WIPP Update New Mexico Society of Professional Engineers June 11, - - PowerPoint PPT Presentation

wipp update
SMART_READER_LITE
LIVE PREVIEW

WIPP Update New Mexico Society of Professional Engineers June 11, - - PowerPoint PPT Presentation

WIPP Update New Mexico Society of Professional Engineers June 11, 2017 Albuquerque, NM www.energy.gov/EM 1 WIPP Configuration 2 www.energy.gov/EM 2 WI WIPP PP Bac ackground ound Facility mined in salt: 2,150 feet deep in ancient


slide-1
SLIDE 1

www.energy.gov/EM 1

WIPP Update

New Mexico Society of Professional Engineers June 11, 2017 Albuquerque, NM

slide-2
SLIDE 2

www.energy.gov/EM 2

2

WIPP Configuration

slide-3
SLIDE 3

www.energy.gov/EM 3

Facility mined in salt:

2,150 feet deep in ancient salt formation that closes in and entombs waste forever

3

WI WIPP PP Bac ackground

  • und
slide-4
SLIDE 4

www.energy.gov/EM 4

4

WIPP Underground Map

slide-5
SLIDE 5

www.energy.gov/EM 5

5

WIPP Routes

slide-6
SLIDE 6

www.energy.gov/EM 6

Types of Shipments Anticipated

TRUPACT-III HalfPACT TRUPACT-II RH-72B

slide-7
SLIDE 7

www.energy.gov/EM 7

7

  • Prior to 2014: 11,897 shipments from 22 sites around the

country

  • Shipments made 1999 through 2014
  • Waste receipt and emplacement suspended in February

2014 due to two events:

  • Fire on underground vehicle
  • Thermal event in an emplaced drum

WIPP Status

slide-8
SLIDE 8

www.energy.gov/EM 8

Timeline

  • Events occurred in February 2014
  • Approximately nine months needed to return to

limited underground operations

  • Original re-start date set for March 2016
  • New re-start date December 2016
slide-9
SLIDE 9

www.energy.gov/EM 9

Manage the Message

  • Baseline was approved and publicly released in

late January 2016

  • What completion date should be discussed

internally?

  • What completion date should be discussed

externally?

  • When schedule slip occurs, how should it be

communicated?

slide-10
SLIDE 10

www.energy.gov/EM 10

Air Quality in the Underground

  • VOC are a common off-gas from the disposed waste
  • Due to diffusion through porous salt, VOC’s can occur in
  • ccupied areas even though waste is behind sealed bulkheads
  • Carbon Monoxide is a combustion product from underground

diesel equipment

  • Low underground ventilation rates can lead to build-up of air

contaminates in work areas

  • In March, 2016 timeframe, multiple incidents illustrated needed

improvements in worksite air monitoring program

  • Alarm set points re-set based on recommendations from IH

workshop and regulations

  • Number of alarms in worksites began increasing
  • What path forwarded should be initiated to keep work going?
slide-11
SLIDE 11

www.energy.gov/EM 11

Schedule and Budget Concerns

  • Mounting schedule concerns led to a series of

meetings with headquarters over the summer to discuss path forward

  • Congressional and stakeholder concern over

schedule was mitigated by increasing the interactions with these groups

  • Tension existed between raising expectations and

need for transparency

  • How would you incentivize completion?
slide-12
SLIDE 12

www.energy.gov/EM 12

Interim Ventilation System

slide-13
SLIDE 13

www.energy.gov/EM 13

Interim Ventilation System

  • Contractor performed a Contractor Readiness

Assessment

  • CBFO performed a Line Management Review in

parallel

  • CBFO determined Contractor Readiness Review

was ineffective and recommends repeating it

  • IVS will double underground air flow
  • Should the RA be repeated?
slide-14
SLIDE 14

www.energy.gov/EM 14

Ground Control

  • Ground control is biggest risk mitigation for

underground work

  • Ground will heave on floor, scale on ribs, and fall
  • n back
slide-15
SLIDE 15

www.energy.gov/EM 15

Ground Control

  • A series of rock falls occurred in prohibited areas

beginning in September 2016

slide-16
SLIDE 16

www.energy.gov/EM 16

Ground Control

  • Operations limited by lack of airflow
  • At most four bolters available
  • At the time, worker safety concerns were

increasing

  • MSHA recommending more areas should be

prohibited

  • What path should be taken to allow work to

continue?

slide-17
SLIDE 17

www.energy.gov/EM 17

Readiness Activities

  • MSA performed in September, 2016 – Six pre-start

findings

  • Contractor ORR performed in October, 2016 –

Seven pre-starts and five post-start findings

  • Calendar indicates DOE ORR can start in mid-

November

  • CBFO Line Management has concerns with

proceeding with the DOE ORR

  • Should DOE ORR be performed and when?
slide-18
SLIDE 18

www.energy.gov/EM 18

Authorization to Proceed

  • ORR completed the first week of December
  • 21 pre-start findings from DOE ORR
  • DOE ORR team recommended team member

concur on CAP and validation packages

  • Completion of all pre-start actions on December

22, 2016

  • When should authorization be given?
  • When should first emplacement be performed?
slide-19
SLIDE 19

www.energy.gov/EM 19

WIPP Re-Opening

slide-20
SLIDE 20

www.energy.gov/EM 20

20

  • Significant changes to site safety management programs
  • Extensive readiness activities performed in 2016
  • DOE/State of NM authorized operations in December 2016
  • First emplacement in early January 2017
  • First shipments received in early April 2017

WIPP Status

slide-21
SLIDE 21

www.energy.gov/EM 21

Questions

21