wrf airport w rf phase 1 expansion
play

( WRF ) Airport W RF Phase 1 Expansion Process Upgrades and - PDF document

Presentation No. 3 1 October 23, 2012 City Council ( WRF ) Airport W RF Phase 1 Expansion Process Upgrades and Capacity Increase to 3.75 MGD Design Milestones Remaining Tasks Major Project Components Construction


  1. Presentation No. 3 1 October 23, 2012 City Council ( WRF )

  2. Airport W RF Phase 1 Expansion Process Upgrades and Capacity Increase to 3.75 MGD • Design • Milestones • Remaining Tasks • Major Project Components • Construction Budget • CMAR Cost Proposal Breakdown • Project Budget and Financing 2

  3. Final Design Operations and Maintenance Existing Facilities Building -Oxidation Ditches/ Equalization Basins -Clarifier / Thickener Blower/Chemical/ -Operations Building Electrical Building /Lab and Chlorine -Centrifuge Building Contact Basin -Recharge Basins -Airpark Tank / Convert to RW Clarifiers Headworks and Aeration Basins 3

  4. Airport W RF Phase 1 Milestones 30% Design Submittal Sep 30, 2011 60% Design Submittal Jan 30, 2012 90% Design Submittal Jun 22, 2012 ADEQ Permit Submittal Aug 2012 100% Submittal Sept 2012 Final Design Documents Oct 2012 Guaranteed Maximum Price Oct 2012 Construction Begins Nov 2012 Construction Completed Fall 2014 4

  5. Airport W RF Phase 1 Expansion Rem aining Tasks • Noise and Odor Easement Acquisition • Permits to be Obtained o ADEQ (Operating) Aquifer Protection Permit o ADWR Underground Storage Facility Permit (USF) o City of Prescott • Utility Coordination o Gas o Electric o (3 rd party utility extension costs, e.g. electric and gas services, not included in cost model) 5

  6. Phase 1 Major Project Com ponents The project will produce Class A+ effluent and includes the following major components: • Influent Piping and Headworks Facilities (Screens and Grit Removal) • EQ Basins (Ox Ditches) 1.2 Mgal • Two Bioreactors/ Aeration Basins • Two Clarifiers • Pumps Stations o RAS – 3.75 MGD, EQ – 4 MGD, Effluent - 12 MGD • Filters 6

  7. Major Project Com ponents ( cont’d) • Disinfection o On-site Generation o Chlorine Contact Tank 235,000 gal • Effluent Water Tank and Piping • Yard Piping 17,885 lf • Blower/ Chemical/ Electrical (BCE) Building 11,000 sf • Solids Thickening and Dewatering o Convert Existing Clarifier o Add a Second, Larger Centrifuge • Operations and Maintenance Buildings 7

  8. Construction Manager at Risk ( CMAR) Construction Budget  Master Plan Construction Budget $36,207,612  30% Cost Model $32,939,000  60% Cost Model $34,864,146  Final GMP $34,787,006  Owner’s Contingency $ 500,000  Construction Contract Total $35,287,006 Standby Generator (Separate Purchase) $544,000 8

  9. CMAR Cost Proposal Breakdow n  Bid Packages – Tw enty – Largest Bid – Electrical/ I&C $6,815,500 – Local Contractors (14) $2,884,244 – Other Contractors $2,685,079  Sub Total $ 1 2 ,3 8 4 ,8 2 3  Major Materials & Suppliers – Permanently Installed Equipment $4,056,506 – Pipe Materials $3,031,007 – Concrete and Aggregates (Local) $1,292,803 – Misc. Other Materials & Supplies $ 389,073  Sub Total $ 8 ,7 6 9 ,3 8 9  I nstallation Labor, Equipm ent & Minor Materials – General Requirements $ 515,187 – Yard Pipe - 17,885 lf $1,203,182 – Site Work $ 229,882 – Concrete Forming and Placing – 9,670 cy $3,044,552  Other Work $1,149,195  Sub Total $ 6 ,1 4 1 ,9 9 8 9

  10. CMAR Cost Proposal Breakdow n ( cont’d)  Fixed and Variable Expenses – Projected Staff/ Labor $1,723,549 – Taxes $1,408,806 – Insurance and Bonds $ 927,747 – Temporary Facilities, Equipment Costs and Other Project Expenses $1,102,061  Landscaping, Odor Control and Furniture $ 35,000  Sub Total $ 5 ,1 9 7 ,1 6 4  CMAR FEE $ 2 ,2 9 3 ,6 3 2  CMAR GUARANTEED MAXI MUM PRI CE $ 3 4 ,7 8 7 ,0 0 6  OW NERS CONTI NGENCY $ 5 0 0 ,0 0 0  CONSTRUCTI ON CONTRACT AMOUNT $ 3 5 ,2 8 7 ,0 0 6 10

  11. Overall Project Budget Fee Description Fee CMAR GMP $34,787,006 Standby Generator (Purchased by City directly and $544,000 Installed by CMAR) Owner’s Contingency $500,000 Engineering Design and Construction Management $5,300,000 Land Acquisition Including Easements $500,000 CMAR Pre Construction Contract $382,000 APS Electric Construction $30,000 UniSource Gas Construction $96,743 ADEQ Permitting $75,000 City of Prescott Permitting $172,675 3 rd Party CMAR Cost Model Audit $19,900 City Personnel Costs $200,000 Total Cost Estimate $42,607,324 11

  12. Financing of Phase 1 Expansion  August 31, 2010 – City Council adopted Resolution No. 4041-1111 authorizing an application to the Arizona Water Infrastructure Financing Authority (WIFA) for project financing  April 26, 2011 – City Council adopted Ordinance No. 4784-1135 authoring a WIFA loan for a 20 year term at an interest rate of 3%

  13. Airport W RF Phase 1 City Council Comments/Questions 13 13

  14. I ncreased W W Strength I m pacts Existing Plant Capacity Existing 450 Conditions Existing 400 Conditions 350 300 Biochemical 250 Oxygen Demand Design 200 Design Conditions (mg/L) Conditions 150 W aste 100 W aste 50 Concentration Concentration 0 has Nearly has Nearly Sundog WWTP Airport WRF Tripled Tripled Existing Conditions Existing Conditions Design Design Conditions Conditions

  15. Current Airport W RF Capacity Capacity Modeled Existing Design Capacity

  16. Current Sundog W W TP Capacity 7 Design Capacity 6 5 Existing Treatment 4 Capacity, mgd Existing Modeled Capacity 3 2 1 0 Preliminary Biological Secondary Filtration Disinfection Thickening Digestion Dewatering Treatment Treatment Clarification

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend