Visions of the Future Concentrator
Increased Productivity Reduction in Operating Costs Improvements in Long Term Sustainability
Dr David Way Chief Executive Officer Dr Sarma Kanchibotla Advisor - Mining
Visions of the Future Reduction in Operating Costs Concentrator - - PowerPoint PPT Presentation
Increased Productivity Visions of the Future Reduction in Operating Costs Concentrator Improvements in Long Term Sustainability Dr David Way Chief Executive Officer Dr Sarma Kanchibotla Advisor - Mining Introduction www.jktech.com.au
Visions of the Future Concentrator
Increased Productivity Reduction in Operating Costs Improvements in Long Term Sustainability
Dr David Way Chief Executive Officer Dr Sarma Kanchibotla Advisor - Mining
www.jktech.com.au
www.jktech.com.au
Final Product Mill KPI’s : Safety, throughput, milling cost/ton, recovery etc Mine KPI’s : Safety, production tons or bcm, mining cost/ton etc
www.jktech.com.au
systems
and risks
manner
interactions and changes
www.jktech.com.au
www.jktech.com.au
Adding Value to Project Delivery
20 40 60 80 100 120 140 1 2 3 4 5 6 7 8
PERCENTAGE OF NAMEPLATE CAPACITY (%) MONTHS
Ramp up of Greenfield Copper Concentrators
225 Axb values 21 Axb values McNulty Series 1
NPV ≈ USD 300 M
www.jktech.com.au
www.jktech.com.au
www.jktech.com.au
1 2 3 4 5 6 7 Frequency Throughput (tph)
Can we go further
Industry standard
Based on total power draw of 49872 kW for Ab = ~35 Throughput estimates: Lower 95% 1904 tph Mean 2178 tph Upper 95% 2545 tph 2820 1st intervention Pre 2011 Mine to Mill Fragmentation 3112 2nd intervention 2011 - 12 Advanced Blast Fragmentation 3400
www.jktech.com.au
Energy
www.jktech.com.au
Throughput = 100 Relative energy intensity /unit metal = 100 Relative capital cost / unit metal = 100
SAG Mill Ball Mill Screen Recycle Crusher Hydrocyclone
Feed Characteristics
D&B cost ≈ $0.30/ton
Fines = 10 -15% F80 = 120 – 150mm
www.jktech.com.au
Throughput = 110 - 120 Relative energy intensity /unit metal = 80 - 90 Relative capital cost / unit metal = 100
SAG Mill Ball Mill Screen Recycle Crusher Hydrocyclone
Feed Characteristics
D&B costs ≈ $0.60/ton
Fines > 15 - 20% F80 < 100mm
www.jktech.com.au
Throughput = 130 - 140 Relative energy intensity /unit metal = 70 - 80 Relative capital cost / unit metal = 100
SAG Mill Ball Mill Screen Recycle Crusher Hydrocyclone
Each block
Integrated Process Model
Grade Hardness Fragmentation
Tph Recovery Kwh/t $/t Value / block
Feed Characteristics
D&B costs ≈ $1.50/ton
F80 < 100mm Fines > 40%
Superior Feed
www.jktech.com.au
Ball Mill
75mm 10mm
Impact breaker Rolls Crusher Grizzly Screen Feed Characteristics
D&B costs ≈ $1.50 /ton
Throughput > 150 Relative energy intensity /unit metal < 60 Relative capital cost / unit metal < 60
www.jktech.com.au
www.jktech.com.au
www.jktech.com.au
www.jktech.com.au
Optimum range for grind size Size Recovery % passing P80 Typical product size
Recovery losses Recovery losses + energy + slimes
Leverage of classification?
www.jktech.com.au
www.jktech.com.au
Water Consumption Site energy consumption Throughput Circulating load in ball mill circuit Flotation Feed P80 Valuables Recovery
www.jktech.com.au
0.00 20.00 40.00 60.00 80.00 100.00 120.00 1 10 100 1000
Efficiency to U/F [%] size [μm]
Alpha=3 Alpha=8 0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00 1 10 100 1000
Efficiency to U/F [%] size [μm]
WS to U/F=30% WS to U/F=10%
Actual efficiency curve (d50c=80micron and WS to U/F=30%) Actual efficiency curve (d50c=80micron and Alpha=3)
Next Steps:
www.jktech.com.au
www.jktech.com.au
50 100 150 200 250 300 350 400 450 500
20 40 60 80 100 50 100 150 200 250 300 350
Metal Sulphide Liberation, % & Metal Recovery, % Primary Grind Size, (P80 microns) Throughput Relative to Basecase, %
Overall Metal Recovery at Target Grade Metal Sulphide Liberation for Rougher Flotation Feed Potential Throughput Variation
Typical Region for Optimum Flotation Recovery
56kt/a Metal in Concentrate
80kt/a Metal in Concentrate 3kt/a Metal in Tailings
www.jktech.com.au
Valuable Sulphide or Precious Mineral A Valuable Sulphide or Precious Mineral B Gangue Mineral
Floatable Non - Floatable Target - Low Grade Composite Particles
www.jktech.com.au
Reference: D. Way & K. Maloney, Mill Optimisation, March 2011, Optimisation of Regrind Power for the Tampakan Copper – Gold Project
David Way, Principal Metallurgist, Xstrata Copper Kenton Maloney, Project Metallurgist, Xstrata Copper
www.jktech.com.au
www.jktech.com.au
unit cost minimisation
Maximise Value & Minimise Risks
Geology / Planning Drilling Blasting Loading Hauling Crushing Grinding Flotation
processes in value chain
www.jktech.com.au
Not Considered but Important
www.jktech.com.au
1000 0% 20% 40% 60% 80% 100% 0.01 0.1 1 10 100 Size mm Cum % passing
In-situ Sag Mill Product ROM Crusher Product Flotation Feed
www.jktech.com.au
Head Office
40 Isles Road Indooroopilly QLD 4068 AUSTRALIA Phone : +61 7 3365 5842
JKTech South America SpA
Las Condes Santiago CHILE Phone: +56 2 2820 4355
Website & Email
www.jktech.com.au jktech@jktech.com.au
Social Media
Facebook.com/ JKTech.Pty.Ltd Twitter.com/jktech
For More Information