September 17, 2019 WEST FALLS CHURCH STATION PLANNING AREA West Falls Church TSA Study Area Plan Amendment 2018-II-1 Tax Map Parcels: 40-4 ((1)) 13; 40-4 ((2)) 1 & 2; 40-3 ((1)) 83, 84, 92 and 92A WHAT YOU WILL LEARN TODAY Progress


slide-1
SLIDE 1

September 17, 2019

WEST FALLS CHURCH STATION PLANNING AREA

West Falls Church TSA Study Area Plan Amendment 2018-II-1 Tax Map Parcels: 40-4 ((1)) 13; 40-4 ((2)) 1 & 2; 40-3 ((1)) 83, 84, 92 and 92A

slide-2
SLIDE 2

WHAT YOU WILL LEARN TODAY

  • Progress Update
  • Development Strategy
  • Next Steps
slide-3
SLIDE 3

PROGRESS UPDATE

  • WMATA and VT proposed an amendment to the

Comprehensive Plan

  • Performing planning and design analysis to support

mixed-use, transit-oriented development

  • Coordinating with adjoining City of Falls Church

development

  • Conducting traffic survey, preparing existing conditions

reports, and modeling future scenarios and mitigations

  • Status of development projects
  • City of Falls Church Economic Development Project –

Interim Development Agreement: FCGP Development (EYA, Hoffman, and Regency)

  • Virginia Tech – selection of HITT/Rushmark team
  • WMATA – considering proposal from a team consisting
  • f EYA, Rushmark, and Hoffman
slide-4
SLIDE 4

TIMELINE

Ongoing monthly WFC Task Force meetings Sept 2019 WFC Task Force: July 2020: Present Winter 2019/20: Planning development WFC Study Commission proposals impact analysis Hearing Winter 2019/20: Spring/Summer Sept 2020: WMATA and VT 2020: Task Force Board of submit traffic and county staff Supervisors study to VDOT recommendations hearing to update Comp Plan

slide-5
SLIDE 5

REGIONAL OVERVIEW

slide-6
SLIDE 6

DEVELOPMENT PROPERTIES

slide-7
SLIDE 7

WFC Commons Drive: 0.35 miles Georgetown M Street: 0.43 miles Mosaic District – District Ave.: 0.34 miles Old Town Alexandria – King St.: 0.4 miles

slide-8
SLIDE 8

PLACEMAKING CONCEPT

People Space Place

slide-9
SLIDE 9

AREA VISION

Active Streets Woonerfs & Alleys Landscape

  • A dynamic, mixed-use neighborhood with…

 Education, research and innovation at its heart (Middle School, High School, VT, HITT HQ)  New spaces to preserve and grow communities (apartments, condos, micro housing, senior housing, etc.)

Multifamily Townhomes Mixed Uses

 New offerings and amenities that serve the surrounding neighborhoods and region

  • Create a unified site plan and approach to traffic

management for all 3 properties

  • Develop 3 distinct development clusters

Retail, Restaurants, & Cafes Urban Parks Transportation

WMATA Virginia Tech

  • Apartments/Condos
  • Classrooms
  • Townhouses
  • Research Labs
  • Retail
  • Housing
  • Office
  • Retail
  • Office
slide-10
SLIDE 10

GENERAL SITE PLAN & ACCESS POINTS

STRATEGIC APPROACH

  • Reduce reliance on Haycock/SR7 intersection
  • Improve safety and pedestrian connectivity
  • Establish unique open spaces that complement

the three (3) thematic clusters

  • Create compatible transitions between existing

communities

  • Limit need for additional parking, but provide flex

space should it be necessary

W1 W2 S1 S2 N3 N1 N2 Retail & Cultural Destination Academic Destination Transit & Neighborhood Destination

slide-11
SLIDE 11

ROAD NETWORK

slide-12
SLIDE 12

VEHICULAR CIRCULATION

slide-13
SLIDE 13

GEORGE MASON HIGH SCHOOL SITE: GROUND FLOOR USES

slide-14
SLIDE 14

GEORGE MASON HIGH SCHOOL SITE: UPPER FLOOR USES

USE SF UNITS

slide-15
SLIDE 15

WFC STATION AREA

slide-16
SLIDE 16

VIRGINIA TECH

slide-17
SLIDE 17

HITT CONTRACTING

slide-18
SLIDE 18

NATIONAL INSTITUTE OF SMART CONSTRUCTION

slide-19
SLIDE 19

PROPOSED HEIGHT DIAGRAM

45’ – 150’ 75’ 75’ – 115’ 135’ 75’ – 135’ 75’ – 125’ 75’ – 125’ 90’ – 135’ 75’ – 155’ 45’ – 85’ 45’ – 75’

slide-20
SLIDE 20

NEXT STEPS

  • October
  • Development team presents vision for redevelopment of the site
  • Update on preliminary traffic analysis
slide-21
SLIDE 21