Lawyer’s view on the Jordanian PPA
Khaldoun Nazer
Lawyers view on the Jordanian PPA Khaldoun Nazer Agenda What is - - PowerPoint PPT Presentation
Lawyers view on the Jordanian PPA Khaldoun Nazer Agenda What is the Jordanian PPA? Renewable Energy and Energy Efficiency Law Development of the Jordanian PPA PPA Main Components Developed Markets Three Important Terms:
Khaldoun Nazer
What is the Jordanian PPA?
Renewable Energy and Energy Efficiency Law Development of the Jordanian PPA
PPA Main Components – Developed Markets Three Important Terms:
Proper Risk Allocation Project Finance Bankability
Walk through the Jordanian PPA Our view on the Jordanian PPA
Not
cover ers PPAs to be be signe ned with NEPCO CO
Renewable Energy & Energy Efficiency Law 13/2012 (REEL)
Regulates the development of Renewable Energy Projects in Jordan
Interrelates with the General Electricity Law – provides the licensing and regulatory regime (generators, transmission and distribution)
REEL - Power Purchase Agreement (PPA) is part of the Project Agreements which will be signed once the project is approved.
REEL does not define a PPA nor does it stipulate any minimum requirements that must be covered in a PPA
PPA under Jordanian Law is a contractual relationship that regulates
the sale and purchase of electrical power.
Jordanian Law recognizes “Freedom of Contract” subject at all times
to Public Order and Mandatory Legal Requirements
Development of the Jordanian PPA
IPP 1 Conventional Generation (Gas, Diesel, HFO)
IPP 2 Conventional Generation
CGECO Privatization – PPAs for existing plants – Conventional Generation
Bidding process relating to Al-Kamsha Wind Farm – PPA was based on IPPs (Conventional Generation)
Bidding process relating to Al-Fujeij Wind Farm – PPA was based on negotiated Kamsha PPA
IPP 3 - Conventional Generation
IPP 4 – Peaking Units of Existing Plants
Tafila Wind Farm PPA
Solar Projects PPAs – Round 1 of Direct Proposals
Developed Markets define the PPA as a contract to buy the electricity
generated by the power plant and refers to the purchaser of the electrical power as the “Off-taker”
PPA main components are:
Duration (typically ranging from 15 to 25 years)
Construction / Commissioning / Interconnection
Sale & Purchase of Electrical Power
Curtailment (by Project Developer / by Off-taker)
Proper Risk Allocation (Project Developer’s Risks and Off-takers Risks)
Insurance
Default and remedies
Environmental Attributes / Credits
Development/Promotion
Power Generation Projects entails understanding and comprehending the following Three Important Terms:
Proper Risk Allocation: Risk Matrix Process (Risk Identification,
Assessment, and Allocation)
Who is the party that will deal with the consequences of each
risk?
Risk to be assumed by the party that is best placed to manage
such risk.
Construction and operation of facility is typically developer’s risk Legal Risks (such as changes in law)
and political risk is Government’s risk
Insurable risk is assumed by the party that is able to insure it.
Project Finance
Project’s feasibility is liked to ability to attract equity and debt Debt usually ranges from 70% to 90% Equity portion is important to ensure developer’s commitment Project Finance is defined as “long term financing with non-
recourse or limited recourse where debt and equity used to finance the project are paid back from the project’s cash flow”.
Project’s cash flow is the principle source of security to lenders. Lenders and developers are looking at clarity as to the project’s
cash flow
Risks affecting the project’s cash flow must be managed
properly in order to ensure ability to attract equity and debt
Bankability:
Continuously used term No set definition No list of requirements to achieve Bankability A project is considered Bankable if lenders are ready to finance
the project on Project Finance basis (limited or non-recourse basis) A couple of banks in Jordan have Project Finance experience. Other banks are working on developing such practices. Active players include IFC, EIB, EBRD ….. etc
The Jordanian PPA – Boiler Plates
Long Term Agreement (20 Years after COD) NEPCO’s payment obligations are guaranteed by the Government
Signing up to Financial Close
Mainly developer to work
procuring the generation license, the environmental approvals (EIA Report) and the financing needed for the Project’s debt (PPA Direct Agreement and Guarantee Direct Agreement).
Financial Close up to COD
Construction of Facility and Interconnection Facilities
Construction of Substation
Commissioning (Independent Engineer, Tests, Sale of Power during tests, delay in commissioning and deemed commissioning)
COD onwards, developer to operate and maintain the facility
pursuant to:
Laws of Jordan;
Transmission system Grid Code
Generation License and other authorizations
Prudent Utility Practice
Operating Protocol and Access Protocol
Sale and Purchase of Power Curtailment of Delivery Major Maintenance activities and maintenance in Emergency
situations.
Metering, disputes on metering and un-availability of meters’
reading
Invoicing, late payments and disputed payments Emission Reduction Credits Insurance Force Majeure (Government FM Events and Other FM Events) Prolonged FM Events (No termination for Prolonged Government
FM Events)
Total / Partial Loss – Restoration Change in Law Protection – (one time vs. ongoing) Default, Termination and Consequences of Termination
Relationship with lenders (Direct Agreements, Notices, Step-in
Rights, Assignment…. etc).
Dispute resolution: Expert (certain technical issues) and Arbitration
per ICC Rules in London.
Applicable Law is Jordanian Law Restrictions on transfer of shares in Project Company (no-rationale) Decommissioning (no-rationale on private lands)
Jordanian Law Issues
FM Events under Jordanian Law – Jordanian Civil Code Liquidated Damages and Agreed Compensation vs. Actual
Damages
Ability to charge Default Interest on Late Payments PPA Not Tested: No Precedents on application of Jordanian
Law on Disputes
Fairly developed given MEMR’s/NEPCO’s experience in IPPs Covers the main components identified in Developed Markets PPAs Needs refinement in certain areas such as:
Risk to lenders relating to Total Debt Outstanding if PPA is terminated for reasons
No termination for prolonged Government FM Events
No recovery of additional costs incurred by Project Company when operating under Government FM Events
Other FM Events – must distinguish between those affecting NEPCO and those affecting Project Company as those affecting NEPCO cannot be insured by Project Company.
Land related risks for projects located within identified areas (Maan Development Area and Mafraq Development Area)
Compensation for NEPCO EoD to provide return on Equity
Amman – Jordan Tel: +962 6 5664750 Email: info@khalifehlaw.com khn@khalifehlaw.com