Working Group Wednesday, 29 th June, 2016 UR Offices Belfast - - PowerPoint PPT Presentation

working group
SMART_READER_LITE
LIVE PREVIEW

Working Group Wednesday, 29 th June, 2016 UR Offices Belfast - - PowerPoint PPT Presentation

Retail Markets Co-Ordination Working Group Wednesday, 29 th June, 2016 UR Offices Belfast ReMCoDS Retail Markets Co-Ordination Design Service 29 th June 2016 ReMCoWG Agenda Agenda Item Presenter Time 12:45 12:50 Introduction Jessica


slide-1
SLIDE 1

Retail Markets Co-Ordination Design Service ReMCoDS

Retail Markets Co-Ordination Working Group

Wednesday, 29th June, 2016 UR Offices Belfast

29th June 2016

slide-2
SLIDE 2

Retail Markets Co-Ordination Design Service ReMCoDS

ReMCoWG Agenda

Agenda Item Presenter Time

Introduction Jessica Gregory, ReMCoDS 12:45 – 12:50 ReMCoSG Meeting Feedback Jessica Gregory, ReMCoDS 12:50 – 12:55 ReMCoWG Action Items Jessica Gregory, ReMCoDS 12:55 – 13:00 Tibco Hub/EMMA Update John Bracken, ESBN 13:00 – 13:10 Smart Metering Update Alan Keegan, CER 13:10 – 13:20 Market Design Update Jessica Gregory, ReMCoDS 13:20 – 13:35 ReMCoWG To-Do List Review Jessica Gregory, ReMCoDS 13:35 – 13:40 AOB & Closing Jessica Gregory, ReMCoDS 13:40 – 13:45

29th June 2016

All participants are kindly requested to mute their phones when dialled into the forum conference call

slide-3
SLIDE 3

Retail Markets Co-Ordination Design Service ReMCoDS

Approval of Minutes

Minutes from ReMCoWG meeting 4th May 2016

29th June 2016

slide-4
SLIDE 4

Retail Markets Co-Ordination Design Service ReMCoDS

ReMCoSG Update

SG Meeting held on 25th May 2016.

Next SG on 24th August 2016. 29th June 2016

Topic Detail Status Smart Metering

  • Final Policy drops re Smart metering have been made by CER
  • Engagement with ESBN in relation to the co-ordinated planning exercise and the impact that TIBCO delays

and wider retail programme of work may have on SM delivery dates. Revised dates are hoped to be delivered mid July 2016.

  • Smart Metering cutover was originally proposed to be mid 2019. CER recognise that based on items falling
  • ut of the co-ordinated planning exercise that this is not feasible and revised dates will be provided.

105 Incorporating Smart changes into the Co-Ordinated Retail Markets - this action is being retained as a standing item/placeholder pre-existing I-SEM

  • Extensive engagement between Meter Data Providers and Market Rules WG under I-SEM attempting to

identify proposed changes to all systems.

  • CER is recommending that changes should be kept to a minimum and attempt where at all possible to

minimise changes to the schema.

  • All parties are close to concluding that no schema changes for I-SEM project will be necessary. SAP/ Central

Market system changes are expected.

  • The I-SEM Eirgrid Team will be providing a set of Interface Specs to the Market on the 3rd June 2016 which

will specify the content of the format of the Interface Specs. TIBCO/Schema Programme J Bracken provided the ESBN/NIE Networks update.

  • The Project is on target with the Project Plan.
  • The Project Go-Live Date was discussed. The result of this discussion resulted in both RAs having no
  • bjection to the 5th August 2016 as the TIBCO Upgrade Go-Live date.
  • Update on status of RA review of report (and follow up answers to questions) provided by ESBN/NIE
  • Networks. All agreed to close action 134 as report had been produced and is now with CER/UR to make a

decision around future co-ordinated delivery programme schedule. See action 135. 134 TIBCO Upgrade Programme (TUP)– ESBN/NIE Networks to provide a report outlining the implications of the TUP Project delay on all other Retail market deliveries/projects closed 1 New Action was logged. Action 135: CER/UR to provide a decision around the future Co-ordinated Market Priorities and deliveries of such. 135 CER/UR to provide a decision around the future Co-ordinated Market Priorities and deliveries

  • f such.

New Action Item

slide-5
SLIDE 5

Retail Markets Co-Ordination Design Service ReMCoDS

ReMCoWG Action Items

  • No Actions were closed since last ReMCoWG meeting.
  • 2 New Actions opened at the last ReMCoWG & 1 Action carried Forward.

29th June 2016

AP No. Title

  • Org. Assigned to

Date Due

140 Disaster Recovery – ReMCoDS to issue a note to Suppliers requesting them to provide a contact name & details (email & phone no.) for the Disaster Recovery Meeting to be organised by Secure. Suppliers to respond to ReMCoDS with contact details. ReMCoDS/Suppliers 29/06/2016 141 ESBN/NIE Networks to request from Capita the process for MPs to follow when an MP needs to take their EMMA offline. RMDS to then issue this process to MPs ESBN/NIE Networks/RMDS 29/06/2016 142 ESBN/NIE Networks to produce a summary report describing the incident

  • f the Unplanned Outage due to Capita building loss of power.

ESBN/NIE Networks 29/06/2016

slide-6
SLIDE 6

29th June 2016

slide-7
SLIDE 7

7 esbnetworks.ie

Tibco Outages

TIBCO Upgrade Project

Start Date E nd Date Planned Contingency Invoked Comments 02/06/2016 14/06/2016 N Y Supplier Connectivity Issues 03/06/2016 03/06/2016 N Y Supplier Connectivity Issues 13/06/2016 15/06/2016 N Y Supplier DB issues 17/06/2016 27/06/2016 Y Y IP Address Changes 21/06/2016 21/06/2016 Y Y E lectron cutover 27/06/2016 27/06/2016 N Y Connection Issues

2 4 6 8 10 12 14 16 18 20 Jan Feb Mar Apr May Jun Number Month

Unplanned Outages 2016

slide-8
SLIDE 8

Capita Report

April 2nd Data Centre Power Failure Incident Update

slide-9
SLIDE 9

9 esbnetworks.ie

Incident Summary

Root Cause of failure

A site mains switch breaker failed to reclose in-sync with a generator switch breaker when the mains power had stabilised after a brief power fluctuation late on the evening of Friday 1st April. Despite the resilient power source (Generator) activating as designed and providing power through the night, the mechanical nature of the breaker fault resulted in false signals being sent to the SCADA monitoring system. Early on Saturday morning a false signal caused an “on-set” generator breaker to shut off the supply from the generator as a safety

  • precaution. This resulted in the Data Centre running on UPS batteries

until they were exhausted, culminating in a total shutdown.

slide-10
SLIDE 10

10 esbnetworks.ie

Initial Response

Problem Diagnosis

The investigating team identified the faulty mains breaker. Whilst the engineers were able to manually close the breaker to restore mains power, the recommendation from the engineers onsite was to replace the faulty breaker before restoring the mains power to the Data Centre systems, to ensure operational resilience.

Resolution Approach (Senior Management Team decisions)

As it was a weekend, there would be less impact on customers than during a normal working day. Instead of restoring power earlier in the day and following consultation with key customers, the decision was taken to delay the IT systems recovery until the faulty breaker was replaced. This negated the need for a further planned outage to replace the breaker. Decision taken to replace both the mains and the generator breakers, which took place

  • n Saturday afternoon. The IT technical staff worked throughout the rest of weekend to

successfully restore and test the systems for start of business on the Monday morning.

slide-11
SLIDE 11

11 esbnetworks.ie

Customer Impact

All key systems were subsequently restored, tested and operational with no data loss by start of business on Monday. There was minimal impact on the Tibco Market Messaging system The Reconciliation process identified 181 messages for RoI plus 10 for NI that had not been processed as a result of the outage on the TIBCO

  • hub. These were processed successfully on Monday. To put this into

perspective, there are approximately 130,000 messages processed across both jurisdictions on an average working day.

slide-12
SLIDE 12

12 esbnetworks.ie

Actions Update

Following the incident, Capita MITS has reviewed and implemented a number of service and process improvements to its internal and supplier support arrangements and maintenance schedules, including: -

– Out of Hours support and escalation – Preventative maintenance schedules – Monitoring/Alerting systems notifications

An independent external consultant has been appointed to conduct a technical review and assessment of the electrical distribution system and associated maintenance for the Hillview House site and Data

  • Centre. The resultant report will be issued and presented to Capita

MITS by the end of July. All recommendations from this review will be discussed and actioned appropriately.

slide-13
SLIDE 13

TIBCO Upgrade Project

slide-14
SLIDE 14

14 esbnetworks.ie

Project Phase

07/03 14/03 21/03 28/03 04/04 11/04 18/04 25/04 02/05 09/05 16/05 23/05 30/05 06/06 13/06 20/06 27/06 04/07 11/07 18/07 25/07 01/08 Aug/ Sep

Build Test EMMA s IPT PT OAT Regrn. Test KT Comm s Cutove r Hyper- care MCR

2.3.2 PT

Cycle 1, 2 & 3

2.3.3 SIT

2.3.3 ESBN PP EMMA

2.3.3 PT 1

Defect Res

2.3.3 Soak 2.3.3 Smart Supplier PT

Close PT

PT Sup Prep

Prod Ready 2.3.3 Prod deploy

2.3.2 & WebSphere to all Supplier EMMAs 2.3.3 Suppliers

Ready to commenc e IPT

Pre- IPT

Environment ready for PT

2.3.3 Packaged

IPT 2

DR3

Go-Live

5th – 7th August

Final Assurance Report CER/UR Project Go/No-Go Hard Freeze – Go- Live release signed off.

End Hypercare 16th September

2.3.3 SIT Deploy

KT

PT Prep MCR UAT / Regression

MCR DR3 MCR Go-Live 2.3.2 / 2.3.3 Pre-Prod Deploy ESBN Dev & IPT EMMA Build

Pre Ready

Pre-Prod Spec Upgrade

Supplier Ops Workshop Supplier Cutover Workshop Market Go-Live Date Agreed Supplier PT Closed Supplier PT Acceptance

OAT Re-Test

6 weeks to Cutover

Hypercare Support Model and Planning

MP EULAs Signed

slide-15
SLIDE 15

15 esbnetworks.ie

Item Comment/Update in terms of milestones & deliverables

Key Highlights Performance Test

  • Performance Test Exit Report draft issued

OAT

  • OAT Exit Report complete and signed off

Market Assurance

  • Pre-IPT2 completed without major incident
  • IPT2 commenced

Market Comms

  • Supplier Workshop on Tues 14th June delivered successfully
  • Progressing preparation for Supplier Cutover and Hypercare

Workshop on Tues 19th July Supplier Installs

  • Supplier Deployments complete

Update

slide-16
SLIDE 16

16 esbnetworks.ie

Item Comment/Update in terms of milestones & deliverables

This / Next Period Performance Test

  • Sign off on PT
  • Complete system tuning on To-be Production environment

Deployments

  • No expected further code release required

Market Comms

  • Market Communications will continue
  • Continue prep for Supplier Cutover & Hypercare workshop

(19th July) Market Assurance

  • Engagement with Market Assurance bodies to continue
  • Complete IPT2 phase (expected completion 8th July)

Next Period

slide-17
SLIDE 17

17 esbnetworks.ie

3 - High 4- Very High 5 - Urgent Deferred In Progress 1* Monitor New Ready for Re-Test Reopened Total 1

All Open Defects

TIBCO Upgrade Project

1 high defect raised during PT – BC Retry not working on EI EMMA

slide-18
SLIDE 18

ReMCoWG Update

Wednesday 29th June, 2016

18

slide-19
SLIDE 19

Retail Markets Co-Ordination Design Service ReMCoDS

29th June 2016

Co-ordinated Retail Market Design Update Jessica Gregory ReMCoDS

slide-20
SLIDE 20

Retail Markets Co-Ordination Design Service ReMCoDS

This MCR covers changes that are required to implement compliance in ROI with SI463. The proposed changes are:-

Capture mental health & dexterity impaired as a type of vulnerability thus allowing suppliers to register customers under this category.

Create a new category named ‘’Other’’ on the Special Services Register and introduce this as a ‘’dormant code’’ which could be activated if the need arose in the future. The purpose of this proposal is to ensure a quick turn-around for introduction into market.

Automate the rejection of disconnection requests for non-payment on account for all vulnerable customers registered on the Priority Services Register (Medical Equipment Special Needs Life-Support and Non-life Support) for all year around

Automate the rejection of disconnection requests for non-payment of account for all vulnerable customers registered on the Special Services Register (Customer Services Special Needs) from 1 November to 31 March. At Todays Meeting: For Approval

29TH June 2016

MCR1173 – Vulnerable Customers Implementation in RoI of SI463

slide-21
SLIDE 21

Retail Markets Co-Ordination Design Service ReMCoDS

Co-ordinated Market Releases

29th June 2016

Co-MMR Release date of Thursday 2nd June 2016. (Joint Release with MMR 10.7) _ SUCCESFULLY COMPLETED

TUP/Schema Release 2015 – Cut over date is 5th August. Market cutover strategy/guide to be issued by TUP.

  • COBL & MM Guides will be updated on 08 August to version 3.0

Schema Release 2016 – Will not occur in 2106. Co-ordinated Retail Planning exercise (SG action 134 and 135) will determine date.

slide-22
SLIDE 22

Retail Markets Co-Ordination Design Service ReMCoDS

IPT Phase of TUP and Schema release 2015

29th June 2016

IPT has been running for 2 days (started Monday 27 June 2016) in NI and ROI.

To date, no significant issues identified.

Progress in ROI

MPs to complete all declarations and evidence by 8th July 2016.

IPT formally closes on 13 July 2016

ROI IPT2 Exit Report completed by Friday 15th July

Assurance Report delivered to RA’s on 25 July

RA Go/No Go decision on 1 August.

Statistic ROI NI Total Test Runs (Week 1 and 2) 636 60 Total test cases started - cumulative for week 123 18 Testing completed 81 12 Evidence to Gemserv 63 7 Open Gemserv Query (this can reduce once query resolved) Test Cases successful sign off by Gemserv/Neueda 20 7 Failed Percentages Percentage testing complete 10.3139 20 Perecentage tests failed Total Testing Completed (Failed and completely signed off) 2 12

slide-23
SLIDE 23

Retail Markets Co-Ordination Design Service ReMCoDS

Upcoming Outages for ROI & NI

http://rmdservice.com/outages-2016/

29th June 2016

No outage information for July has been received as of yet

slide-24
SLIDE 24

Retail Markets Co-Ordination Design Service ReMCoDS

Next Steps

29th June 2016

 Diary dates for next ReMCoWG meeting:

Wednesday 31st August 2016 - Dublin Dates included on Calendar of Events on RMDS website www.rmdservice.com

slide-25
SLIDE 25

Retail Markets Co-Ordination Design Service ReMCoDS

ReMCoWG Meeting

AOB

29th June 2016

slide-26
SLIDE 26

Retail Markets Co-Ordination Design Service ReMCoDS

Thank You

ReMCoWG Meeting

29th June 2016