Welcome to the Online Consultation Western Alignment & Vehicle - PowerPoint PPT Presentation

Welcome to the Online Consultation Western Alignment & Vehicle Maintenance & Storage Facility Update Please review the presentation and complete the survey by July 10, 2012. Western Alignment & Future Vehicle Maintenance and


  1. Welcome to the Online Consultation Western Alignment & Vehicle Maintenance & Storage Facility Update Please review the presentation and complete the survey by July 10, 2012. Western Alignment & Future Vehicle Maintenance and Storage Facility Update 1

  2. Format for Feedback • Please complete the online survey at www.thecrosstown.ca by July 10, 2012 • A consultation report to inform the designers will be posted online at: www.thecrosstown.ca Western Alignment & Future Vehicle Maintenance and Storage Facility Update 1

  3. Online Consultation Overview Part 1 • Crosstown Background, Key Developments & Construction Update Part 2 • New Keele Street to Weston Road Routing – Preliminary Planning Part 3 • Vehicle Facility – Preliminary Planning * Metrolinx is beginning the Mount Dennis Mobility Hub Study for the area around the station. Western Alignment & Future Vehicle Maintenance and Storage Facility Update 2

  4. The Purpose of this Online Consultation • Provide a brief project update • Present proposed changes & improvements to the alignment from Keele Street to Weston Road • Provide an overview of the Maintenance and Storage Facility layout & challenges Most importantly: • Get your input on the Preliminary Planning early in this process. A second community consultation will be held in Fall, 2012 Western Alignment & Future Vehicle Maintenance and Storage Facility Update 3

  5. Presentation Part 1: Crosstown Background, Key Developments & Construction Update Western Alignment & Future Vehicle Maintenance and Storage Facility Update 4

  6. What was determined in 2010 Keele to Jane Section A street-level LRT alignment on the following panel was approved through a study (Transit Project Assessment) in 2010. Western Alignment & Future Vehicle Maintenance and Storage Facility Update 5

  7. 2010 Alignment (Street Level) Western Alignment & Future Vehicle Maintenance and Storage Facility Update 6

  8. What we heard in 2009 – 2010 Community Concerns were raised during the previous study. The new study will address these: • Traffjc concerns at Black Creek Drive • Pedestrian Crossings at Weston Road • Property impacts in the vicinity of Weston Road • Plan for Crosstown connection to GO Transit Western Alignment & Future Vehicle Maintenance and Storage Facility Update 7

  9. Key Project Developments since 2010 • An off-street (elevated) route is now proposed from a portal west of Keele Street to Black Creek • Underground LRT is now proposed from Black Creek to Weston Road • An underground “Weston Rd/Mt Dennis Station” is now proposed, just east of Weston Road • Protecting for future GO Transit connection • Preliminary plans are developing to retain Kodak Building Western Alignment & Future Vehicle Maintenance and Storage Facility Update 8

  10. Proposed New Route Alignment – 2012 • This project includes construction to Weston Rd/Mt Dennis Station to be complete in 2020 • The timing and construction method for Weston Road to Jane Street is TBD through further study Western Alignment & Future Vehicle Maintenance and Storage Facility Update 9

  11. Potential Benefjts of the New LRT Route Proposal • Improve access to the proposed Vehicle Maintenance and Storage Facility (MSF) • Build a new underground LRT station near Weston Road • Improve pedestrian connections at the newly proposed Station • Provide a new bus terminal for connection to proposed Weston Road/Mount Dennis Station • Preserve the former Kodak Employees Building for future re-development • Protect for a future GO Transit to Crosstown LRT connection A new study will now assess the pros and cons of the design changes and identify measures to mitigate any impacts such as those related to “Weston Rd/Mt Dennis” Station. Western Alignment & Future Vehicle Maintenance and Storage Facility Update 10

  12. The Eglinton Crosstown Plan 2012 • 19 km Rapid Transit Line (Jane/Black Creek Drive to Kennedy Station) • 10 km Underground Tunnel (Keele Area to Laird Drive*) • SRT Replacement, Enhancement & Extension from Kennedy Station to Sheppard Avenue East • 60% faster than bus service today Exact alignment west of Keele Street TBD through this study * Western Alignment & Future Vehicle Maintenance and Storage Facility Update 11

  13. The Crosstown – 2012 *Final number and location of stations subject to Provincial review • 60% faster than current bus routes • 15 minutes from Keele to Yonge Western Alignment & Future Vehicle Maintenance and Storage Facility Update 12

  14. Implementation • The Keele to Weston Rd/Mt Dennis Station segment is part of the Province of Ontario’s $8.4 Billion Future Community Centre Future Bridge investment for Transit expansion in Toronto • Crosstown Phase 1 (2011 – 2020) – Tunnel contract for Keele to Yonge and Keelesdale Park Bridge are currently being tendered for bids – 6 LRT Stations are currently under design (Keele to Chaplin) Western Alignment & Future Vehicle Maintenance and Storage Facility Update 13

  15. Crosstown Construction Update • Tunnel preparation work at Black Creek and Eglinton in Keelesdale Park • Piling rigs are building concrete support walls for the future west tunnel launch shaft • The west launch shaft will enable tunnelling works in late 2012 towards Allen Road Western Alignment & Future Vehicle Maintenance and Storage Facility Update 14

  16. Presentation Part 2: Route Alignment Update Keele Street to Jane Street Western Alignment & Future Vehicle Maintenance and Storage Facility Update 15

  17. Guiding Principles The plans being presented today are conceptual, and will be refjned over the coming months to: • Minimize impacts to the natural environment • Reduce property impacts if possible • Minimize costs • Minimize impacts to buildings • Enhance access to vehicle facility Western Alignment & Future Vehicle Maintenance and Storage Facility Update 16

  18. Study Areas * * For future study Western Alignment & Future Vehicle Maintenance and Storage Facility Update 17

  19. 2012 – New Proposed Plan/Profjle Western Alignment & Future Vehicle Maintenance and Storage Facility Update 18

  20. Weston Rd / Mt Dennis Station Western Alignment & Future Vehicle Maintenance and Storage Facility Update 19

  21. Presentation Part 3: Vehicle Maintenance & Storage Facility Preliminary Planning Western Alignment & Future Vehicle Maintenance and Storage Facility Update 20

  22. Maintenance and Storage Facility Requirements • 17 hectares (42 acres) of fmat property • Vacant property preferred or property which causes minimal displacement of existing commercial/industrial activities • Ideally zoned for industrial/employment or transportation use • Proximity to the Eglinton line – ideally less than 1 kilometre • Ideally close to future intersecting LRT lines. Western Alignment & Future Vehicle Maintenance and Storage Facility Update 21

  23. Maintenance and Storage Facility Western Alignment & Future Vehicle Maintenance and Storage Facility Update 22

  24. Maintenance and Storage Facility Concept Western Alignment & Future Vehicle Maintenance and Storage Facility Update 23

  25. Bus Terminal The Weston Rd/Mt Dennis LRT Station will be connected to a new 15-bay bus terminal. Western Alignment & Future Vehicle Maintenance and Storage Facility Update 24

  26. Bus Routes Serving the Bus Terminal It is proposed that the following TTC bus routes will serve the new bus terminal: • 19 Jane South (new) • 89 Weston (local southbound) • 32 Eglinton West • 161 Rogers Rd • 35 Jane • 168 Symington • 35E Jane Express • 170 Emmett (new) • 71 Runnymede • 171 Mount Dennis • 89 Weston (local northbound) • TTC Wheel-Trans Western Alignment & Future Vehicle Maintenance and Storage Facility Update 25

  27. Bus Terminal: MSF Site with Kodak Building Black Creek Dr Existing Building Photography Dr Eglinton Ave W Western Alignment & Future Vehicle Maintenance and Storage Facility Update 26

  28. Study Processes Transit Project Assessment (TPAP) • The alignment study focuses on the proposed changes to the approved Eglinton-Crosstown LRT plan, and will assess the impacts of the changes using the same assessment factors as the previous study. • The public will be provided opportunities to review and comment on the assessment of the impacts of the proposed design changes, and measures to mitigate those impacts. • The impact assessment and results of the study will be documented in a report for the Eglinton Crosstown LRT Project. • The Vehicle Facility will also undergo study under the TPAP Western Alignment & Future Vehicle Maintenance and Storage Facility Update 27

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.