Yale Science Building

Town Hall Meeting September 21, 2017

slide-2
SLIDE 2

Project Site Logistics Sept. – Dec. 2017

Pavilion

slide-3
SLIDE 3

Project Site Logistics Jan. 2018 to Mar. 2019

Pavilion

slide-4
SLIDE 4

Project Schedule

  • Site excavation for new building completes mid-October (2 shifts

working from 7am-10pm will continue until excavation is complete)

  • Concrete foundations began mid-July.
  • Pipe Installation at KGL roadway mid-October 2017 (Weekends).

Steam & Chilled Water Shutdowns will take place in spring of 2018.

  • Steel erection will begin next week working toward topping off at

the end of January 2018.

  • Curtainwall installation scheduled to begin at the end of January

2018.

  • Dates are weather permitting and subject to change
  • Noise and vibration impacts will be minimized, monitoring vibration throughout science hill, no blasting.
slide-5
SLIDE 5

Pedestrian Access Paths

slide-6
SLIDE 6

Get YSB Construction Updates

slide-7
SLIDE 7

Questions & Contacts

Visit the YSB project website at

http: / / yalesciencebuilding.yale.edu/

Sheri Miller Associate Director Project Management & Construction Yale University Office of Facilities sheri.miller@yale.edu