York Region Rapid Transit Corporation Markham Development Services Committee Update | September 25, 2012 May 3, 2012 YRRTC Board Meeting 0 0 transformation unfolding 1 how the rapidway works 2 construction in west section 3 canopies H3


slide-1
SLIDE 1

May 3, 2012 YRRTC Board Meeting

York Region Rapid Transit Corporation

Markham Development Services Committee Update | September 25, 2012

slide-2
SLIDE 2

1

transformation unfolding

slide-3
SLIDE 3

2

how the rapidway works

slide-4
SLIDE 4

3

construction in west section

slide-5
SLIDE 5

4

canopies

H3 – Canopies

slide-6
SLIDE 6

5

urban transformation

H3 – Tree Planters

slide-7
SLIDE 7

6

boulevard pavers

H3 – Boulevard Pavers

slide-8
SLIDE 8

7

construction in the east section

slide-9
SLIDE 9

8 H3 – Widening Corridor

slide-10
SLIDE 10

9

staging options

Cedarland Boulevard facing east from Warden Avenue South Town Centre Boulevard facing north toward Highway 7

slide-11
SLIDE 11

south town centre boulevard work april to september 2013

slide-12
SLIDE 12

11

south town centre boulevard streetscape

South Town Centre Blvd

slide-13
SLIDE 13

Warden Avenue [northbound]

cedarland drive work

  • ctober 2012 to february 2013
slide-14
SLIDE 14

cedarland drive streetscape

Cedarland Dr

slide-15
SLIDE 15

14

warden bridge work september 2012 to spring 2013

Warden Avenue facing south

slide-16
SLIDE 16

15

warden avenue completed streetscape

Warden Ave

slide-17
SLIDE 17

16

Highway 7 Paving Plan

slide-18
SLIDE 18

17 17

  • verview

› Hwy. 7 – from Doncrest Rd. to East Beaver Creek Rd. › September 17 to mid-November (Oct. 5-8 excluded) › Multiple lane and partial intersection closures will take place on

weeknights and weekends

› Grinding and milling on weeknights › Base layer paving on weekends › North side first then the south › Hours of work:

› Monday to Thursday: 8pm to 6am › Friday 8pm to Monday 6am

slide-19
SLIDE 19

18

Doncrest to Rockwell

CONSTRUCTION AREA

WEEK

1

18

Full Closure Entrance Closed

slide-20
SLIDE 20

19 19

Rockwell to Valleymede

CONSTRUCTION AREA

WEEK

2

Full Closure Entrance Closed

slide-21
SLIDE 21

20 20

Valleymede to West Beaver Creek

CONSTRUCTION AREA

WEEK

3

Full Closure Entrance Closed

slide-22
SLIDE 22

21

West Beaver Creek to East Beaver Creek

CONSTRUCTION AREA

WEEK

4

Full Closure Entrance Closed

slide-23
SLIDE 23

22 YRRTC Board Meeting 22

Doncrest to Saddlecreek

CONSTRUCTION AREA

WEEK

5

Full Closure Entrance Closed

slide-24
SLIDE 24

23 23

Saddlecreek to Commerce Valley Drive W

CONSTRUCTION AREA

WEEK

6

Full Closure Entrance Closed

slide-25
SLIDE 25

24 24

Commerce Valley Drive W to Commerce Valley Drive E

CONSTRUCTION AREA

WEEK

7

Full Closure Entrance Closed

slide-26
SLIDE 26

25 25

keeping you informed

› Bulletin › Bilingual notice › News release and traffic advisory › Radio and print ads › Posters › Roadside electronic

billboard and construction detour signage

› Social media and web updates › Personal contact from

Community Liaison Specialist

slide-27
SLIDE 27

26

supporting businesses along Highway 7

slide-28
SLIDE 28

27

Thank you…