WELCOME! Ford Construction Logistics Meeting March 10, 2020 Agenda - - PowerPoint PPT Presentation

welcome
SMART_READER_LITE
LIVE PREVIEW

WELCOME! Ford Construction Logistics Meeting March 10, 2020 Agenda - - PowerPoint PPT Presentation

WELCOME! Ford Construction Logistics Meeting March 10, 2020 Agenda Team Introduction Schedule Site Logistics Demolition Construction Hours & Noise 2020 & 2021 Activities Haul Routes Phasing Video


slide-1
SLIDE 1

WELCOME!

Ford Construction Logistics Meeting

March 10, 2020

slide-2
SLIDE 2
  • Team Introduction
  • Schedule
  • Site Logistics
  • Demolition
  • Construction Hours & Noise
  • 2020 & 2021 Activities
  • Haul Routes
  • Phasing Video
  • Scheduled Closures
  • Ongoing Communication
  • Q & A

Agenda

slide-3
SLIDE 3

Ben Terry, Director of Construction

slide-4
SLIDE 4

Nick Koch, Project Executive, Construction

slide-5
SLIDE 5

Kelly Beach, Project Coordinator

slide-6
SLIDE 6

Bob Thompson, Field Coordinator

slide-7
SLIDE 7

Will Rollo, Senior Project Engineer

slide-8
SLIDE 8

Schedule

slide-9
SLIDE 9

Security Fence & Soil Erosion Control

slide-10
SLIDE 10

Site Logistics

slide-11
SLIDE 11

Early Demolition

slide-12
SLIDE 12

Early Demolition – Crushing

slide-13
SLIDE 13

Construction Hours & Noise

  • Construction Hours:

– Typical Work Week

  • Monday to Friday 7:00AM to 5:00PM
  • Extended hours 5:00PM to 7:00PM if

necessary

  • Saturdays – Make up day due to

schedule or weather

  • Construction Noise:

– Similar noises to past demolition activities – Activities generating noise:

  • Loading/Unloading Trucks
  • Concrete & Asphalt Demolition
  • Onsite Crushing
  • Limestone Bedrock Removal (Utilities

Installation)

slide-14
SLIDE 14

Phase 1 Utilities

slide-15
SLIDE 15

Cut/Fill Map

slide-16
SLIDE 16

Haul Routes

slide-17
SLIDE 17

2021 Road Construction

slide-18
SLIDE 18

Schedule – 2021 Activities – Public Open Spaces

slide-19
SLIDE 19

Schedule – 2021 Activities – Parks Facilities

slide-20
SLIDE 20

Phasing Video

slide-21
SLIDE 21
  • 2020

– Watermain connection – Ford Pkwy & Cretin

  • 1-2 week duration

– Watermain Connection – Ford Pkwy & Mt. Curve

  • 1-2 week duration

– Watermain Connection – Cleveland & Montreal

  • 1-2 week duration

Partial Temporary Lane Closures

slide-22
SLIDE 22

Partial Lane Closures

  • Summer/ Fall 2021

– Cretin & Ford Pkwy – Intersection Reconstruction – Mt. Curve & Ford Pkwy – Intersection Reconstruction – Cleveland & Montreal – Intersection Reconstruction

slide-23
SLIDE 23
  • Summer 2020:

– Mississippi River Blvd

  • New sanitary drop shaft
  • 2-3 month duration
  • Note:

– No bike/walking path closure associated with sanitary drop shaft.

Potential Full Road Closure

slide-24
SLIDE 24
  • Summer 2020:

– Mississippi River Blvd

  • New stormwater connection to

Hidden Falls

  • 1-2 months duration
  • Note:

– Intermittent bike/walking path closure associated with stormwater connection

Potential Full Road Closure

slide-25
SLIDE 25

Site Plan of Potential MRB Closure

slide-26
SLIDE 26
  • Highland District Council

www.highlanddistrictcouncil.org

  • City of St. Paul

www.stpaul.gov

  • Ford Website

www.fordsitestpaul.com

  • Ryan Companies

www.ryancompanies.com

  • Constant Contact

Get signed up for updates today!

Ongoing Communication

slide-27
SLIDE 27

Thank you!