( WRF ) Airport W RF Phase 1 Expansion Process Upgrades and - - PDF document

wrf airport w rf phase 1 expansion
SMART_READER_LITE
LIVE PREVIEW

( WRF ) Airport W RF Phase 1 Expansion Process Upgrades and - - PDF document

Presentation No. 3 1 October 23, 2012 City Council ( WRF ) Airport W RF Phase 1 Expansion Process Upgrades and Capacity Increase to 3.75 MGD Design Milestones Remaining Tasks Major Project Components Construction


slide-1
SLIDE 1

1 City Council Presentation No. 3 October 23, 2012

(WRF)

slide-2
SLIDE 2

2

Airport W RF Phase 1 Expansion

Process Upgrades and Capacity Increase to 3.75 MGD

  • Design
  • Milestones
  • Remaining Tasks
  • Major Project Components
  • Construction Budget
  • CMAR Cost Proposal Breakdown
  • Project Budget and Financing
slide-3
SLIDE 3

3

Final Design

Headworks and Aeration Basins Blower/Chemical/ Electrical Building and Chlorine Contact Basin Clarifiers Existing Facilities

  • Oxidation Ditches/

Equalization Basins

  • Clarifier / Thickener
  • Operations Building

/Lab

  • Centrifuge Building
  • Recharge Basins
  • Airpark Tank /

Convert to RW Operations and Maintenance Building

slide-4
SLIDE 4

4

Airport W RF Phase 1 Milestones

30% Design Submittal Sep 30, 2011 60% Design Submittal Jan 30, 2012 90% Design Submittal Jun 22, 2012 ADEQ Permit Submittal Aug 2012 100% Submittal Sept 2012 Final Design Documents Oct 2012 Guaranteed Maximum Price Oct 2012 Construction Begins Nov 2012 Construction Completed Fall 2014

slide-5
SLIDE 5

5

Airport W RF Phase 1 Expansion Rem aining Tasks

  • Noise and Odor Easement Acquisition
  • Permits to be Obtained
  • ADEQ (Operating) Aquifer Protection Permit
  • ADWR Underground Storage Facility Permit (USF)
  • City of Prescott
  • Utility Coordination
  • Gas
  • Electric
  • (3rd party utility extension costs, e.g. electric and

gas services, not included in cost model)

slide-6
SLIDE 6

Phase 1 Major Project Com ponents

The project will produce Class A+ effluent and includes the following major components:

  • Influent Piping and Headworks Facilities (Screens

and Grit Removal)

  • EQ Basins (Ox Ditches)

1.2 Mgal

  • Two Bioreactors/ Aeration Basins
  • Two Clarifiers
  • Pumps Stations
  • RAS – 3.75 MGD, EQ – 4 MGD, Effluent - 12 MGD
  • Filters

6

slide-7
SLIDE 7

Major Project Com ponents ( cont’d)

  • Disinfection
  • On-site Generation
  • Chlorine Contact Tank

235,000 gal

  • Effluent Water Tank and Piping
  • Yard Piping

17,885 lf

  • Blower/ Chemical/ Electrical

(BCE) Building 11,000 sf

  • Solids Thickening and Dewatering
  • Convert Existing Clarifier
  • Add a Second, Larger Centrifuge
  • Operations and Maintenance Buildings

7

slide-8
SLIDE 8

Construction Manager at Risk ( CMAR) Construction Budget

  • Master Plan Construction Budget $36,207,612
  • 30% Cost Model

$32,939,000

  • 60% Cost Model

$34,864,146

  • Final GMP

$34,787,006

  • Owner’s Contingency

$ 500,000

  • Construction Contract Total

$35,287,006 Standby Generator (Separate Purchase) $544,000

8

slide-9
SLIDE 9

CMAR Cost Proposal Breakdow n

  • Bid Packages – Tw enty

– Largest Bid – Electrical/ I&C $6,815,500 – Local Contractors (14) $2,884,244 – Other Contractors $2,685,079

  • Sub Total

$ 1 2 ,3 8 4 ,8 2 3

  • Major Materials & Suppliers

– Permanently Installed Equipment $4,056,506 – Pipe Materials $3,031,007 – Concrete and Aggregates (Local) $1,292,803 –

  • Misc. Other Materials & Supplies

$ 389,073

  • Sub Total

$ 8 ,7 6 9 ,3 8 9

  • I nstallation Labor, Equipm ent & Minor Materials

– General Requirements $ 515,187 – Yard Pipe - 17,885 lf $1,203,182 – Site Work $ 229,882 – Concrete Forming and Placing – 9,670 cy $3,044,552

  • Other Work

$1,149,195

  • Sub Total

$ 6 ,1 4 1 ,9 9 8

9

slide-10
SLIDE 10

CMAR Cost Proposal Breakdow n ( cont’d)

  • Fixed and Variable Expenses

– Projected Staff/ Labor $1,723,549 – Taxes $1,408,806 – Insurance and Bonds $ 927,747 – Temporary Facilities, Equipment Costs and Other Project Expenses $1,102,061

  • Landscaping, Odor Control and Furniture

$ 35,000

  • Sub Total

$ 5 ,1 9 7 ,1 6 4

  • CMAR FEE

$ 2 ,2 9 3 ,6 3 2

  • CMAR GUARANTEED MAXI MUM PRI CE

$ 3 4 ,7 8 7 ,0 0 6

  • OW NERS CONTI NGENCY

$ 5 0 0 ,0 0 0

  • CONSTRUCTI ON CONTRACT AMOUNT

$ 3 5 ,2 8 7 ,0 0 6

10

slide-11
SLIDE 11

11

Overall Project Budget

Fee Description Fee CMAR GMP $34,787,006 Standby Generator (Purchased by City directly and Installed by CMAR) $544,000 Owner’s Contingency $500,000 Engineering Design and Construction Management $5,300,000 Land Acquisition Including Easements $500,000 CMAR Pre Construction Contract $382,000 APS Electric Construction $30,000 UniSource Gas Construction $96,743 ADEQ Permitting $75,000 City of Prescott Permitting $172,675 3rd Party CMAR Cost Model Audit $19,900 City Personnel Costs $200,000 Total Cost Estimate $42,607,324

slide-12
SLIDE 12

Financing of Phase 1 Expansion

  • August 31, 2010

– City Council adopted Resolution No. 4041-1111 authorizing an application to the Arizona Water Infrastructure Financing Authority (WIFA) for project financing

  • April 26, 2011

– City Council adopted Ordinance No. 4784-1135 authoring a WIFA loan for a 20 year term at an interest rate of 3%

slide-13
SLIDE 13

13

Airport W RF Phase 1

13

City Council Comments/Questions

slide-14
SLIDE 14

I ncreased W W Strength I m pacts Existing Plant Capacity

50 100 150 200 250 300 350 400 450 Sundog WWTP Airport WRF Biochemical Oxygen Demand (mg/L)

Existing Conditions Existing Conditions Existing Conditions Existing Conditions Design Conditions Design Conditions Design Conditions Design Conditions

W aste Concentration has Nearly Tripled W aste Concentration has Nearly Tripled

slide-15
SLIDE 15

Current Airport W RF Capacity

Design Capacity Existing Modeled Capacity

slide-16
SLIDE 16

Current Sundog W W TP Capacity

1 2 3 4 5 6 7

Preliminary Treatment Biological Treatment Secondary Clarification Filtration Disinfection Thickening Digestion Dewatering

Existing Treatment Capacity, mgd

Design Capacity Existing Modeled Capacity