wipp update
play

WIPP Update New Mexico Society of Professional Engineers June 11, - PowerPoint PPT Presentation

WIPP Update New Mexico Society of Professional Engineers June 11, 2017 Albuquerque, NM www.energy.gov/EM 1 WIPP Configuration 2 www.energy.gov/EM 2 WI WIPP PP Bac ackground ound Facility mined in salt: 2,150 feet deep in ancient


  1. WIPP Update New Mexico Society of Professional Engineers June 11, 2017 Albuquerque, NM www.energy.gov/EM 1

  2. WIPP Configuration 2 www.energy.gov/EM 2

  3. WI WIPP PP Bac ackground ound Facility mined in salt: 2,150 feet deep in ancient salt formation that closes in and entombs waste forever 3 www.energy.gov/EM 3

  4. WIPP Underground Map 4 www.energy.gov/EM 4

  5. WIPP Routes 5 www.energy.gov/EM 5

  6. Types of Shipments Anticipated RH-72B TRUPACT-II TRUPACT-III HalfPACT www.energy.gov/EM 6

  7. WIPP Status • Prior to 2014: 11,897 shipments from 22 sites around the country • Shipments made 1999 through 2014 • Waste receipt and emplacement suspended in February 2014 due to two events: • Fire on underground vehicle • Thermal event in an emplaced drum 7 www.energy.gov/EM 7

  8. Timeline • Events occurred in February 2014 • Approximately nine months needed to return to limited underground operations • Original re-start date set for March 2016 • New re-start date December 2016 www.energy.gov/EM 8

  9. Manage the Message • Baseline was approved and publicly released in late January 2016 • What completion date should be discussed internally? • What completion date should be discussed externally? • When schedule slip occurs, how should it be communicated? www.energy.gov/EM 9

  10. Air Quality in the Underground • VOC are a common off-gas from the disposed waste • Due to diffusion through porous salt, VOC’s can occur in occupied areas even though waste is behind sealed bulkheads • Carbon Monoxide is a combustion product from underground diesel equipment • Low underground ventilation rates can lead to build-up of air contaminates in work areas • In March, 2016 timeframe, multiple incidents illustrated needed improvements in worksite air monitoring program • Alarm set points re-set based on recommendations from IH workshop and regulations • Number of alarms in worksites began increasing • What path forwarded should be initiated to keep work going? www.energy.gov/EM 10

  11. Schedule and Budget Concerns • Mounting schedule concerns led to a series of meetings with headquarters over the summer to discuss path forward • Congressional and stakeholder concern over schedule was mitigated by increasing the interactions with these groups • Tension existed between raising expectations and need for transparency • How would you incentivize completion? www.energy.gov/EM 11

  12. Interim Ventilation System www.energy.gov/EM 12

  13. Interim Ventilation System • Contractor performed a Contractor Readiness Assessment • CBFO performed a Line Management Review in parallel • CBFO determined Contractor Readiness Review was ineffective and recommends repeating it • IVS will double underground air flow • Should the RA be repeated? www.energy.gov/EM 13

  14. Ground Control • Ground control is biggest risk mitigation for underground work • Ground will heave on floor, scale on ribs, and fall on back www.energy.gov/EM 14

  15. Ground Control • A series of rock falls occurred in prohibited areas beginning in September 2016 www.energy.gov/EM 15

  16. Ground Control • Operations limited by lack of airflow • At most four bolters available • At the time, worker safety concerns were increasing • MSHA recommending more areas should be prohibited • What path should be taken to allow work to continue? www.energy.gov/EM 16

  17. Readiness Activities • MSA performed in September, 2016 – Six pre-start findings • Contractor ORR performed in October, 2016 – Seven pre-starts and five post-start findings • Calendar indicates DOE ORR can start in mid- November • CBFO Line Management has concerns with proceeding with the DOE ORR • Should DOE ORR be performed and when? www.energy.gov/EM 17

  18. Authorization to Proceed • ORR completed the first week of December • 21 pre-start findings from DOE ORR • DOE ORR team recommended team member concur on CAP and validation packages • Completion of all pre-start actions on December 22, 2016 • When should authorization be given? • When should first emplacement be performed? www.energy.gov/EM 18

  19. WIPP Re-Opening www.energy.gov/EM 19

  20. WIPP Status • Significant changes to site safety management programs • Extensive readiness activities performed in 2016 • DOE/State of NM authorized operations in December 2016 • First emplacement in early January 2017 • First shipments received in early April 2017 20 www.energy.gov/EM 20

  21. Questions 21 www.energy.gov/EM 21

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend