WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Orla Nagle UCC, October - - PowerPoint PPT Presentation

wind farms from development to operations
SMART_READER_LITE
LIVE PREVIEW

WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Orla Nagle UCC, October - - PowerPoint PPT Presentation

WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Orla Nagle UCC, October 22 nd 2012 IEI Young Engineers Society Wind Energy Development Stages Bord Gs Energy 2 1. Feasibility Feasibility Assessment : Ground conditions, Land cover


slide-1
SLIDE 1

WIND FARMS: FROM DEVELOPMENT TO OPERATIONS

Orla Nagle UCC, October 22nd 2012 IEI Young Engineers Society

slide-2
SLIDE 2

Wind Energy Development Stages

Bord Gáís Energy 2

slide-3
SLIDE 3

Feasibility Assessment :

  • Planning Policies – Site Zoning
  • Ground conditions, Land cover
  • 1. Feasibility

Bord Gáís Energy 3

  • Planning Policies – Site Zoning
  • Environmental Designation(s)
  • Wind Resource
  • Site ownership
  • Planning History - Site & Area
  • Prelim Landscape & Visual Assessment
  • Site Drainage & Hydrology
  • Ground conditions, Land cover
  • Proximity to neighbouring

development

  • Archaeological
  • Prelim Grid Connection Assessment
  • Access & Transportation
  • Cumulative Impacts
  • Assessment of Alternatives
slide-4
SLIDE 4
  • 1. Feasibility - cont’d
  • Preliminary turbine layout
  • Constraints identified
  • Viable development areas established
  • Site Capacity - no. of turbines
  • A feasibility study can prove very effective in

Bord Gáís Energy 4

  • A feasibility study can prove very effective in

identifying areas for further investigation and allows an early focus on relevant issues

  • Pre-planning discussions
  • Feasibility Stage Consultation
slide-5
SLIDE 5
  • Development Team
  • Environmental Assessment:

Environmental Impact Assessment (EIA) Environmental Report

  • An EIA is a multi-disciplinary, iterative process
  • 2. Assessment

Bord Gáís Energy 5

  • An EIA is a multi-disciplinary, iterative process

designed to identify, characterise and quantify the likely effects of a proposed development on the environment

  • The approach to an EIA should be informed by:

Statutory requirements (EIA Directive and EIA Regs) Consultation with statutory and non-statutory consultees Current guidance and best practice

slide-6
SLIDE 6
  • 2. Environmental Assessment

& Planning Application - cont’d

Bord Gáís Energy 6

slide-7
SLIDE 7
  • Typical Planning Process
  • 2. Assessment – cont’d

Bord Gáís Energy 7

  • Other possible consents & contracts:

CER - License to Construct, Authorisation to Generate Felling License – Forestry Services Grid Connection Agreement - Eirgrid Land Lease Agreement

slide-8
SLIDE 8
  • 3. Construction Stage
  • Development & implementation of a

Construction & Environmental Management Plan (CEMP), which defines

  • work practices
  • construction management procedures
  • environmental responsibilities

Bord Gáís Energy 8

  • environmental responsibilities

Ensuring environmental protection and planning compliance during development construction

  • Contractual requirement for Civil

Contractor, Turbine Contractor, Electrical Contractor etc.

slide-9
SLIDE 9
  • 3. Construction Stage – cont’d
  • Surface Water Management Plan:
  • Site Hydrology
  • Drainage Infrastructure
  • Erosion & Sediment Control – buffer

zones, silt traps, silt fencing etc.

  • Watercourse Crossings – bridges, culverts

Bord Gáís Energy 9

  • Watercourse Crossings – bridges, culverts
  • Materials Storage – fuels, oils etc.
  • Consultation – IFI, OPW etc.
slide-10
SLIDE 10

Benefits of a CEMP & Good Environmental Practice on Site:

  • 3. Construction Stage – cont’d

Bord Gáís Energy 10

slide-11
SLIDE 11

Questions?