WEST DESERT WATER SUPPLY PROJECT Population Projections & Actual Growth 180000 168,383 160000 140000 122,639 120000 94,169 POPULATION 100000 80000 53,000 60000 40000 20000 0 1960 1965 1970 1975 1980 1985 1990 1995 2000


slide-1
SLIDE 1

WEST DESERT WATER SUPPLY PROJECT

slide-2
SLIDE 2

168,383 122,639 94,169

53,000

20000 40000 60000 80000 100000 120000 140000 160000 180000 1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 2018 2020 2030 2040 2050 2060 2070 POPULATION

YEAR OF REPORT GOVERNOR'S OFFICE OF MANAGE AND BUDGET

Population Projections & Actual Growth 1968 1980 1984 1992 1996 2000 2008 2012 2016 Actual Growth

slide-3
SLIDE 3

Population Projection

2018

50,000

2068

123,000

166% increase

  • ver 50 years
slide-4
SLIDE 4

1 acre foot of water =

326,700 gallons

1 acre foot of water supports

Economic Benefits

Today West Desert 3,913 10,400

= .4 =1.52 =1.71 =4.34

15,285 39,500 17,154 44,500 46,163 112,840

slide-5
SLIDE 5

West Desert Water Supply Water Rights Timeline

2006

Application to appropriate new water in three Valleys NW of Cedar City.

2010

Water Right Hearing

2012

Ground Water Study BLM, Div.Water Rights, USGS, CICWCD SE Approved Water Rights For CICWCD, & UA/SITLA. These WRs were all appealed

2016

Utah Alunite/SITLA Application

2014

July - Trial de Novo August - Enter Settlement discussions & Mediation

2018

Today - Finalization of agreement and settlement Hamlin Valley 10,000 AF Pine Valley 15,000 AF Wah Wah Valley 12,000 AF Cedar Valley We use Safe Yield

slide-6
SLIDE 6

West Desert Water Supply Project

slide-7
SLIDE 7

Phase 1 Pine Valley Water Supply Project (PVWS)

slide-8
SLIDE 8

Pine Valley Water Supply Project

2006-2018

Research, Studies and Preliminary Design

2013-2017

Drilling of Test Wells, Lithological Studies, Hydrologic Tests and Pump Tests BLM NEPA

  • Preliminary License

Application Submitted

  • Cost Recovery Agreement

2019-2020 2018

  • Select 3rd party environmental

Consultant

  • Acquire Right of Way permits
  • Conduct Archeological &

Biological Surveys

2021-2026

  • Draft EIS
  • Final EIS Decision
  • Record of Decision
  • Project Design
  • Financing Plan
  • Construction
slide-9
SLIDE 9

Fast Facts Pine and Wah Wah Valleys Phase 1 & 2

Pine Valley

  • $225 million

Wah Wah Valley

  • $125 million

Est stimated Cost st TOTAL $350 million Pine Valley

  • 15,000 acre feet per year

Wah Wah Valley

  • 11,000 acre feet per year

Total

  • 26,000 acre feet per year

How Much h Water Approximately 81 Miles of underground pipe 13-16 Wells 5-8 Pump stations Compo ponent nents