What do we need to consider? Design Installation Cleaning - - PowerPoint PPT Presentation
What do we need to consider? Design Installation Cleaning - - PowerPoint PPT Presentation
What do we need to consider? Design Installation Cleaning methodology Water Quality at Practical Completion Design The system design should be reviewed to make sure that it allows good water quality to be achieved and
What do we need to consider?
- Design
- Installation
- Cleaning methodology
- Water Quality at Practical Completion
Design
The system design should be reviewed to make
sure that it allows good water quality to be achieved and maintained
All necessary flushing facilities are present
(bypasses, flushing connections, valve arrangements etc.)
Dead legs should be avoided Pipework materials of installation Pressurisation units (flow through units, short
connecting pipework)
Design
Dosing pots (not automated dosing) Use of de-aerators Use of HEX units Water conservation in flushing Side stream filters The BMS needs to be considered to ensure
that routine circulation through all previously wetted areas can be achieve
Installation
Clean installation practices Wet pipework and plant as close to the start
- f flushing as possible
Use treated water for pressure test Take appropriate precautions after pipework is
wet
Water treatment planning to be co-ordinated
with installation plan
Pipework waiting to be installed
Pipework installed
Even when racked no caps fitted
Stored on site
Installation
All points listed are common to both
conventional and low effluent processes and are instrumental in the successful
- utcome of water treatment
Cleaning Methodology
Conventional No/Low effluent
Tried and tested Will require significant water and
drainage capacity
Is robust in approach The long term prognosis is
understood
Saves water and relies on filtration-
but filters go to ‘land fill’
Possible time saving/ labour
reduction
Requires consideration at the time
- f design/installation
Chemicals added to system stay
there increasing TDS and presenting
- ther challenges
If it should fail it would be
necessary to revert to conventional treatment
Use of Side Stream Filter as Flushing Aid
Water Treatment
Flushing and cleaning should be undertaken in
accordance with BG 29/2012
Dynamic flushing should be correctly undertaken Biocide washes should be employed as necessary Chemical cleaning should be carefully monitored Final dosing chemicals should be effective and
selected with system metallurgy and components in mind
Limitations of low flow devices when backflushing
Where low flow occurs
2 port valve, kv value 0.25 (open)
Water Quality Maintenance until PC
Take first set of samples 7 days after final chemical
- dose. PCC samples
Routine (daily) checks that completed systems are
kept full and pressurised
Routine (daily) checks that pumps are circulating and
valves are in the correct position
Control over any necessary drain downs and
pipework alterations
Fortnightly sampling to allow timely chemical
additions as required
At PC the client should be provided with:
Stable and maintainable water in closed systems Trend results as outlined in BSRIA 29/2012 (see next
2 slides)
The Site LTHW TVC @22˚C CFU/ml Date Geometric mean PC Guideline PCC Guideline Trend 01/02/2012 105 100,000 10,000 17/02/2012 1 100,000 10,000 01/03/2012 1 100,000 10,000 Acceptable 15/03/2012 1 100,000 10,000 Acceptable
1 10 100 1000 10000 100000
TVC Level
Date
Site - LTHW -
Geometric mean PC Guideline PCC Guideline
The Site LTHW Secondary Pseudomonad @30˚C CFU/100 ml Date Geometric mean PC Guideline PCC Guideline Trend 01/02/2012 412.13 10,000 1,000 17/02/2012 100 10,000 1,000 01/03/2012 2607.23 10,000 1,000 Increasing trend and above PCC level 15/03/2012 100000 10,000 1,000 Unacceptable
1.00 10.00 100.00 1000.00 10000.00 100000.00
Pseudomonad Level
Date
Site LTHW Secondary
Geometric mean PC Guideline PCC Guideline