Wekezhi Land and Water Boards Public Hearing Dominion Diamond Ekati - - PowerPoint PPT Presentation

wek ezh i land and water board s public hearing dominion
SMART_READER_LITE
LIVE PREVIEW

Wekezhi Land and Water Boards Public Hearing Dominion Diamond Ekati - - PowerPoint PPT Presentation

Wekezhi Land and Water Boards Public Hearing Dominion Diamond Ekati Corporation Jay Diamond Mine Project Fisheries and Oceans Canada December 13-15, 2016 Yellowknife, NWT Overview 1. DFO Mandate 2. Intervention - Conclusions and


slide-1
SLIDE 1

Wek’èezhìi Land and Water Board’s Public Hearing Dominion Diamond Ekati Corporation Jay Diamond Mine Project

Fisheries and Oceans Canada December 13-15, 2016 Yellowknife, NWT

slide-2
SLIDE 2

Overview

2

1. DFO Mandate 2. Intervention - Conclusions and Recommendations 3. Questions

  • J. Stewart DFO
slide-3
SLIDE 3

DFO’s Fisheries Protection Program - Mandate

  • J. Stewart DFO

The mandate of the Fisheries Protection Program is to maintain the sustainability and ongoing productivity of commercial, recreational and Aboriginal fisheries. Fisheries Act

  • Subsection 35 (1) - no person shall carry on any work, undertaking or activity

that results in serious harm to fish that are part of a commercial, recreational

  • r Aboriginal fishery, or to fish that support such a fishery.
  • Paragraph 35 (2) (b) allows for the issuance of a Fisheries Act Authorization
  • Section 20 relates to the provision of sufficient water and unimpeded fish

passage.

  • Section 36 – administered by Environment Canada - prohibits the deposit of a

deleterious substance into fish-frequented waters unless authorized by regulation made under the Fisheries Act.

3

slide-4
SLIDE 4

Intervention Conclusions and Recommendations

4

slide-5
SLIDE 5

5

Water Crossings

Issue

  • Potential for a fish passage barrier to

form at the inlet of Culvert B0 if backwatering of Lake B0 occurs during peak flows

Drawing 965-11-2001, Jay Road Construction Drawings (DDEC and Golder, April 22, 2016), p. 4

M D’Aguiar DFO

slide-6
SLIDE 6

Water Crossings – Recommendations

  • For the Developer to implement best management practices to avoid and

mitigate serious harm to fish as a result of water crossing construction,

  • peration and decommissioning.
  • For the Developer to implement a water crossing maintenance and

monitoring plan.

  • For the Developer to provide detailed engineering plans of all water

crossings, supported by measured or modeled stream flow data, for review prior to construction.

6

slide-7
SLIDE 7

7

Timing of Connection to Diversion Channel

Issue

  • Fisheries and Oceans Canada is unclear what impact the

proposed fall 2020 connection of the diversion channel to Lac du Sauvage will have on migrating fishes within the natural channels (Streams Ac35 and B0).

Recommendation

  • For the Developer to continue working with Fisheries and

Oceans Canada.

slide-8
SLIDE 8

8

Diversion Channel

Issue

  • Sub-Basin B diversion channel does not

account for fish passage needs of all fish species present, e.g.:

– A 8% slope is required to connect the Ac35 intake to main channel; and – Only Arctic Grayling and Burbot are considered

DFO

slide-9
SLIDE 9

9

Diversion Channel - Recommendations

1. For the Developer to implement best management practices in the design of Sub-Basin B Diversion Channel to avoid and mitigate serious harm to fish. 2. For the Developer to implement an appropriate stream diversion maintenance and monitoring plan. 3. For the Developer to provide detailed plans for the diversion. 4. For the Developer to provide detailed closure and reclamation plans for Sub- Basin B Diversion channel.

slide-10
SLIDE 10

10

Conceptual Fish-out Plan

Issue

  • The full extent of the impacts to fisheries

productivity has yet to be determined.

  • The fate of fish to be captured during the

fish-out also has to be determined.

DDEC, DAR, Conceptual Fish-out Plan, 2014 DFO

slide-11
SLIDE 11

11

Conceptual Fish-out Plan - Recommendation

1. For the Developer to conduct additional consultation with affected Aboriginal Groups regarding the handling and fate of fish captured during the fish-out. 2. For the Developer to continue working with Fisheries and Oceans Canada and affected Aboriginal Groups during the Fisheries Act authorization process

slide-12
SLIDE 12

12

Water Level

Issue

  • Potential Impacts from changes to

water levels in the Narrows, Lake C1 and Stream C1.

slide-13
SLIDE 13

13

Water Level - Recommendation

1. For the Developer to monitor water levels at critical or depth-limiting locations within the Narrows. 2. For the Developer to establish a mitigation, response or action plan in the event that significant changes in water levels are likely to occur, to mitigate the risk of the formation of barriers to fish passage or serious harm to fish in Lake C1/Stream C1 and the Narrows. 3. For the Developer to continue working with Aboriginal groups in the development of appropriate back flooding procedures and timing, with appropriate monitoring to ensure the rate of back flooding does not negatively impact fish and fish habitat

slide-14
SLIDE 14

14

Fish and Fish Habitat

Issue

  • Need for suitable avoidance,

mitigation and offsetting plans for the Jay Project to address Project impacts to fish and fish habitat

Map 2.3-1 Fish and Fish Habitat Baseline (DDEC and Golder, 2015), p. 15

slide-15
SLIDE 15

15

Fish and Fish Habitat - Recommendations

1. For the Developer to include the newly identified shoals as part of their offsetting calculations. 2. For the Developer to provide information regarding the Dyke design and mitigation measures associated with its construction, operation and decommissioning during their application for a Fisheries Act Authorization.

slide-16
SLIDE 16

16

Conclusion

Fisheries and Oceans Canada will continue to engage with the Developer and stakeholders, including potentially affected Aboriginal Groups, to ensure that interests for the protection of fish and fish habitat are being addressed and that:

  • Appropriate mitigation measures, follow-up and monitoring programs are

implemented;

  • A Fish-out Plan and Offsetting Plan are developed that are adequate and

acceptable to Fisheries and Oceans Canada and the affected Aboriginal Groups.

slide-17
SLIDE 17

17

Questions?

Mahsi Cho

  • J. Stewart DFO