yale science building
play

Yale Science Building Town Hall Meeting September 21, 2017 Project - PowerPoint PPT Presentation

Yale Science Building Town Hall Meeting September 21, 2017 Project Site Logistics Sept. Dec. 2017 Pavilion Project Site Logistics Jan. 2018 to Mar. 2019 Pavilion Project Schedule Site excavation for new building completes


  1. Yale Science Building Town Hall Meeting September 21, 2017

  2. Project Site Logistics Sept. – Dec. 2017 Pavilion

  3. Project Site Logistics Jan. 2018 to Mar. 2019 Pavilion

  4. Project Schedule • Site excavation for new building completes mid-October (2 shifts working from 7am-10pm will continue until excavation is complete) • Concrete foundations began mid-July. • Pipe Installation at KGL roadway mid-October 2017 (Weekends). Steam & Chilled Water Shutdowns will take place in spring of 2018. • Steel erection will begin next week working toward topping off at the end of January 2018. • Curtainwall installation scheduled to begin at the end of January 2018.  Dates are weather permitting and subject to change  Noise and vibration impacts will be minimized, monitoring vibration throughout science hill, no blasting.

  5. Pedestrian Access Paths

  6. Get YSB Construction Updates

  7. Questions & Contacts Visit the YSB project website at http: / / yalesciencebuilding.yale.edu/ Sheri Miller Associate Director Project Management & Construction Yale University Office of Facilities sheri.miller@yale.edu

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend