WASTE TRANSFER {634} NRCS Waste Management Standards Overview Meeting - - PowerPoint PPT Presentation

waste transfer 634
SMART_READER_LITE
LIVE PREVIEW

WASTE TRANSFER {634} NRCS Waste Management Standards Overview Meeting - - PowerPoint PPT Presentation

WASTE TRANSFER {634} NRCS Waste Management Standards Overview Meeting [Aug. 2012] 634 Team Members Name Affiliation Title John Ramsden NRCS Sponsor Ronnie Williams Ronnie Williams DATCP {currently private} DATCP {currently private} Team


slide-1
SLIDE 1

WASTE TRANSFER {634}

NRCS Waste Management Standards Overview Meeting [Aug. 2012]

slide-2
SLIDE 2

634 Team Members

Name Affiliation Title John Ramsden NRCS Sponsor Ronnie Williams DATCP {currently private} Team Leader Ronnie Williams DATCP {currently private} Team Leader Todd Boehne CRA

{currently DATCP}

Brian Bogucki NRCS Amanda Crowe NRCS Brian Goepfert Juneau Cty. LCD Todd Rietmann Columbia Cty. LCD Steve Struss DATCP

slide-3
SLIDE 3

Overview

 Standard Updated  Standard Updated  New Specification for 634  New Companion Document for 634  New Companion Document for 634

slide-4
SLIDE 4

What’s in a Name?

Existing New Name Manure Transfer Waste Transfer Definition Manure conveyance system Byproducts from agricultural operations Purposes Animal manure All things waste

slide-5
SLIDE 5

What’s in a Name?

Wastewater Manure Processing Contaminated Leachate Derivatives Runoff

  • milkhouse
  • result of treatment or
  • water that has
  • water that has
  • milking parlor

washwater

  • leachate
  • similar waste

processing

  • examples:

flush water separated touched barnyard, animal lot, feed storage percolated through a pile of manure, processing derivatives or

  • similar waste

**wastewater from holding area is flush water, separated sand, separated manure solids, digested liquids, etc

  • generally has

manure, sediment, feed or other derivatives, or animal feed considered manure material in it

slide-6
SLIDE 6

What’s in a Name?

E i i N { k i d} Existing New {tank is not used} Tank Reception Structure Hopper Channel

  • never defined
  • used
  • collection vessel used to

hold waste and facilitate

  • sole purpose to feed

waste into a transfer

  • narrow structure
  • immediate transfer to

used throughout standard hold waste and facilitate its transfer waste into a transfer pump

  • >6,000 gallon

capacity are reception immediate transfer to reception structures, hoppers, w.s.f

  • include modified

structures gutters

slide-7
SLIDE 7

What’s in a Name?

P R i T f S P W ki P Pressure Rating Transfer System Pressure Rating Working Pressure for pipe pipe, pipe fittings, other appurtenances

  • max. designed operating

pressure of the transfer appurtenances pressure of the transfer system

  • max. pressure the pipe can

withstand without failure lowest pressure rating of any

  • f the items listed above

72% of the transfer system pressure rating withstand without failure determined by the manufacture

  • f the items listed above

pressure rating

slide-8
SLIDE 8

General Criteria

Existing New Conditions Where Applicable

  • Permanently installed

conveyance system

  • Does not apply to gutters

(d fi d i ti (defined as existing open troughs – think of stanchion barns)

Management Assessment Refer to 313 Components Listed g p Site Assessment Refer to 313 Components Listed

slide-9
SLIDE 9

General Criteria

Existing New Soil Investigations Tanks Only 1 40’ Reception Structures, Channels, and Transfer Pipe ti >100’ f il

  • 1 per 40’
  • +1 per add. 80’
  • no more than 100’

from footprint

  • no portion >100’ from soil

investigation

  • extend deep enough to ensure required

separation distance is achieved p p

  • complete more if soil varies significantly
  • each soil investigation can be used for

multiple components

  • logs follow new 313 criteria
  • logs follow new 313 criteria
slide-10
SLIDE 10

Example 1

slide-11
SLIDE 11

Example 2

slide-12
SLIDE 12

General Criteria

NEW SECTION

Separation from Subsurface Saturation or Bedrock p

 criteria consistent with 313  separation measured from closet distance from any point

th i id f f th t t th f t f

  • n the inside surface of the component to the feature from

which separation is required

 Perched Conditions

 drained via gravity  system located outside the component footprint  drain to surface outlet

 Bedrock

 No blasting  Treat fractures or voids  Min. 1% positive grade away from component

slide-13
SLIDE 13

General Criteria

NEW SECTION

Floodplain p

 protect reception structures, channels, and hoppers

from 25 yr 24 hr rainfall

 inundation  structural damage  instability

 transfer components affected by 25 yr 24 hr rainfall

 designed for loading (buoyancy/uplift) {companion document}  evaluated for additional protections (backflow, watertight connections,

  • auto. shutoffs)

ff f

 keep vents, power supplies, shutoffs out of water

slide-14
SLIDE 14

General Criteria

Safety Safety

 Safety fences – refer to Fence (382) Standard  design of tank cover, criteria listed  design of tank cover, criteria listed  ventilation of enclosed areas now required

slide-15
SLIDE 15

General Criteria

NEW SECTION

Failure Analysis Failure Analysis

 evaluate entire design  address issues  address issues

 during the design phase  O&M  E

R Pl

 Emergency Response Plan

 be sure to document the analysis and decisions made

slide-16
SLIDE 16

General Criteria

Construction Plans and Specifications Construction Plans and Specifications

Existing New Vague Specific

  • only required

an inspection

  • must include maximum

design working pressure

  • location map
  • plan view

an inspection plan design working pressure

  • transfer system

pressure rating

  • plan view
  • profiles
  • cross sections
  • details and specs to ensure it can be built

correctly

slide-17
SLIDE 17

General Criteria

NEW SECTION

Engineering Design Documentation Engineering Design Documentation

 follow Statement of Work (efotg)  includes all data, computations, assumptions  includes all data, computations, assumptions  must prove you have met the standard

slide-18
SLIDE 18

General Criteria

NEW SECTION

Quality Assurance Plan {formally known as Inspection} Quality Assurance Plan {formally known as Inspection}

 required for each construction plan  specifically lists required items  specifically lists required items

 site info.  key Parties  testing/Observations/etc.

slide-19
SLIDE 19

General Criteria

Operation and Maintenance Operation and Maintenance

Existing New refer to 313 Specific

  • must be reviewed with

landowner/operator

  • general system overview
  • safety and emergency response

landowner/operator

  • specific for each

component

  • detail maintenance
  • safety and emergency response
  • operating procedures, pump start up/downs
  • maintenance item schedule

items

slide-20
SLIDE 20

Specific Criteria p

Reception Structures, Channels, Hoppers, Pumps Reception Structures, Channels, Hoppers, Pumps

Existing (tanks and pumps) New Liquid tight “they” Joints and appurtenances Openings to Structures f S All National criteria Mi i di i d i d from Scrape Alleys

  • Min. area, min. dimension, designed

grate Cast in Place Refer to 313 Some criteria listed Prefab Structures

  • Listed in Database (online only)
  • No structural mods (ex. no attaching

pumps to tank walls) p p ) Manhole Base must be monolithic riser and floor

slide-21
SLIDE 21

Specific Criteria p

Reception Structures, Channels, Hoppers, Pumps Reception Structures, Channels, Hoppers, Pumps

Existing (tanks and pumps) New (tanks and pumps) Pump Must follow Pumping Plant Standard W S F Penetration Must follow 634 SPECIFICATION W.S.F. Penetration Must follow 634 SPECIFICATION Solid Liquid Separation Basins/tanks/etc must be designed following the 632 Standard following the 632 Standard

slide-22
SLIDE 22

Specific Criteria p

Reception Structure Sizing MANURE CONTAMINATED RUNOFF OR MANURE RUNOFF -OR - WASTEWATER NO RUNOFF NO PRECP RUNOFF and/or PRECP NO RUNOFF NO PRECP RUNOFF and/or PRECP PRECP PRECP EXAMPLE “A”

“B” “C” “D”

slide-23
SLIDE 23

Example A Manure Only p y

*Under floor structures should have 1’ extra depth of safety.

slide-24
SLIDE 24

Example B Manure + H2O p

2

slide-25
SLIDE 25

Example B Manure + H2O on LOT p

2

slide-26
SLIDE 26

Example C Other Waste Only p y

Designed per the appropriate standards (i e sediment basin) typically barnyard or feed Designed per the appropriate standards (i.e. sediment basin) typically barnyard or feed storage runoff system. *Under floor structures should have 1’ extra depth of safety.

slide-27
SLIDE 27

Example D Other Waste + H2O p

2

Designed per the appropriate standards (i e sediment basin) typically barnyard or feed Designed per the appropriate standards (i.e. sediment basin) typically barnyard or feed storage runoff system.

slide-28
SLIDE 28

Specific Criteria {Table 1} p

{ }

slide-29
SLIDE 29

Specific Criteria {pipes} p {p p }

Pipe Transfer Pipe Severe Service Gravity Transfer must meet transfer pipe must meet transfer pipe transfer pipe criteria + additional transfer pipe criteria + criteria in Table 2

slide-30
SLIDE 30

Specific Criteria {transfer pipe} p { p p }

Existing New Pipe Material Table 2 Spec 634 {table 1} Installation Spec 15, 204 Spec 634 Thrust Control ½ yd concrete Designed size {tools available}

slide-31
SLIDE 31
slide-32
SLIDE 32

Specific Criteria {transfer pipe} p { p p }

Existing New Liner Penetration Additional criteria l h

  • min. pipe length
  • concrete restraint
  • meet SPEC. 634

Protect liners from preferential flow Protect liners from preferential flow along pipe

slide-33
SLIDE 33
slide-34
SLIDE 34

Specific Criteria {transfer pipe} p { p p }

New Flow Velocity {national criteria} l 3 6 f

  • Pulsating 3-6 fps
  • May exceed 6 fps if system takes into account during design

Sunlight Pipe must withstand UV throughout the design life

  • UV resistant material or Protect the pipe
  • UV resistant material or Protect the pipe

Marking Mark “at risk” pipe by fences or markers Cl O t R i d l ( i l d) Clean Out Required clean out access (except pipe to cropland) Backflow Required backflow prevention Relief Air Vents and Vacuum Reliefs, use as needed

slide-35
SLIDE 35

Specific Criteria {transfer pipe} p { p p }

Design Factors Design Factors

 Pipe compatible with working pressure

 Don’t forget maintenance and cleaning pressures!

g g p

 Pipe working pressure shall be no less than the Pump

Shut Off Head (a.k.a. the maximum pressure the pump can produce)

 look at all loads and pressures on the pipe and system,

required capacity, etc. required capacity, etc.

slide-36
SLIDE 36

Specific Criteria {severe service} p { }

 Severe Service  Severe Service

 pressure pipes supplying flush water {to flume systems}  pipe with air flushing/blowing risers  pipe with air flushing/blowing risers  pipes to cropland application  NOT gravity pipes

slide-37
SLIDE 37

Specific Criteria {severe service} p { }

 Transfer Pipe Criteria PLUS  Transfer Pipe Criteria PLUS

 check value near pumps  pressure relief valves near pumps  pressure relief valves near pumps  warning signs on all risers stating transfer system

pressure rating

 pipelines for irrigation shall follow Irrigation Water

Conveyance, Pipeline Standard (430)

 pressure testing pipes following Spec 634

slide-38
SLIDE 38

Pipe Testing p g

Before Pressure Testing g

  • a. Solvent welded or heat fused joints cure.

b S i t f i h ll b fl h d d l d

  • b. Severe service transfer pipe shall be flushed and cleaned.
  • c. All thrust control structures shall be in place and cured
  • d. Pipes shall be backfilled or otherwise restrained sufficiently. Braced and/or anchored at

each end to prevent movement. e The ends of the pipe shall be plugged and a pressure gauge shall be attached to the

  • e. The ends of the pipe shall be plugged, and a pressure gauge shall be attached to the

upstream and downstream ends. All high points along the severe service transfer pipe shall be vented to permit the complete removal of all air within the pipe.

slide-39
SLIDE 39

Pipe Testing p g

Filling g Slowly fill the restrained test section completely with clear water. Initial Expansion Phase G d ll i th t t ti ith t t th ki ( ifi d i th Gradually pressurize the test section with water to the working pressure (as specified in the construction plans) plus 10 psi and maintain that pressure for three hours. Test Phase Immediately following the initial expansion phase, reduce test pressure back to working pressure, stop adding water and isolate test section. If test pressure remains steady (within 5% of the target value) for one hour, no leakage is indicated and the test section passes. Depressurizing Following the test phase, and prior to putting the pipe into service, gradually reduce pressure on the test section, drain out and properly dispose of all test water.

slide-40
SLIDE 40

Specific Criteria {gravity transfer} p {g y }

 follow Transfer Pipe Criteria PLUS  follow Transfer Pipe Criteria PLUS  no gravity outlets from w.s.f.  no gravity outlets from load out areas without  no gravity outlets from load out areas without

secondary containment

 gravity transfer from one storage to another shall  gravity transfer from one storage to another shall

have 2 shut off values, {1 manual}

 no max lengths  no max. lengths

slide-41
SLIDE 41

Specific Criteria {gravity transfer} p {g y }

slide-42
SLIDE 42

NEW SPECIFICATION

 lists pipe materials

p p

 installation of pipe

 laying the pipe New Spec

y g p p

 bedding the pipe  backfilling the pipe Spec

 pressure testing  table of approved pipe  standard references of allowed and not

unacceptable pipe

slide-43
SLIDE 43

SPECIFICATION

slide-44
SLIDE 44

Questions