SLIDE 1 1
828 South Broadway, Tarrytown, NY 10591 914.478.4527 f: 914.478.4527 www.riverkeeper.org
VIA E-MAIL AND FIRST-CLASS MAIL January 12, 2010 Secretary U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 ATTN: Rulemakings and Adjudications Staff Rulemaking.Comments@nrc.gov Re: Riverkeeper, Inc.‟s Comments on the U.S. Nuclear Regulatory Commission‟s Proposed Revisions to NUREG-1437, Generic Environmental Impact Statement for License Renewal
Dear Rulemakings and Adjudications Staff: Riverkeeper, Inc. (“Riverkeeper”) hereby respectfully submits the following comments in response to the U.S. Nuclear Regulatory Commission‟s (“NRC”) Proposed Rule, “Revisions to Environmental Review for Renewal of Nuclear Power Plant Operating Licenses,” 74 Fed. Reg. 38,117, 10 C.F.R. Part 51, RIN 3150-AI42, NRC-2008-0608 (July 31, 2009) (hereinafter “Proposed Rule”), and associated draft documents, including: NUREG-1437, Volume 1, Revision 1, “Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Main Report,” Draft Report for Comment (June/July 2009) (hereinafter “Revised GEIS”); NUREG-1437, Volume 2, Revision 1, “Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Appendices,” Draft Report for Comment (June/July 2009) (hereinafter “Revised GEIS Appendices”); NUREG-1555, Supplement 1, Revision 1, “Standard Review Plans for Environmental Reviews of Nuclear Power Plants, Supplement 1: Operating License Renewal,” Draft Report for Comment (July 2009), (hereinafter “Draft Revised SRP”); Draft Regulatory Guide DG-4015, “Preparation of Environmental Reports for Nuclear Power Plant License Renewal Applications,” Revision 1 (July 2009) (“hereinafter Draft
For the reasons set forth below, the proposed regulatory revisions fail to adequately address numerous fundamental deficiencies with the current environmental review process for nuclear
SLIDE 2
2
power plant license renewal. Riverkeeper, therefore, urges the NRC to fully address the concerns identified herein prior to finalizing the proposed changes. I. RIVERKEEPER’S INTEREST Riverkeeper is a member-supported, not-for-profit organization dedicated to protecting the Hudson River and its tributaries.1 Since its inception in 1966, Riverkeeper has used litigation, science, advocacy, and public education to raise and address concerns relating to the Indian Point nuclear power plant, located on the eastern bank of the Hudson River in Buchanan, NY. Riverkeeper is headquartered in Tarrytown, New York, approximately twenty-two (22) miles from the Indian Point facility, and has numerous members that reside within at least fifty (50) miles of the plant.2 Riverkeeper has been actively involved in the Indian Point license renewal proceeding due to the serious concerns relating to the continued operation of the facility, including the environmental damage caused by its antiquated once-through cooling system and leaking spent fuel pools, the vulnerability of the plant‟s spent fuel pools to terrorist attacks and serious accidents, and the failure of any long-term solution for permanent nuclear waste disposal. Riverkeeper filed a successful petition to intervene in Indian Point‟s relicensing proceeding, raising various environmental and safety concerns, and is currently litigating three contentions which have been admitted for an adjudicatory hearing.3 Riverkeeper has consistently raised concerns with the adequacy of the environmental review process the NRC is currently still undertaking in the Indian Point relicensing case. Riverkeeper submitted extensive environmental scoping comments, as well as comments on the supplemental site-specific environmental impact statement prepared in relation to the Indian Point relicensing proceeding, both times heavily criticizing the NRC‟s improper reliance on the outdated 1996 Generic Environmental Impact Statement for License Renewal of Nuclear Plants (hereinafter “1996 GEIS”).4 The NRC‟s use of the 1996 GEIS has done a great disservice to the Indian Point license renewal process, by failing to ensure sufficient analysis of all relevant concerns. The
1 See generally, Riverkeeper.org, Our Story, http://www.riverkeeper.org/ourstory_index.php (last visited Jan. 12,
2010).
2 See Riverkeeper.org, Contact Us, http://www.riverkeeper.org/contact/ (last visited Jan. 12, 2010). 3 See Riverkeeper, Inc.‟s Request for Hearing and Petition to Intervene in Indian Point License Renewal Proceeding,
November 30, 2007 (hereinafter “Riverkeeper Petition for Hearing”), ADAMS Accession No. ML073410093. Riverkeeper‟s Petition for Hearing raised many concerns relevant to the issues discussed in the Revised GEIS, and Riverkeeper provides this petition in further support of the comments made herein, for your consideration, as Exhibit B.
4 Many of the concerns articulated in Riverkeeper‟s Indian Point license renewal environmental scoping comments
and supplemental site-specific environmental impact statement comments would remain unresolved by the NRC‟s Revised GEIS, and Riverkeeper provides them as exhibits in further support of the comments made herein, for your consideration in the instant rulemaking proceeding: Riverkeeper Comments on Environmental Scoping for the Indian Point License Renewal Proceeding, Docket Nos. 50-247, 50-286 (Oct. 12, 2007), ADAMS Accession No. ML072960455 (hereinafter “Riverkeeper‟s Scoping Comments), are attached hereto as Exhibit C; Riverkeeper Comments on Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 38, Regarding Indian Point Nuclear Generating Unit Nos. 2 and 3, Draft Report for Comment (March 18, 2009), ADAMS Accession No. ML090860983 (hereinafter “Riverkeeper‟s IP DSEIS Comments”), are provided herewith as Exhibit D.
SLIDE 3 3
NRC‟s attempt to now belatedly revise the 1996 GEIS continues to fall short of guaranteeing a comprehensive environmental review process in license renewal proceedings. Riverkeeper now
- ffers the following comments to highlight our ongoing concerns, in order to ensure that the
NRC carries out adequate environmental reviews in the future. II. IMPROPER FOCUS ON “STREAMLINING” The Proposed Rule repeatedly emphasizes that the changes made by the Revised GEIS will “simplify and streamline the NRC review process.5 Understanding the efficacy of having generic EISs pursuant to the National Environmental Policy Act of 1969 (“NEPA”), i.e., to avoid unnecessary repetition of review, a reading of the Proposed Rule leads one to surmise that the NRC‟s primary concern was how to further streamline the process. Indeed, the NRC proudly touts that “[t]he 1996 GEIS has been effective in focusing NRC resources on important environmental issues and increased efficiency of the environmental review process. Currently, 51 nuclear units at 29 plant sites have received renewed licenses.”6 Yet, the focus of the NRC should be on performing an objective, NEPA-compliant, comprehensive review and not to efficiently get reviews done at breakneck speed. This misplaced emphasis has manifested itself throughout the Revised GEIS, in the failure of the NRC to provide for adequate review of various environmental issues, as discussed forthwith.
- III. INADEQUATE ASSESSMENT OF INADVERTENT RADIOACTIVE RELEASES
TO THE ENVIRONMENT The Revised GEIS acknowledges the problem encountered at various nuclear power plants across the country over the past several years of unplanned releases of radionuclides to the
- environment. Given this ongoing issue, it is critical that the license renewal environmental
review process address all relevant concerns posed by such releases. Unfortunately, the NRC‟s proposed revisions to the 1996 GEIS do not go far enough toward ensuring that the environmental impacts of such releases will be analyzed in a comprehensive manner. A History of Inadvertent Radioactive Releases to the Environment Unplanned releases of radionuclides to the environment have become ubiquitous at nuclear power plants across the United States. To date, leaks from varying plant systems have occurred at 29 plants in the United States, nearly a third of the United States‟ operating fleet. Riverkeeper has compiled documentation related to these leaks, attached hereto as Exhibit A, for your consideration in this rulemaking proceeding. It is imperative that the update to the 1996 GEIS fully address any and all relevant concerns. Unfortunately, as discussed below, the Revised GEIS as proposed would not ensure a comprehensive review of this issue.
5 See, e.g., Proposed Rule at 38,123, 38,124, 38,126, 38,128. 6 Id. at 38,119.
SLIDE 4
4
Revised Assessment of Groundwater Resources The NRC proposes to add a new Category 2 issue to address radionuclides released to groundwater.7 It is in this portion of the Revised GEIS that the NRC recognizes the reality of inadvertent releases of radionuclides: “There is a growing concern about radionuclides detected in groundwater at nuclear power plants. These releases have occurred as leaks in at least 14 plants.”8 However, as discussed in more detail below, it is apparent that the Revised GEIS would not require consideration of the environmental impacts of such releases in relation to other “resources areas,” i.e. aquatic ecology, terrestrial resources, and threatened/endangered species. Providing for such a narrow assessment related only to impacts to groundwater would lead to a narrow and incomplete analysis of the impacts of such releases to the environment. As discussed below, the NRC must require a comprehensive site-specific analysis of the impacts of accidental releases on all relevant environmental media. This is the only way to ensure a thorough assessment and accurate conclusions as to significance of such inadvertent contamination. The newly proposed Category 2 issue to address radionuclide releases to groundwater is problematic for other reasons as well. While the Proposed Rule implies a focus on an assessment of public health impacts, the Revised GEIS and associated guidance documents notably fail to provide concrete direction to ensure adequate analysis related to such impacts. Instead, the Draft Revised SRP and Draft Reg. Guide 4015 provide vague directives, mostly emphasizing assessment of groundwater monitoring systems.9 The Revised GEIS even appears to largely dismiss public health concerns, stating that “[t]he NRC does not consider these tritium releases to be a health risk to the public or onsite workers in any of these [previously reported] cases because the tritiated groundwater is expected to remain onsite.”10 The NRC should provide more specific guidance to ensure that licensees and the NRC accurately assess all reasonably foreseeable impacts to public health at particular plants. For example, at Indian Point, licensee/license renewal applicant, Entergy Nuclear Operations, Inc., (hereinafter “Entergy”) acknowledges groundwater contamination that is slowly leaching through the underlying bedrock to the Hudson River,11 contrary to the NRC‟s blanket conclusion stating that groundwater contamination has remained onsite. Currently, there is proposed project that would site a desalination plant in Rockland County, New York, across and slightly downstream from Indian Point, which would withdraw Hudson River water for drinking water.12 Far from speculative, this proposal is currently in the planning, environmental review, and permitting stages.13 Accordingly, an appropriate assessment of the impacts of radionuclide releases from the Indian Point facility should include impacts to the public from use of contaminated drinking water. Unfortunately, in the Indian Point relicensing proceeding, the
7 See Revised GEIS at 4-46 to 4-47; Revised GEIS Appendices at B-12. 8 See Revised GEIS at 4-46; see also Proposed Rule, 74 Fed. Reg. at 38,122. 9 See Draft Revised SRP at 4.4.6-1 to 4.4.6-3; Draft Reg. Guide 4015 at 31-32. 10 Revised GEIS at 4-47. 11 See Groundwater Investigation Executive Summary (Indian Point Energy Center, Buchanan, N.Y., Jan. 2008), at
2-4, available at http://jic.semo.state.ny.us/Resources/ExecutiveSummary%20GW%20final.pdf.
12 See generally Riverkeeper‟s IP DSEIS Comments at 22-25. 13 See generally id.
SLIDE 5 5
NRC Staff‟s site-specific Draft Supplemental Environmental Impact Statement14 was completely devoid of assessment of the impacts of license renewal on drinking water quality in regards to the use of the Hudson River as a source of drinking water via the desalination plant.15 Thus, in the instant rulemaking, the NRC must provide clear direction so that any reasonably foreseeable radionuclide exposure to the public, such as through anticipated drinking water sources, will be assessed. Revised Assessment of Aquatic Resources The NRC proposes to add a new issue to address “Exposure of Aquatic Organisms to Radionuclides.”16 While analysis of such impacts is important and necessary, unfortunately, the NRC has misguidedly chosen to label this a Category 1 issue, making a generic determination that such impacts will always be small.17 This is problematic because the NRC‟s consideration of this issue is limited to the impact of radionuclides on aquatic organisms from normal operations.18 Normal operations, by definition, do not include accidental releases of radionuclides from a facility. As such, the NRC‟s analysis here on its face excludes consideration of the impacts to aquatic biota from inadvertent releases, despite the earlier recognition that this has been a problem.19 Instead, the NRC relies on past Radiological Environmental Monitoring Program reports of 15 nuclear power plants to conclude that “normal operations of these facilities would not result in negative effects on aquatic biota.”20 With the noted history of accidental releases at the nation‟s nuclear power plants, it is absolutely necessary to specifically consider such releases when evaluating impacts to aquatic resources. Given the nature of this ongoing problem, and the likelihood of future unplanned releases, this is simply not an issue that is appropriate for one generic determination at this time. Instead, the NRC should make this a Category 2 issue and require licensees and NRC Staff to specifically consider the impacts of any known inadvertent releases to the environment on aquatic biota at the time of license renewal. This would ensure a full assessment of any impacts to aquatic resources, including nearby critical ecosystems, which are not otherwise specifically encompassed by the Revised GEIS‟s generic analysis.
14 Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 38, Regarding
Indian Point Nuclear Generating Unit Nos. 2 and 3, Draft Report for Comment, Main Report (U.S. Nuclear Regulatory Commission December 2008) (“Indian Point Draft Supplemental EIS”), available at, http://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/sr1437/supplement38/ (last visited Jan. 12, 2010).
15 See Indian Point Draft Supplemental EIS at §§ 2.2.7, 4.3. 16 Revised GEIS at 4-98 to 4-100; Revised GEIS Appendices at B-22. 17 Revised GEIS at 4-98 to 4-100; Revised GEIS Appendices at B-22. 18 See Revised GEIS at 4-98 (“The potential impacts of radionuclides on aquatic organisms from normal operations
- f a nuclear power plant during the license renewal term were not identified as an issue in the 1996 GEIS”)
(emphasis added); id. at 4-99 (“Thus, it is anticipated that normal operations of these facilities would not result in negative effects on aquatic biota”) (emphasis added).
19 Revised GEIS at 4-46 (“There is a growing concern about radionuclides detected in groundwater at nuclear power
- plants. These releases have occurred as leaks in at least 14 plants.”)
20 Id. at 4-99.
SLIDE 6 6
For example, the Indian Point nuclear power plant is adjacent to the ecologically critical area of Haverstraw Bay. Haverstraw Bay is a New York State designated Essential Fish Habitat and Significant Coastal Fish and Wildlife Habitat.21 Despite the considerable amount of inadvertent radionuclide releases from Indian Point over the past few decades, Entergy and the NRC Staff have consistently refused to assess the impacts to the Hudson River ecosystem in the Indian Point license renewal proceeding.22 Under the proposed changes to the 1996 GEIS, site-specific impacts of unplanned radionuclide releases on aquatic biota would continue to evade assessment. This is utterly illogical, and completely inconsistent with the NRC‟s recognition that inadvertent releases are an ongoing issue. Revised Assessment of Terrestrial Resources The NRC also proposes a new Category 1 issue to address “Exposure of Terrestrial Organisms to Radionuclides.”23 While the intention of this new issue is admirable, it suffers from the same problems articulated above. In particular, this issue, once again, only applies to radioactive releases from normal operations.24 Based on this assumption, the NRC made a generic determination that impacts to terrestrial resources are small.25 However, it is necessary for the NRC to require consideration of radioactive releases that are not part of the normal course of operation.26 This would be the only way ensure an accurate and complete assessment of impacts to terrestrial biota. Accordingly, the NRC should make this a Category 2 issue and require licensees and the NRC Staff to look at radionuclide impact to terrestrial resources on a site-specific basis.
21 See Coastal Fish & Wildlife Habitat Rating Form,
http://www.nyswaterfronts.com/downloads/pdfs/sig_hab/hudsonriver/Haverstraw_Bay.pdf (last accessed Jan. 12, 2010).
22 See Entergy, Inc., License Renewal Application, Appendix E: Applicant‟s Environmental Report, Operating
License Renewal Stage, Indian Point Energy Center (ER), available at, http://www.nrc.gov/reactors/operating/licensing/renewal/applications/indian-point.html; Indian Point Draft Supplemental EIS at §§ 2.2.7, 4.3.
23 See Revised GEIS at 4-55 to 4-58; Revised GEIS Appendices at B-12. 24 See Revised GEIS at 4-55 (“Releases into terrestrial environments often result from deposition of small amounts
- f radionuclide particulates released from power plant vents during normal operations”) (emphasis added); id. at 4-
58 (“[T]he NRC concludes that the impact of routine radionuclide releases from past and current operations on terrestrial biota would be small at all nuclear power plants and would not be expected to appreciably change during the renewal period”) (emphasis added).
25 See Revised GEIS at 4-58; Revised GEIS Appendices at B-12. 26 For example, Indian Point has a noted history of unplanned radiological releases which have the potential to affect
the surrounding terrestrial environment; in addition to the extensive releases from underground piping and the plants spent fuel pools, which the NRC and Entergy have both acknowledged, the most recent example involved a release
- f radioactive steam resulting from an unplanned shutdown at the plant. See Abby Luby, Nuclear Steam Leak
Intentional: Response to Indian Point Plant Shutdown, New York Daily News (Jan. 8, 2010), http://www.nydailynews.com/ny_local/2010/01/08/2010-01- 08_nuclear_steam_leak_intentional_response_to_indian_point_plant_shutdown.html (last visited Jan. 12, 2010).
SLIDE 7 7
Revised Assessment of Threatened/Endangered Species The Revised GEIS would expand the scope of a existing Category 2 issue related to threatened or endangered species to include “essential fish habitats.”27 Riverkeeper believes this addition is an improvement to this assessment. Riverkeeper further commends the NRC for recognizing that releases of radionuclides to the environment have the potential to impact threatened, endangered, and protected aquatic species, and essential fish habitats. In particular, the Revised GEIS acknowledges that terrestrial and aquatic threatened, endangered, and protected species, and essential fish habitats could be affected by, inter alia, “exposure to radionuclides.”28 While this explicit recognition is a departure from the 1996 GEIS, Riverkeeper remains apprehensive that licensees and the NRC Staff would continue to fail to fully address the impacts
- f inadvertent radioactive releases to the environment on threatened, endangered, and protected
species, and essential fish habitats, since there is no explicit requirement that such impacts be
- evaluated. For example, the Draft Revised SRP simply requires that site-specific supplemental
environmental impact statements present a “list of adverse impacts to listed and proposed threatened or endangered species or critical habitats from continued operations during the renewal term and refurbishment.”29 Given the discussion in the Revised GEIS recognizing potential impacts from radionuclides, license renewal applicants and NRC Staff assessments of this issue should ostensibly include adverse impacts caused by radionuclide contamination, both from normal operations as well as inadvertent releases. However, with the noted history of accidental radioactive contamination at nuclear power plants, and the tendency to evade full review of this issue, as evidenced from the discussion above, a more explicit requirement is preferable.30 Failure to specifically require this analysis will lead to inadequate environmental reviews of this
- issue. For example, in the Indian Point license renewal proceeding, Entergy‟s Environmental
Report and the NRC Staff‟s Indian Point Draft Supplemental EIS lack any assessment of the potential effects on threatened or endangered species caused by groundwater contamination at the facility. Despite leakage of extensive amounts of highly toxic radionuclides from the IP1 and IP2 spent fuel pools, including strontium-90 and tritium, into the groundwater around the plant, the environmental review documents completed by the license renewal applicant and the NRC Staff at no point assesses the effects of such contamination on the Hudson River‟s federally listed shortnose sturgeon, or candidate species, Atlantic sturgeon.31 This is particularly concerning due to the known dangers of exposure to these radioactive substances: strontium-90 imitates calcium by concentrating in fish bones and shells of clams and blue crab; clams are a major part of the diet of sturgeon found in the Hudson River. Therefore, concern that Hudson
27 See Revised GEIS at 4-71 to 4-77; Revised GEIS Appendices at B-24. 28 Revised GEIS at 3-73, 4-111, 4-112. 29 Draft Revised SRP at 4.5.5-5. 30 In the newly required essential fish habitat assessment under the Magnuson-Stevens Fishery Conservation and
Management Act, “adverse impact” is defined as including “direct or indirect physical, chemical, or biological alterations of the waters or substrate and loss of, or injury to, benthic organisms, prey species and their habitat, and
- ther ecosystem components, if such modifications reduce the quality and/or quantity of EFH.” Draft Revised SRP
at 4.5.5-2. This would ostensibly cover accidental radionuclide contamination, but once again, an overt requirement in light of the ongoing problem is preferable.
31 See Indian Point Draft Supplemental EIS at 4-49 to 4-53
SLIDE 8 8
River sturgeon are being exposed to elevated levels of such dangerous substances, is wholly
- warranted. It is, therefore clear that the environmental review in the Indian Point relicensing
case was lacking in this regard. The NRC must, therefore, explicitly require consideration of radionuclide contamination to avoid such deficient assessments in the future. Assessment of Decommissioning Impacts The Revised GEIS proposes to make a generic Category 1 determination as to impacts of relicensing on decommissioning.32 However, this appears to be inconsistent with the NRC‟s recognition of the problem of radioactive contamination. Based on the discussion above, past, current, and future inadvertent releases will undoubtedly have an impact on water quality, ecological resources, and aquatic resources at the time of decommissioning. Accordingly, it is necessary to require site-specific analysis of the impacts of any unplanned leaks in regards to this issue as well. Need for a Comprehensive Framework to Assess Inadvertent Radionuclide Releases As discerned from the discussion above, it is evident that the Revised GEIS will not ensure a complete evaluation of the environmental impacts of inadvertent radionuclide releases from nuclear power plant facilities. NRC must implement a comprehensive framework to ensure that all aspects of such contamination are properly assessed. At a minimum, NRC must ensure that the impacts of unintended radionuclide releases on groundwater, aquatic ecology, terrestrial resources, and threatened, endangered, and protected species, and essential fish habitats, are all Category 2 issues, with specific requirements for appropriate assessment, as indicated above. However, preferably, the NRC should put all of these issues under one umbrella issue, to ensure that an all-inclusive review occurs. Indeed, separating all of the individual environmental effects
- f accidental radioactive contamination does a disservice to the environmental review process by
disallowing a look at the overall, collective impacts of this issue. Notably, the NRC‟s proposed method of analyzing radionuclide contamination as articulated throughout the Revised GEIS would lead to inconsistencies in the review process. For example, the NRC would apparently require a Category 2 site-specific assessment of radionuclide impact to threatened, endangered, and protected species, and essential fish habitats, however, makes a generic Category 1 determination with respect to the impacts of radionuclides on aquatic
- rganisms. Thus, for example, while the impacts of radioactive contamination to certain
federally listed fish species would require extra analysis, the impacts to the majority of fish species would be categorically dismissed as small. This makes no sense, and, in fact, only serves to prove that Category 2 analysis is warranted in relation to effects on aquatic resources from inadvertent radioactive contamination. Furthermore, instead of a comprehensive review, the NRC‟s Revised GEIS envisions a narrow assessment of inadvertent releases that would essentially focus on impacts to groundwater and associated public exposure pathways. To the contrary, NEPA requires a broader evaluation of
32 See Proposed Rule at 38,128; Revised GEIS Appendices at B-40.
SLIDE 9 9
environmental impacts beyond mere public health concerns.33 The significance of any radiological release is governed by the CEQ regulation defining “significantly”; this definition requires consideration of the context of the action and intensity or severity of the impacts.34 Accordingly, in order to accurately evaluate the significance of inadvertent radiological release, license renewal applicants and the NRC Staff must fully assess all of the impacts to the surrounding natural environment. Thus, the need for a comprehensive site-specific review of impacts to all relevant environmental media is apparent. For example, in the Indian Point license renewal proceeding, Entergy and the NRC Staff‟s environmental analysis of the leaks from the Indian Point spent fuel pools was seriously
- deficient. In that proceeding, the relevant environmental analyses focused solely on radiological
doses to humans from the proclaimed “only” exposure pathway, i.e., consumption of aquatic
- foods. 35 By determining that the leaks did not exceed public radiation dose limits via
consumption of aquatic foods, the NRC Staff concluded that the leaks did not have a significant impact on “plant workers, the public, or the environment.”36 In their reviews, Entergy and the NRC Staff did not perform any analysis of the impacts of the contamination to the Hudson River
- ecosystem. In particular, Entergy‟s Environmental Report and the NRC Staff‟s Indian Point
Draft Supplemental EIS failed to determine if toxic radionuclides including strontium-90 and cesium-137 are bioaccumulating in the environment; there was no analysis of the contamination to Hudson River fish or shellfish despite sampling showing elevated levels of such radionuclides in fish; there was no assessment of the effects of the contamination to the nearby essential fish habitat and ecologically critical area of Haverstraw Bay; and, as discussed above, there was no assessment of the potential effects of the leaking on the Hudson River‟s federally listed endangered species, including the short-nosed sturgeon.37 If the Revised GEIS is implemented as proposed, such an inadequate review would continue to be acceptable, since no site-specific review of impacts of radionuclides on terrestrial/aquatic/endangered, etc resources would be required. It is, thus, clear that the Revised GEIS must be adjusted to provide for a comprehensive review of impacts of radionuclide releases on all relevant resources. Moreover, any complete assessment of inadvertent radioactive releases to the environment must specifically include an analysis of the cumulative impact of such contamination. For example, in the Indian Point relicensing proceeding, neither Entergy nor the NRC Staff performed any evaluation of the cumulative long-term effects of the contaminated groundwater plumes at Indian
- Point. The NRC Staff cited Entergy‟s removal of spent fuel from the IP1 pool as evidence that
impacts from the contamination would be minimized.38 Entergy made further claims that leaking is no longer active at the facility, a claim that is dubious at best, as explained in Riverkeeper‟s
33 See Marsh v. Oregon Natural Resources Counsel, 490 U.S. 360, 374 (1989). 34 See 40 C.F.R. § 1508.27 (requiring analysis of ten different factors). 35 Indian Point Draft Supplemental EIS § 2.2.7, at 2-107 to 2-108; § 4.3, § 4.5, § 4.7. In addition to incorrectly
relying on dose limits as a sole measurement of the impacts from the leaks, the NRC Staff‟s assessment of dose limits was also fundamentally flawed since it did not take into consideration the proposed desalination plant, discussed above, that is likely to result in a direct drinking water pathway.
36 Indian Point Draft Supplemental EIS §§ 4.3, 4.5, 4.7 (emphasis added). 37 See generally id. 38 Id. § 4.3, at 4-36.
SLIDE 10 10
Petition for Hearing. However, the extensive leakage that has emanated from the Indian Point spent fuel pools to date is still in the groundwater and will continue to slowly leach into the Hudson River.39 Whether leaking is active or not, it is undisputed that there has never been an assessment of the environmental impacts of this contamination. Current and future accidental radioactive releases from the plant will only add to the existing plumes. For example, an underground pipe leak at the facility in February 2009 resulted in over 100,000 gallons of tritiated water being released directly into the waterway.40 It is, therefore, imperative that the NRC specifically require an evaluation of the cumulative environmental impacts of inadvertent radioactive releases at nuclear power plant sites. In contrast, the Revised GEIS‟s new Category 2 issue requiring analysis of cumulative impacts41 would not necessarily require such an assessment. The Revised GEIS explains that an “analysis
- f cumulative impacts focuses on the resources that could be affected by the incremental impacts
from continued operations of the nuclear plant” and that “[p]ast and present actions include all actions up to and including the time of the license renewal application.”42 And yet, despite the fact that repeated inadvertent releases of radionuclides can have an incremental impact on the surrounding environment, this new Category 2 issue does not explicitly require consideration of this issue. Other than stating that the cumulative impacts on terrestrial and aquatic resources would include habitat degradation,43 the Revised GEIS does not provide any specific guidance that would ensure consideration of the cumulative impact of radioactive contamination. This failure precisely highlights the problem with breaking down this issue into various sections of the Revised GEIS. Only with an all-inclusive review of the environmental impacts of unplanned radioactive contamination will the NRC ever be able to come to an accurate conclusion as to the degree of the overall impact. Accordingly, the NRC must require site-specific assessment of accidental releases on all pertinent environmental media, including terrestrial animals and plants, soils, river sediments, aquatic biota, and endangered/threatened/protected resources, as well as the cumulative impacts thereto. In light of the foregoing, it is also clear that the range of impacts, when taking into account all of the potential environmental consequences of inadvertent radiological release, could be anywhere from SMALL to LARGE.44 Given the long history of widespread contamination at nuclear power plant sites across the country, along with the fact that license renewal proceedings involve continually aging facilities, it is reasonably foreseeable that additional tritium leakage will occur
39 For example, in the months leading up to the completion of draining of the pool at Indian Point Unit 1, Entergy
reported it was leaking around 70 gallons per day, contributing thousands and thousands of additional gallons of polluted water into the groundwater and eventually the Hudson River.
40 See Annie Correal, Indian Pt. Broken Pipe Spurs Safety Worries, THE NEW YORK TIMES (Feb. 27, 2009). 41 See Revised GEIS at 4-220 to 4-227. 42 See id. at 4-220, 4-221. 43 See id. at 4-223, 4-224. 44 Thus, the NRC‟s proposed range of impacts in relation to the new Category 2 issue related to radionuclide release
to groundwater, of “small to moderate,” is unfounded, (see Revised GEIS at 2-9; Revised GEIS Appendices at B- 12), and the conclusion of “small” impact in relation to the two Category 1 issues related to radionuclide impact on terrestrial and aquatic resources, is also unsupported (see Revised GEIS at 2-9, 2-11; Revised GEIS Appendices at B-12, B-22).
SLIDE 11 11
at aging, relicensed plants during their twenty year term of extended operation, and that such leakage could result in “LARGE” impacts to the environment. Indeed, the NRC has offered no support for its assertion that current and future impacts will only be SMALL or MODERATE, beyond simply relying on its belief that the incidences of tritium leakage that have occurred thus far have had no health impacts and minimal environmental impacts, at least according to the NRC‟s assessment. Riverkeeper strongly disagrees with this assertion, as evidenced by the arguments put forth in our intervention petition, environmental scoping comments, and comments to the Draft Supplemental EIS in the Indian Point relicensing proceeding.45 Therefore, the NRC should find that impacts on all media, as explained above, from inadvertent radiological releases to groundwater could be “SMALL, MODERATE OR LARGE.”
- IV. NON-RADIOLOGICAL CONTAMINATION THE ENVIRONMENT
The Revised GEIS would create a new Category 2 issue requiring assessment of non-radiological groundwater and soil contamination resulting from general industrial practices.46 Riverkeeper supports inclusion of this new issue, however, urges the NRC to specifically require that in the course of the assessment of this issue, licensees provide detailed, publicly available inventories
- f any and all spills, leaks, and other releases that contributed to any such soil and groundwater
- contamination. Such a requirement would ensure a more complete evaluation of such
contamination. V. FAILURE TO REQUIRE AN ASSESSMENT OF EMERGENCY PREPAREDNESS A fundamental flaw with the Revised GEIS is the NRC‟s continued narrow scope of the environmental review which, inter alia, precludes assessment of emergency preparedness at nuclear power plants.47 The NRC rationalizes that “[b]efore a plant is licensed to operate, the NRC must have „reasonable assurance that adequate protective measures can and will be taken in the event of a radiological emergency.‟”48 The Revised GEIS further explains how NRC‟s finding of reasonable assurance is founded upon compliance with NRC regulations and guidance, which require that nuclear power plant licensees routinely demonstrate effectiveness of their emergency plans.49 However, this reasoning is flawed since NRC‟s emergency preparedness regulatory scheme is inherently deficient, and, as such, reliance upon those regulations is misguided. Indeed, due to the purely procedural nature of the emergency planning standards found in 10 C.F.R. § 50.47(b), which fail to set actual benchmarks for determining what constitutes a workable emergency plan, there is no guarantee that a particular plan would actually be effective in light of site-specific concerns.50
45 See Riverkeeper Exhibits B, C, D. 46 See Revised GEIS at 4-45 to 4-46. 47 See id. at 1-10, 1-11 (“The NRC will not make a decision or any recommendations on the basis of information
presented in this GEIS regarding emergency preparedness at nuclear power plants.”)
48 See id. at 1-11. 49 See id. 1-11. 50 Riverkeeper explained at length the deficiencies of the emergency preparedness regulatory scheme in recent
comments on a recent proposed update to the emergency planning regulations. See Riverkeeper‟s Comments on NRC‟s Proposed Enhancements to Emergency Preparedness Regulations (Oct. 19, 2009), ADAMS Accession No.
SLIDE 12 12
This is starkly apparent when examining the situation at Indian Point. Of the nations commercial reactor sites, Indian Point, located just 24 miles north of New York City, (35 miles north of Times Square) tops the list as the nuclear power plant with the greatest population density within a 10-mile radius (at least 300,000) and 50-mile radius (approximately 20 million people).51 This represents nearly a doubling of the population since Indian Point‟s initial licensing. This high population density, coupled with the nature of the region‟s infrastructure (prone to severe congestion), present serious impediments to effective emergency evacuation. Indeed, a 2003 traffic study performed for Entergy by KLD Associates determined that evacuation times for the Emergency Planning Zone around Indian Point had doubled since 1994. The original estimate was 2.5 hours for people to proceed with evacuation, with a total of 5.5 hours for complete
- evacuation. KLD‟s 2003 estimates increased mobilization time to 4 hours, while complete
evacuation of the region in good weather conditions could take up to 9.5 hours and in snow conditions up to 12 hours.52 Shadow evacuation, which is not adequately addressed by NRC emergency planning regulations and guidance, would further increase this time. Based on these evacuation time estimates, which apply only to the narrow 10-mile Emergency Planning Zone, it is clear that many residents could not be evacuated in time to avoid exposure to high doses of radiation under a traditional release scenario, much less a fast-breaking release. According to an independent analysis of Indian Point‟s emergency plan commissioned by former New York Governor George Pataki in 2003 and authored by former FEMA director James Lee Witt, the radiological emergency plan for Indian Point is badly flawed, unworkable and key components are unfixable. Witt found that “. . . the current radiological response system and capabilities are not adequate to . . . protect the people from an unacceptable dose of radiation in the event of a release from Indian Point . . . .”53. Even the NRC has voiced concerns associated with the location of Indian Point: in 1979, Robert Ryan, the NRC‟s Director of the Office of State programs, stated “I think it is insane to have a three-unit reactor on the Hudson River in Westchester County, 40 miles from Times Square, 20 miles from the Bronx . . . [Indian Point is]
- ne of the most inappropriate sites in existence.”54
And yet, due to the lack of enforceable standards, NRC consistently finds the requisite “reasonable assurance,” in the Indian Point emergency plan, despite the glaring problems that would hinder effective evacuation at the facility.
ML093100527 (hereinafter “Riverkeeper EP Comments”). Riverkeeper provides these comments in further support
- f the comments made herein, for your consideration in the instant rulemaking proceeding, as Exhibit E.
51 See, e.g., James Lee Witt Associates, LLC, Review of Emergency Preparedness of Areas Adjacent to Indian Point
and Millstone (2003) (hereinafter “Witt Report”) at 4, 81-82. The NRC has previously acknowledged that Indian Point has the “highest population within 10, 30 and 50 miles of any nuclear power plant in the U.S. At 50 miles, it population is more than double any other plant site.” See U.S. Nuclear Regulatory Commission, Consolidated Edison Company of New York: Indian Point, Units 2 and 3, Memorandum and Order, January 8, 1981, at 6; see also Indian Point Draft Supplemental EIS” at Table 2-1.
52 Indian Point Energy Center Evacuation Time Estimate, Tbl. 1-1, p. 1-12, KLD Associates, Inc., 2003. 53 Witt Report at viii. 54 Report of the Office of the Chief Counsel on Emergency Preparedness to the President's Commission on the
Accident at Three Mile Island, October 31, 1979, p. 5.
SLIDE 13 13
The NRC‟s emergency preparedness regulations are further deficient because they fail to fully consider the effects of accidents or intentional attacks involving onsite nuclear waste. The likelihood for such a scenario is not insignificant given the vulnerabilities of such facilities, for example, those at Indian Point: the spent fuel pools at Indian Point are not housed under containment, but rather in non-reinforced cinderblock industrial buildings which are admittedly penetrable by aircraft; the dry casks in the Indian Point ISFSI are stored on an outdoor concrete pad, lined up in rows that are easily visible from the air and the Hudson River. Moreover, numerous reports indicate that nuclear power plants remain likely targets of terrorist attacks.55 The results of such an occurrence could potentially be catastrophic. For example, at Indian Point, an attack on the densely packed IP2 or IP3 spent fuel pools would result in contamination
- f a significant portion of the 10-mile emergency planning zone and the 50-mile ingestion
pathway zone. A 2006 National Academy of Sciences Study concluded that storage pools are susceptible to fire and radiological release from intentional attacks.56 The environmental impacts
- f a fire in a spent fuel pool may be severe, extending over a geographic area larger than a state‟s
legal boundaries and continuing for decades.57 Federal government reports note that a radioactive release could begin in less than an hour. And yet, NRC‟s emergency preparedness scheme, including the pending proposed update, fails to adequately require that nuclear power plant licensees are capable of dealing with such severe radiological consequences.58 This simply further demonstrates how emergency plans may not provide the needed “reasonable assurance” that the public would be protected in the event of an emergency. Therefore, it is clear that compliance with existing emergency preparedness regulations and guidance does not necessarily guarantee adequate emergency preparedness at nuclear power plants in light of all relevant factors. Indeed, the Revised GEIS‟s statement that “[t]hrough its standards and required exercises, the Commission reviews existing emergency preparedness plans throughout the life of any facility, keeping up with changing demographics and other site- related factors,”59 is utterly belied by the foregoing. The need to address emergency preparedness during the license renewal environmental review process, thus, quickly becomes apparent. This becomes even clearer when examining nuclear power plant siting regulations: were Entergy applying for a license to build a new nuclear power plant where Indian Point is now located, it is unlikely they would be allowed to do so, based on its proximity to such a highly populated
55 For example, a 2006 study by the National Academy of Sciences on security risks posed by the storage of spent
fuel at nuclear plant sites, confirmed that attacks by civilian aircrafts remain a plausible threat. Nat‟l Acad. of Sciences., Safety and Security of Commercial Spent Nuclear Fuel Storage: Public Report (2006) (hereinafter “2006 NAS Study”). The study found that attacks on spent fuel pools are attractive targets since they are less protected structurally than reactor cores and typically contain much greater inventories of medium and long-lived radionuclides than reactor cores. Id.
56 See 2006 NAS Study at 49, 57. 57 See generally Gordon R. Thompson, “Risk Related Impacts from Continued Operation of the Indian Point
Nuclear Power Plants” (Institute for Resource and Security Studies) (November 28, 2007) (hereinafter “Thompson Report”). Riverkeeper provides this report in further support of the comments made herein, for your consideration in the instant rulemaking proceeding, as Exhibit F.
58 See generally Riverkeeper EP Comments. 59 See Revised GEIS at 1-11.
SLIDE 14 14
area.60 The regulations for reactors built after 1997 require that every site must have an exclusion area and a low population zone.61 These regulations define low population zone as “the area immediately surrounding the exclusion area which contains residents, the total number and density of which are such that there is a reasonable probability that appropriate protective measures could be taken on their behalf in the event of a serious accident.”62 The regulations do not specify a permissible population density or total population within this zone because the situation may vary from case to case.63 The regulations go on to say whether a specific number
- f people can, for example, be evacuated from a specific area, or instructed to take shelter, on a
timely basis will depend on many factors such as location, number and size of highways, scope and extent of advance planning, and actual distribution of residents within the area.64 As far as Indian Point is concerned, there is no low population zone, therefore if Entergy were applying to build a new nuclear power plant as opposed to a relicensing it would likely not be permitted. Therefore, if held to the same standard as a new nuclear power plant, an evaluation of emergency preparedness would likely preclude license approval. It defies logic to then exclude consideration of this issue in a license renewal review, given significant changes to the baseline environment upon which initial evaluations were made. The NRC cannot continue to hide behind a set of deficient regulations. The NRC should, thus, include emergency preparedness as a site-specific Category 2 issue for review, and require an assessment of all relevant concerns, including population changes, transportation/traffic issues, varying radiological consequences, etc.
- VI. INADEQUATE ASSESSMENT OF THE ENVIRONMENTAL CONSEQUENCES
OF SEVERE ACCIDENTS Inadequate Consideration of Spent Fuel Pool Accidents The Revised GEIS recognizes that severe accident analyses in the 1996 GEIS “were limited to consideration of reactor accidents caused by internal events.”65 Proclaiming an understanding that accident risk has naturally evolved since issuance of the 1996 GEIS, the Revised GEIS identifies new sources of postulated severe accidents, including an explicit recognition of spent fuel pool accidents.66 However, while this recognition is commendable, the Revised GEIS goes on to draw erroneous conclusions about the potential consequences of spent fuel pool accidents. After weighing new information said to decrease estimated environmental impact against new information (including spent fuel pool accidents) said to increase estimated impacts, the Revised GEIS concludes “that the reduction in environmental impacts from the use of new information outweighs any increases
60 See 10 C.F.R. Pts. 100.3, 100.10(b), 100.11, & 100.21(h). 61 10 C.F.R. § 100.21(h). 62 10 C.F.R. § 50.2. 63 Id. 64 Id. 65 Revised GEIS at 4-153. 66 See id. at 4-153 to 4-154; Revised GEIS Appendices at E-32 (“The 1996 GEIS did not include an explicit
assessment of the environmental impacts of accidents at the spent fuel pools (SFPs) located at each reactor site.”).
SLIDE 15 15
resulting from new considerations. As a result, the findings in the 1996 GEIS remain valid.”67 In particular regard to spent fuel pool accidents, the Revised GEIS concludes that “the environmental impacts from accidents at spent fuel pools . . . can be comparable to those from reactor accidents at full power . . . Subsequent analyses performed, and mitigative measures employed since 2001 have further lowered the risk of this class of accidents.”68 Accordingly, the NRC continues to exclude spent fuel pool accidents from site-specific analysis, including Severe Accident Mitigation Alternatives (SAMAs) related to spent fuel pool accidents.69 The NRC‟s revised assessment here continues to ignore relevant information about the risk of spent fuel pool accidents, which undermines the NRC‟s continued conclusion that the impact of releases to the environment from severe accidents will always be “small.”70 While initially, it was assumed that stored spent fuel generally did not pose significant risks, with the introduction of high-density, closed-form storage racks into spent fuel pools beginning in the 1970s, this understanding is no longer valid.71 The closed-form configuration of the high density racks can create a major problem if water is lost from a spent fuel pool, including disastrous pool fires.72 Studies conducted after the issuance of the 1996 License Renewal GEIS contradict previous studies that had asserted that complete drainage of spent fuel pools was the most severe case and that aged fuel would not burn.73 These later studies establish that if the water level in a fuel storage pool dropped to the point where the tops of the fuel assemblies are uncovered, the fuel would burn regardless of its age, and resulting fires can be catastrophic.74 Furthermore, the Revised GEIS acknowledges that mitigative measures have been taken to reduce the risk of spent fuel pool fires. However, the existence of such measures at particular nuclear power plant sites completely contradicts the NRC‟s end conclusion that spent fuel pool accidents do not warrant site-specific consideration.75 Accordingly, the NRC conclusion that that all consequences from severe accidents, including those involving spent fuel pools, are “small for all plants,” is without proper foundation. The
67 Revised GEIS at 4-154. 68 Id. at 4-156. 69 See id. at 4-154 (“[T]he impacts from reactor accidents at full power (including internal and external events)
should continue to be considered in assessing Sever Accident Mitigation Alternatives (SAMAs). The impacts of all
- ther new information do not contribute sufficiently to the environmental impacts to warrant their inclusion in the
SAMA analysis, since the likelihood of finding cost-effective plant improvements is small.”) (emphasis added).
70 See Revised GEIS Appendices at B-33. 71 See Thompson Report at 18-27. 72 Id. 73 See Waste Confidence Rule, 55 Fed. Reg. 38,474, 38,481 (Sept. 18, 1990). 74 NUREG-1738, Final Technical Study of Spent Fuel Pool Accident Risk at Decommissioning Nuclear Power
Plants (January 2001); 2006 NAS Study at 53-54. The Revised GEIS improperly attempts to underplay the findings
- f NUREG-1738 at various turns. See, e.g., Revised GEIS Appendices at E-34 (“the impact analysis contained in
NUREG-1738 is considered conservative”); id. at E-35 (“low ruthenium source term is . . . viewed as the more accurate representation. Therefore, the risk and environmental impact from fires in SFPs as analyzed in NUREG- 1738 are expected to be comparable to or lower than those from reactor accidents and are bounded by the 1996 GEIS.”); id at E-36 (“Based on the more rigorous accident progression analyses, the recent mitigation enhancements, and NRC site evaluations of every SFP in the United States, the risk of an SFP zirconium fire initiation is expected to be less than reported in NUREG-1738”).
75 See generally Riverkeeper‟s IP DSEIS Comments at 26-33.
SLIDE 16
16
impacts of severe accidents from spent fuel pool accidents should be addressed in a site-specific manner, with the appropriate potential range of impact being SMALL to LARGE. In any event, it is crucial that NRC require consideration of spent fuel pool accidents in licensee and NRC Staff SAMA analyses. Failure to do so will lead to highly inaccurate results.76 For example, in the Indian Point relicensing proceeding, in the first step of the SAMA analysis (establishing the baseline of severe accidents) neither Entergy nor the NRC Staff considered the contribution to severe accident costs by fire in either of the spent fuel pools at IP2 or IP3.77 No SAMAs that would avoid or mitigate such costs were identified.78 However, if the costs of pool fires were considered, the value of SAMAs would be significant. Even using unrealistically low probability estimates in NUREG-1353, Regulatory Analysis for the Resolution of Generic Issue 82, Beyond Design Basis Accidents in Spent Fuel Pools (1982), the offsite cost risk of a pool fire is substantially higher than the offsite cost risk of an Early High release from a core-damage accident.79 The present value of cost risk for a conventional pool accident at Indian Point (i.e., an accident not caused by intentional attack), using the unrealistically low probability assumptions in NUREG-1353, is $27.7 million, a significant sum.80 If more realistic assumptions about the likelihood of a pool fire were used, the cost would be considerably higher.81 Moreover, the present value of cost risks (“PVCR”) for a spent fuel pool fire would increase substantially (i.e., from $27.7 million to $38.7 million) if the discount rate were changed from 7% to 3%, a more appropriate rate for an analysis of the benefits of measures to prevent or mitigate radiological accidents that Entergy used to test the sensitivity of its SAMA analysis.82 If the discount rate were dropped to zero, a rate that is justified in light of the catastrophic nature of the consequences involved, the PVCR for a spent fuel pool fire would be even higher -- $51.5 million.83 Given the potential costs involved, it is essential that such risks are assessed in licensee SAMA analyses. Continued Failure to Specifically Address the Risk of Intentional Acts of Sabotage The Revised GEIS maintains that “the risk of a successful terrorist attack (i.e., one that results in a zirconium fire) is very low.”84 Notably, the NRC continues to rely upon Sandia National Lab studies that are classified as “sensitive security related” and, thus, not available to the public, to support its conclusion that environmental consequence of a terrorist attack would be adequately mitigated.85 Accordingly, NRC folds this issue into its generic determination that the impact of severe accidents is “small,” and would continue to not require any site specific analysis, including SAMAs related to terrorist attacks.
76 See generally Thompson Report. 77 See Indian Point Draft Supplemental EIS § 5.2; Entergy‟s Environmental Report at § 4.21. 78 Indian Point Draft Supplemental EIS § 5.2 79 Thompson Report at 28 80 Id. at 49 and Table 7-7. 81 Id. at 51. 82 Id. at 51-52. 83 Id. at 52. 84 Revised GEIS Appendices at E-35. 85 See id. at E-36.
SLIDE 17
17
However, ample evidence undermines the NRC‟s conclusions here. Firstly, the Revised GEIS downplays the potential risk of terrorist attack on nuclear power plants. Numerous reports indicate that nuclear power plants remain likely targets of terrorist attacks. The 9/11 Commission Report revealed that the mastermind of the 9/11 attacks had originally planned to hijack additional aircrafts to crash into targets, including nuclear power plants, but wrongly believed the plants were heavily defended.86 This report indicates that the terrorists were considering attacking a specific nuclear facility in New York which one of the pilots had seen during a familiarization flight near New York.87 This was likely Indian Point, especially given the fact that almost 20 million people live within 50 miles of the facility.88 In the years since the 9/11 attacks, the federal government, including the NRC, has repeatedly recognized that there is a credible threat of intentional attacks on nuclear power plants.89 Notably, existing nuclear power plants in the United States were built between the 1950s and the 1980s and were not intended to be able to withstand the impact of aircraft crashes or explosive forces, thus, making success of a potential terrorist attack a credible possibility.90 Furthermore, as discussed above, the Revised GEIS continues to underplay the severity of consequences of spent fuel pool fires that could result from an intentional attack. For example, at Indian Point, the impacts of terrorist attack would be far ranging. Such impacts are explained in a report prepared on behalf of Riverkeeper in connection with Riverkeeper‟s Petition for Hearing in the Indian Point relicensing proceeding by Edwin Lyman, entitled, Chernobyl on the Hudson? The Health & Economic Impacts of a Terrorist Attack at the Indian Point Nuclear Power Plant. This report is attached hereto in support of the comments made herein, for your consideration in the instant rulemaking proceeding, as Exhibit G. Once again, the existence of mitigation measures which have been implemented to reduce the risk of intentional attack only highlight the fact that a comprehensive site-specific assessment as part of the NEPA process has never been performed, and is greatly needed here.91 The inadequate assessment of intentional attack on nuclear power plants, thus, further erodes the
86 Nat‟l Comm‟n on Terrorist Attacks Upon the U.S., The 9/11 Commission Report (2004), at 154 (“9/11
Commission Report”).
87 9/11 Commission Report at 245. 88 See, e.g., Witt Report at 4, 81-82. 89 See, e.g.,; Wide-Ranging New Terror Alerts, CBS News.com (May 26, 2002), available at,
http://cbsnews.com/stories/2002/05/24/attack/main510054.shtml (discussing heightened alert of the U.S.‟s nuclear power plants as a result of information gained by the intelligence community); FBI Warns of Nuke Plant Danger, CBS News.com (May 1, 2003), available at, http://www.cbsnews.com/stories/2003/09/04/attack/main571556.shtml (discussing FBI warning to nuclear plant operators to remain vigilant about suspicious activity that could signal a potential terrorist attack); General Accounting Office, Nuclear Regulatory Commission: Oversight of Security at Commercial Nuclear Power Plants Needs to be Strengthened, GAO-03-752 (2003) (noting that U.S. nuclear power plants are possible terrorist target, and criticizing the NRC‟s oversight of plant security); FBI’s 4th Warning, CBS News.com (July 2, 2004) (discussing FBI warning of recent intelligence showing Al-Qaeda interest in attacking nuclear plants).
90 In re All Nuclear Power Reactor Licensees, DD-02-04 (Nov. 1, 2002), available at http://www.nrc.gov/reading-
rm/doc-collections/petitions-2-206/directors-decision/2002/ml022890031.pdf; NRC: Nuclear Power Plants Not Protected Against Air Crashes, Associated Press (Mar. 28, 2002).
91 See generally Riverkeeper‟s IP DSEIS Comments at 26-33.
SLIDE 18 18
NRC‟s basis for concluding that the consequences from severe accidents are categorically “small for all plants.” Additionally, it is crucial that NRC require consideration of intentional attack in licensee and NRC Staff SAMA analyses. Failure to do so will once again lead to highly inaccurate results.92 For example, in the Indian Point relicensing proceeding, in the first step the SAMA analysis (i.e., establishing the baseline of severe accidents), Entergy and the NRC Staff did not consider the contribution to severe accident costs made by such intentional attacks at Indian Point.93 The present value of cost risks for an attack at an Indian Point reactor and its pool exceeds half a billion dollars, which would warrant significant expenditures on SAMAs.94 The present value of cost risks for an attack on a reactor alone are also significant -- $62 million to $73 million.95 However, relevant SAMAs with a value of this magnitude were not considered. It is, thus, clear that the failure to consider the risk of intentional attack renders the required SAMA analysis highly inaccurate.
- VII. INADEQUATE ASSESSMENT OF NUCLEAR WASTE STORAGE IMPACTS
Low-Level Waste Storage and Disposal The Revised GEIS recognizes that the Barnwell disposal facility in South Carolina has stopped accepting waste from States that are not part of the Atlantic compact as of July 2008.96 The Revised GEIS further acknowledges the difficulty this poses to the 36 States who now have limited options for disposal of low-level waste. And yet, the NRC proposes to once again generically dispose of this as Category 1 issue. However, in light of the closure of the aforementioned disposal facility, it should be incumbent on licensees to perform a site-specific assessment of the environmental impacts of the accumulating volumes of low-level waste, which may now have to remain onsite on a long-term basis. Accordingly this should be re-categorized as a Category 2 issue. Onsite Storage of Spent Nuclear Fuel The Revised GEIS continues to hide behind the generic determination of no significant environmental impact in 10 C.F.R. § 51.23(b), stemming from the NRC‟s Waste Confidence Decision, to avoid requiring site-specific review of onsite nuclear waste storage impacts.97 This is highly problematic for numerous reasons. To begin with, a pending proposal, which the Revised GEIS acknowledges, to update the NRC‟s Waste Confidence Decision, if finalized, would extend the finding of no significant impact an additional 30 years.98 A concomitant proposed rule change, would omit any reference to how
92 See generally Thompson Report. 93 Indian Point Draft Supplemental EIS § 5.2; Entergy‟s Environmental Report at § 4.21. 94 See Thompson Report at 45-46, Table 7-7, Section 9. 95 Id. at 49. 96 Revised GEIS at 4-165. 97 See id. at 1-9 to 1-10, 4-165 to 4-168. 98 Waste Confidence Decision Update, 73 Fed. Reg 59,551, 59551, 59563-59569 (Oct. 9, 2008) (“WCD Update”).
SLIDE 19 19
long spent fuel can safely be stored in “temporary” on- or off-site facilities, and simply state that such waste can be so temporarily stored without significant impact “until a disposal facility can reasonably be expected to be available.”99 Given the status of the Yucca Mountain proposal and lack of a clear long-term disposal solution, it is reasonably foreseeable that spent nuclear fuel and high level waste will have to remain onsite indefinitely. If the proposed rule changes are implemented, the NRC‟s generic finding of no significant impact would essentially be extended to some indefinable point in the future. Foregoing any analysis of impacts of decades and decades of spent nuclear waste storage because of the NRC‟s “waste confidence” is, thus, improper. The NRC‟s reasonable assurance of safe interim storage, first instituted over a quarter of a century ago and never supported by an environmental assessment or environmental impact statement under NEPA,100 simply does not hold up given current knowledge and circumstances. Most blatantly, the NRC‟s generic assurance of benign spent fuel pool storage is completely undermined by the evidence of leaks at reactors across the United States.101 For example, at Indian Point, the Unit 1 pool began leaking as early as the 1990s, and the leaks from Unit 2 were discovered in 2005.102 With spent fuel pool degradation already at nuclear plants, it is patently absurd to rely on the generic no impact finding to project the long-term integrity of the pools for decades into the future. Given this circumstance, a generic finding about the impacts of pool storage is simply not appropriate, and a site-specific review should be performed at the license renewal juncture. The NRC‟s Waste Confidence Decision also fosters unbridled assurance in the safety of dry cask storage, yet this is also questionable. It is far from clear what environmental impacts will result if dry casks remain loaded with spent fuel beyond their design life.103 In light of the fact that these casks will remain on the banks of the Hudson River indefinitely into the future, the NRC Staff must perform a site specific assessment of impacts of such long-term storage. The NRC‟s generic finding of no significant impact also flies in the face of new information about the risks of accidents at on-site nuclear waste storage facilities. Numerous reports and studies show that fuel storage pools are potentially susceptible to fire and radiological release from natural phenomena.104 As discussed above, the environmental impacts of a fire in a spent
99 Proposed Rule on the Consideration of Environmental Impacts of Temporary Storage of Spent Fuel After
Cessation of Reactor Operation, 73 Fed. Reg. 59,547, 59551 (Oct. 9, 2008).
100 Final Waste Confidence Decision, 49 Fed. Reg. 34658 (“[T]he Commission finds that NEPA does not require an
EIS to support the [temporary storage] finding”); see also 40 C.F.R. § 1508.9 (explaining that environmental assessments under NEPA should provide sufficient evidence and analysis for determining whether to prepare an EIS
101 See Liquid Radioactive Release Lessons Learned Task Force Final Report, U.S. Nuclear Regulatory
Commission, at 5-6 (September 1, 2006) (hereinafter “Radioactive Release Task Force Report”).
102 See Entergy‟s Environmental Report, at 5-4; Groundwater Investigation Executive Summary (Indian Point
Energy Center, Buchanan, N.Y., Jan. 2008), available at http://jic.semo.state.ny.us/Resources/ExecutiveSummary%20GW%20final.pdf; see also Riverkeeper‟s Exhibit A.
103 See Riverkeeper‟s Scoping Comments at 9-10. 104 See, e.g., NUREG-1738, Final Technical Study of 1 Spent Fuel Pool Accident Risk and Decommissioning
Nuclear Power Plants (NRC: January 2001); National Academy of Sciences Committee on the Safety and Security
- f Commercial Spent Nuclear Fuel Storage, Safety and Security of Commercial Spent Nuclear Fuel Storage (The
National Academies Press: 2006); Gordon Thompson, Risks and Risk-Reducing Options Associated with Pool
SLIDE 20 20
fuel pool may be severe, extending over a geographic area larger than a state‟s legal boundaries and continuing for decades.105 Despite such ominous potential consequences, the Revised GEIS would continue to completely ignore the vulnerability of stored spent fuel to natural phenomenon, such as earthquakes. For example, recent new information from seismologists at Columbia University‟s Lamont-Doherty Earth Observatory, who published a study in August 2008 on earthquakes in the greater New York City Area, indicates that Indian Point sits on a previously unidentified intersection of two active seismic zones. 106 Indeed, several recent earthquakes in New Jersey right near the Ramapo fault, which runs directly underneath Indian Point, starkly demonstrate the active nature of the seismic areas around the facility.107 The Columbia study further found that historic activity of earthquakes of a magnitude more than 5 has been higher in southeastern New York than in many
- ther areas of the central and eastern United States, and that the fault lengths and stresses suggest
magnitude 6 or 7 quakes (which would be 10 and 100 times bigger than magnitude 5, respectively) are “quite possible.108 Yet, due to the categorical exclusion of nuclear waste storage impacts, the Revised GEIS would not require consideration of such information. This is notwithstanding the new issue in the Revised GEIS related to new seismological information,109 which would ostensibly not extend to impacts to nuclear waste in light of NRC‟s reliance on the Waste Confidence Rule. There is no certainty whatsoever that the dry casks or spent fuel pools at plants like Indian Point are designed so as to be able to withstand such natural occurrences in light of the new seismic information. The existence of such new information highlights why a generic determination of environmental safety for long-term on-site storage of spent fuel is totally inappropriate. The NRC Staff also relies upon the NRC‟s generic safety determination to further justify its refusal to consider the risks to spent fuel storage from intentional acts of sabotage.110 However, the likelihood and seriousness of such risks necessitates a thorough review of the impacts of long-term storage of spent fuel at Indian Point. As discussed above, future terrorist attacks at Indian Point remain reasonably foreseeable, and such risks must be fully assessed in the relicensing proceeding. Based on the foregoing, it is clear that the NRC‟s generic determination can not form the basis for continued exclusion of this issue in all future license renewal proceedings. Based on the
Storage of Spent Nuclear Fuel at the Pilgrim and Vermont Yankee Nuclear Power Plants (May 25, 2006); Jan Beyea, Report to the Massachusetts Attorney General on the Potential Consequences of a Spent-fuel Pool Fire at the Pilgrim or Vermont Yankee Nuclear Plant (May 25, 2006).
105 See generally, Thompson Report. 106 See Lynn R. Sykes, John G. Armbruster, Won-Young Kim, & Leonardo Seeber, Observations and Tectonic
Setting of Historic and Instrumentally Located Earthquakes in the Greater New York City-Philadelphia Area, Bulletin of the Seismological Society of America, Vol. 98, No. 4, pp. 1696-1719 (August 2008) (“2008 Columbia Earthquake Study”).
107 See, e.g., Lawrence Ragonese, Morris County Shows Signs of Stress: Four Quakes, The Star-Ledger (Feb. 18,
2009), available at, http://www.nj.com/news/index.ssf/2009/02/morris_county_shows_sign_of_st.html.
108 2008 Columbia Study; see also Robert Roy Britt, Large Earthquakes Could Strike New York City (Aug. 21,
2008), available at http://www.livescience.com/environment/080821-new-york-earthquakes.html.
109 See Revised GEIS at 3-49 to 3-50. 110 See Waste Confidence Decision Update, 73 Fed. Reg. 59,551.
SLIDE 21 21
changed landscape, NRC must make this a Category 2 issue and require site-specific analysis of the impacts of long-term on-site storage. Offsite Radiological Impacts of Spent Nuclear Fuel and High-Level Waste Disposal The Revised GEIS continues to review the offsite radiological impacts from spent nuclear fuel and high level waste disposal in relation to the use of Yucca Mountain as the future long-term geologic repository. This flies in the face of recent indications that Yucca is no longer a viable
- ption. Indeed, there is no dispute that the current Administration has brought the axe down on
the Yucca project. Most recent accounts indicate that the U.S. Department of Energy intends to stop pursuing a license for the Yucca repository by this December.111 Even the NRC Commissioner‟s have acknowledged the current plan to eliminate the Yucca Mountain Project.112 It is, thus, curious, that a document that will serve as a generic environmental impact statement for decades to come would continue to rely upon this eventuality. Indeed, the Revised GEIS explicitly relies upon dose limits from documents filed in connection with the Department of Energy‟s Yucca Application.113 In addition to misguidedly relying upon a pending application, such information was developed specifically in relation to Yucca, and is therefore essentially unusable in light of the aforementioned circumstances. Given the uncertainly of long-term disposal of nuclear waste, and the likelihood of essentially indefinite on-site storage, it makes far more sense to perform a site specific review to discern the
- ffsite impacts of this waste at particular plants. While the NRC will undoubtedly claim that
they are relying in good faith on the Department of Energy‟s pending application which has not been withdrawn yet, the NRC must not “shut . . . [their] ears to the din of current debate” as Commissioner Svinicki has articulated.114
For the foregoing reasons, Riverkeeper respectfully submits that the Revised GEIS for license renewal of nuclear power plants is inadequate and incomplete. The environmental review based
- n the Revised GEIS would fail to provide for a comprehensive review which is necessary to
comply with NEPA.
111 See, e.g., Keith Rogers, Yucca Mountain: Memo casts doubt on license for Yucca repository, LAS VEGAS
REVIEW-JOURNAL (Nov. 10, 2009), http://www.lvrj.com/news/memo-casts-doubt-on-license-for-yucca-repository- 69639342.html (last visited Jan. 12, 2009).
112 See Notation Vote of Commissioner Klein, SECY-09-0090 – Final Update of the Commission‟s Waste
Confidence Decision (September 16, 2009), available at, http://www.nrc.gov/reading-rm/doc- collections/commission/cvr/2009/2009-0090vtr-dek.pdf; Notation Vote of Commissioner Svinicki, SECY-09-0090 – Final Update of the Commission‟s Waste Confidence Decision (September 24, 2009), available at, http://www.nrc.gov/reading-rm/doc-collections/commission/cvr/2009/2009-0090vtr-kls.pdf (“Svinicki Vote on WCD”).
113 See Proposed Rule at 38,127. 114 Svinicki Vote on WCD at 3.
SLIDE 22
22
Thank you for your consideration. Sincerely, s/ s/ _____________________________ _____________________________ Phillip Musegaas, Esq. Deborah Brancato Hudson River Program Director Staff Attorney
SLIDE 23 23
LIST OF EXHIBITS Exhibit A – compiled documentation related to nuclear power plant leaks across the United States. Exhibit B – Riverkeeper, Inc.‟s Request for Hearing and Petition to Intervene in Indian Point License Renewal Proceeding, November 30, 2007 Exhibit C – Riverkeeper Comments on Environmental Scoping for the Indian Point License Renewal Proceeding, Docket Nos. 50-247, 50-286 (Oct. 12, 2007) Exhibit D – Riverkeeper Comments on Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 38, Regarding Indian Point Nuclear Generating Unit
- Nos. 2 and 3, Draft Report for Comment (March 18, 2009)
Exhibit E – Riverkeeper‟s Comments on NRC‟s Proposed Enhancements to Emergency Preparedness Regulations (Oct. 19, 2009) Exhibit F – Gordon R. Thompson, “Risk Related Impacts from Continued Operation of the Indian Point Nuclear Power Plants” (Institute for Resource and Security Studies) (November 28, 2007) Exhibit G – Edwin S. Lyman, Chernobyl on the Hudson? The Health & Economic Impacts of a Terrorist Attack at the Indian Point Nuclear Power Plant (Union of Concerned Scientists, September 2004)