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

~

Federal Aviation

~

Administration

FY 2020 AIP Funding

  • Fiscal Year 2020 Appropriations

– Expired on September 30, 2019 – Continuing Resolution through November 21, 2019

October 15, 2019 Airport Sponsor Informational Briefing

3

slide-4
SLIDE 4

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

~

Federal Aviation

~

Administration

FY 2020 AIP Funding Continued

  • Sponsor’s Proposed FY 2020 Projects

– Already Moving Forward – Continued Coordination with ADO Project Manager – Pre-Applications – Due 1/30 – Eligibility of projects – Determination by 12/1 – Consistency of project narratives between pre-applications & final application

October 15, 2019 Airport Sponsor Informational Briefing

4

slide-5
SLIDE 5

~

Federal Aviation

~

Administration zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

Grant Activity

  • Grant Drawdowns
  • Amendment Requests

– Early Spring

  • Closeout Package Submission

– Send to Christine Sanchez, include PM – Review/Paid and closed by July/August deadline

October 15, 2019 Airport Sponsor Informational Briefing

5

slide-6
SLIDE 6

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

~

Federal Aviation

~

Administration

SAM’s/Delphi

  • SAM’s & Delphi information should be the same

– Experienced issues in FY19 – Delays issuance of grant and payments made on grant

  • SAM’s

– Keep current – Provide Omi Thomas with PDF once updated

  • Delphi

– Closes at the end of each month for 3-4 days

October 15, 2019 Airport Sponsor Informational Briefing

6

slide-7
SLIDE 7

FAA Order 5090.5

  • Formulation of the NPIAS and ACIP Order

– https://www.faa.gov/airports/planning_capacity/npias _acip_order/ – Date Issued: September 3, 2019. – Combined the NPIAS and ACIP orders into a single document. – Revised work codes and NPR values.

October 15, 2019 Airport Sponsor Informational Briefing

7

slide-8
SLIDE 8

Planning Dates - 1

Date Actions

September 2019 – November 2019 The ADO and sponsor hold FY20-24 CIP meetings NOTE: FY20 adjustments will typically be limited to deletions or cost adjustments and not the addition

  • f new projects.

December 1, 2019 Determination of eligibility made by ADO based on documentation submitted by September 30, 2019 (including 1542 certifications and negotiated land agreements). A formal letter or email will be provided by the respective team member approving the request.

October 15, 2019 Airport Sponsor Informational Briefing

8

slide-9
SLIDE 9

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

Planning Dates - 2

Date Actions

December 1, 2019 For FY20, submit Construction Plans and Specification and Construction Safety and Phasing Plans (CSPP) (for single review projects) at 90% completion for formal review. For CSPP complex projects that require multiple reviews, discussions with the ADO will be required (see ARP SOP 1.00 for further guidance). December 15, 2019 Sponsor submits FY21-25 CIP update request to ADO, including: A CIP data sheet for FY21-23 projects only. Include a sketch of all the projects referencing the ALP. Updates to the ALP (if necessary).

October 15, 2019 Airport Sponsor Informational Briefing

9

slide-10
SLIDE 10

Planning Dates - 3

Date Actions

December 31, 2019 Sponsor submits year-end financial reports (due 90 days after the end of each of the FAA’s fiscal year) to summarize grant expenditures and the status of project funds per the AIP Grant Payment and Sponsor Financial Reporting Policy, Section 9 (PDF). SF-425 – Federal Financial Report SF-271 – Outlay Report and Request for Reimbursement for Construction Program SF-270 – Request for Advance or Reimbursement (non-construction projects)

October 15, 2019 Airport Sponsor Informational Briefing

10

slide-11
SLIDE 11

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

Planning Dates - 4

Date Actions

January 31, 2020 Sponsor submits FY20 grant pre-application(s) based on estimates. Eligibility determination letter/email will need to be included as part of the pre- application. March 1 – June 1, 2020 Submission of Bid Tabulations to ADO requesting ADO Concurrence to Award. NOTE: It is recommended the contractor be able to hold the bid through September 2019. April 15, 2020 Sponsor confirms intent to use available entitlements to the ADO. (Final Date provided by Federal Register Notice)

October 15, 2019 Airport Sponsor Informational Briefing

11

slide-12
SLIDE 12

A

~

Federal Aviation

~

Administration zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

Questions?

October 15, 2019 Airport Sponsor Informational Briefing

12

slide-13
SLIDE 13

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

~

Federal Aviation

~

Administration

Thank You

October 15, 2019 Airport Sponsor Informational Briefing

13