visions of the future
play

Visions of the Future Reduction in Operating Costs Concentrator - PowerPoint PPT Presentation

Increased Productivity Visions of the Future Reduction in Operating Costs Concentrator Improvements in Long Term Sustainability Dr David Way Chief Executive Officer Dr Sarma Kanchibotla Advisor - Mining Introduction www.jktech.com.au


  1. Increased Productivity Visions of the Future Reduction in Operating Costs Concentrator Improvements in Long Term Sustainability Dr David Way Chief Executive Officer Dr Sarma Kanchibotla Advisor - Mining

  2. Introduction www.jktech.com.au

  3. Traditional Process Flowsheet Mine KPI’s : Safety, production tons or Final Product bcm, mining cost/ton etc Mill KPI’s : Safety, throughput, milling cost/ton, recovery etc www.jktech.com.au

  4. Traditional Process Flowsheet • Mine and mill are under different management structures and reporting systems o cost centres • Each process has production targets and cost budgets o endeavours to meet targets and budgets o focus on quantity (volume) rather than quality o Little understanding on the impact on other processes and overall value • KPI’s do not encourage to understand risks and maximise the overall value and risks • Inadequate systems to measure the outcomes in a timely and reliably manner • Inadequate communication between different processes to understand the interactions and changes • Cost focus rather than value maximisation and risk mitigation www.jktech.com.au

  5. Ore Characterisation www.jktech.com.au

  6. Information is Key Adding Value to Project Delivery 140 120 225 Axb values PERCENTAGE OF NAMEPLATE CAPACITY (%) 100 NPV ≈ USD 300 M 80 21 Axb values 60 40 McNulty Series 1 20 Ramp up of Greenfield Copper Concentrators 0 0 1 2 3 4 5 6 7 8 www.jktech.com.au MONTHS

  7. Drill to Mill – Downstream Prediction Using Blast Hole Data www.jktech.com.au

  8. Ore Fragmentation www.jktech.com.au

  9. Ore Fragmentation Opportunities Based on total power draw of 49872 kW for Ab = ~35 Throughput estimates: Lower 95% 1904 tph Mean 2178 tph Upper 95% 2545 tph 7 1 st intervention 2 nd intervention Pre 2011 2011 - 12 6 Mine to Mill Advanced Blast Fragmentation 5 Fragmentation Frequency 4 3 Industry standard 2 3112 3400 2820 1 ? 0 Can we go further Throughput (tph) www.jktech.com.au

  10. Breakage in the Mine-to-Mill Value Chain Energy www.jktech.com.au

  11. Baseline - Current Practise Throughput = 100 F80 = 120 – 150mm Relative energy intensity /unit metal = 100 Relative capital cost / unit metal = 100 Fines = 10 -15% Feed Characteristics Hydrocyclone • F80 > 120mm • Fines (-10mm) < 10 % Recycle • Crusher Ab = 35 • Bwi = 14 • Grade – 5 -10 % dilution D&B cost ≈ $0.30/ton SAG Ball Mill Screen Mill www.jktech.com.au

  12. Best Case – Mine to Mill Practise F80 < 100mm Throughput = 110 - 120 Relative energy intensity /unit metal = 80 - 90 Relative capital cost / unit metal = 100 Fines > 15 - 20% Feed Characteristics Hydrocyclone • F80 < 100mm • Fines (-10mm) > 15 - 20 % Recycle • Crusher Ab = 35 • Bwi = 14 • Grade < 5 % dilution D&B costs ≈ $0.60/ton SAG Ball Mill Screen Mill www.jktech.com.au

  13. Future Feed Integrated Process Model Throughput = 130 - 140 Grade Relative energy intensity /unit metal = 70 - 80 Hardness Each Relative capital cost / unit metal = 100 block Fragmentation Tph Recovery Kwh/t $/t Value / block F80 < 100mm Hydrocyclone Superior Feed Recycle Fines > 40% Crusher Feed Characteristics • F80 < 50mm • Fines (-10mm) > 40 % SAG • Ab = 45 (micro fractures) Ball Mill Screen Mill • Bwi = 12 (micro fractures • Grade < 3 % dilution www.jktech.com.au D&B costs ≈ $1.50/ton

  14. Super Fine Feed with Future Concentrator Throughput > 150 Relative energy intensity /unit metal < 60 Relative capital cost / unit metal < 60 Impact breaker Grizzly 75mm Screen 10mm Feed Characteristics • F80 < 50mm • Fines (-10mm) > 40 % Rolls • Ab = 45 (intense micro fracturing) • Bwi = 10 Crusher • Grade < 2% dilution Ball Mill D&B costs ≈ $1.50 /ton • Δ ≈ $1.00 /ton www.jktech.com.au

  15. Ore Pre - Concentration www.jktech.com.au

  16. Ore Pre - Concentration • Early Gangue Rejection • Reduced Mass for Grinding and Mineral Separation • Reduced Maintenance in Comminution Circuit www.jktech.com.au

  17. Classification www.jktech.com.au

  18. Classification Typical product size Recovery losses P 80 Recovery Optimum Recovery losses + range for % energy + grind size passing slimes Size Leverage of classification? • Energy savings • Minimise production of slimes www.jktech.com.au

  19. Classification www.jktech.com.au

  20. Classification - Opportunities Site energy Circulating load Throughput Flotation Feed P 80 consumption in ball mill circuit Water Consumption Valuables Recovery www.jktech.com.au

  21. Classification – JKMRC Research • JKTech Promoted Research - Current Hydrocyclone Technology v Screening • Measure the size of the opportunity for screening • Novel Cyclone Design • Proof of concept tests completed with 250mm cyclone with synthetic ores and a real ore • Results show that the new cyclones • Cut much coarser with lower water split compared to standard cyclone • Performance is comparable to that of fine wet screening Actual efficiency curve (d50c=80micron and WS to U/F=30%) Actual efficiency curve (d50c=80micron and Alpha=3) 100.00 120.00 90.00 100.00 Efficiency to U/F [%] 80.00 Efficiency to U/F [%] 70.00 80.00 60.00 60.00 50.00 Alpha=3 WS to U/F=30% 40.00 40.00 Alpha=8 WS to U/F=10% 30.00 20.00 20.00 10.00 0.00 1 10 100 1000 0.00 1 10 100 1000 size [ μ m] size [ μ m] Next Steps: 1. Prototype development and detailed parametric testing www.jktech.com.au 2. Industrial testing

  22. Flotation & Regrind www.jktech.com.au

  23. Effect of Flotation Feed Size on Overall Performance 500 100 450 Overall Metal Recovery at Target Grade Metal Sulphide Liberation, % 80 Throughput Relative to Basecase, % 400 Typical Region for & Metal Recovery, % 350 Optimum Flotation Recovery 60 300 Metal Sulphide Liberation for Rougher Flotation Feed 250 40 80kt/a Metal in 56kt/a Metal in Concentrate 200 Concentrate 3kt/a Metal in 20 Tailings 43% 150 100 Potential Throughput Variation 0 per unit time 50 -20 0 50 100 150 200 250 300 350 Primary Grind Size, (P 80 microns) www.jktech.com.au

  24. Liberation for Rougher Recovery Target - Low Grade Composite Particles Floatable Non - Floatable Valuable Sulphide or Precious Mineral A Valuable Sulphide or Precious Mineral B Gangue Mineral www.jktech.com.au

  25. Low Grade Composite Flotation – Some Considerations • Increase in Rougher Concentration Mass Recovery • More Regrind Capacity • Staged Regrind David Way, Principal Metallurgist, Xstrata Copper Kenton Maloney, Project Metallurgist, Xstrata Copper Reference: D. Way & K. Maloney, Mill Optimisation, March 2011, Optimisation of Regrind Power for the Tampakan Copper – Gold Project www.jktech.com.au

  26. Conclusions www.jktech.com.au

  27. Future Concentrator Process Flowsheet • Mine and Concentrator as one business unit • Integrate and optimise the total process rather than an individual process • Focus on maximising the overall value and minimising the risk to total business rather than unit cost minimisation • Understand the interactions between the key processes in value chain Geology / Planning Flotation Drilling Maximise Value & Grinding Blasting Minimise Risks Crushing Loading Hauling www.jktech.com.au

  28. Future Concentrator Opportunities • Improved Ore Characterisation • Comminution & Waste Rejection Starts in the Mine • Ore Pre - Concentration • Classification • Separating Coarser Particles containing Lower Valuable Mineral Content • Higher Rougher Mass Recoveries • Staged Regrind and Flotation • Improved Dewatering • Reduced Environmental Exposure Not Considered but Important • Separation and Water Chemistry, Mill Design Options, Flotation Cell Options, etc … www.jktech.com.au

  29. Breakage in the Future Process Flowsheet 100% Sag Mill Product 80% Crusher Flotation ROM Product Feed 60% Cum % passing 40% 20% In-situ 0% 1000 0.1 1 10 0.01 100 Size mm www.jktech.com.au

  30. Contact Us For More Information Social Media Head Office Website & Email JKTech South America SpA Facebook.com/ JKTech.Pty.Ltd 40 Isles Road www.jktech.com.au Av. Vitacura 2670, Piso 15 Twitter.com/jktech Indooroopilly QLD 4068 jktech@jktech.com.au Las Condes Santiago AUSTRALIA CHILE Phone : +61 7 3365 5842 Phone: +56 2 2820 4355 www.jktech.com.au

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend