An Update for the West Valley PPA Model Neptune and Company 23 August 2017 West Valley Quarterly Public Meeting August 2017 1 The West Valley PPA Model Model development continues... This presentation follows from the Quarterly Public


slide-1
SLIDE 1

1

West Valley Quarterly Public Meeting • August 2017

An Update for the West Valley PPA Model

Neptune and Company 23 August 2017

slide-2
SLIDE 2

2

West Valley Quarterly Public Meeting • August 2017

The West Valley PPA Model

Model development continues... This presentation follows from the Quarterly Public Meeting presentation of 10 May 2017. Focus is on the representation of Facilities and Decision Units and manipulation in the model.

slide-3
SLIDE 3

3

West Valley Quarterly Public Meeting • August 2017

High-Level Layout of the Model

  • Calculations are organized by Waste Management

Area (WMA), Facilities within each WMA, and Decision Units within those Facilities.

  • Off-Site modeling includes creeks and Lake Erie.
slide-4
SLIDE 4

4

West Valley Quarterly Public Meeting • August 2017

Main Control Panel

slide-5
SLIDE 5

5

West Valley Quarterly Public Meeting • August 2017

WMA Controls

slide-6
SLIDE 6

6

West Valley Quarterly Public Meeting • August 2017

WMA 3 (WTF) Controls

slide-7
SLIDE 7

7

West Valley Quarterly Public Meeting • August 2017

WMA 7 (NDA) Layout Detail

slide-8
SLIDE 8

8

West Valley Quarterly Public Meeting • August 2017

NDA WVDP Trenches

slide-9
SLIDE 9

9

West Valley Quarterly Public Meeting • August 2017

NDA Deep Holes • Map Controls

slide-10
SLIDE 10

10

West Valley Quarterly Public Meeting • August 2017

NDA Deep Holes • Table Controls

slide-11
SLIDE 11

11

West Valley Quarterly Public Meeting • August 2017

NDA Special Holes – East Group

slide-12
SLIDE 12

12

West Valley Quarterly Public Meeting • August 2017

NDA Special Holes – North Group

slide-13
SLIDE 13

13

West Valley Quarterly Public Meeting • August 2017

NDA Special Holes – West Group

slide-14
SLIDE 14

14

West Valley Quarterly Public Meeting • August 2017

NDA Other Facilities

slide-15
SLIDE 15

15

West Valley Quarterly Public Meeting • August 2017

WMA 8 (SDA) Layout Details

slide-16
SLIDE 16

16

West Valley Quarterly Public Meeting • August 2017

SDA North Facilities Controls

slide-17
SLIDE 17

17

West Valley Quarterly Public Meeting • August 2017

SDA South Facilities Controls

slide-18
SLIDE 18

18

West Valley Quarterly Public Meeting • August 2017

Results Dashboards

slide-19
SLIDE 19

19

West Valley Quarterly Public Meeting • August 2017

Results Index

slide-20
SLIDE 20

20

West Valley Quarterly Public Meeting • August 2017

SDA Contaminant Transport Results

slide-21
SLIDE 21

21

West Valley Quarterly Public Meeting • August 2017

SDA Erosion Results

slide-22
SLIDE 22

22

West Valley Quarterly Public Meeting • August 2017

Dose to On-Site Resident Farmer

slide-23
SLIDE 23

23

West Valley Quarterly Public Meeting • August 2017

RF Dose by Facility

slide-24
SLIDE 24

24

West Valley Quarterly Public Meeting • August 2017

RF Dose for SDA South Facilities

slide-25
SLIDE 25

25

West Valley Quarterly Public Meeting • August 2017

RF Dose for SDA Trench 9

slide-26
SLIDE 26

26

West Valley Quarterly Public Meeting • August 2017

RF Dose • SDA 9, by Radionuclide

slide-27
SLIDE 27

27

West Valley Quarterly Public Meeting • August 2017

RF Dose • SDA 9, by Pathway

slide-28
SLIDE 28

28

West Valley Quarterly Public Meeting • August 2017

RF Dose • SDA 9, External Irradiation