vcfn vcfn a update
play

VCFN / VCFN A Update Transition Plan & CTI Project Chad West, - PowerPoint PPT Presentation

VCFN / VCFN A Update Transition Plan & CTI Project Chad West, Manager of IT Committee of the Whole April 21, 2020 Origin Jan 2019 Business Plan funded Spring 2019 Business Plan delivered Summer 2019 Transition Plan


  1. VCFN / VCFN A Update Transition Plan & CTI Project Chad West, Manager of IT Committee of the Whole April 21, 2020

  2. Origin Jan 2019 – Business Plan funded • Spring 2019 – Business Plan delivered • Summer 2019 – Transition Plan developed • Fall 2019 – Transition Plan introduced to COTW • Winter 2020 – Transition Plan updated • Update provided to COTW 2

  3. VCFN Transition Plan Update Key to long term network viability • Transition negotiations ongoing • Led by CAO • Terms being negotiated by partners • 3

  4. Impact on Broadband Project Adaptable plan in place • Expect plan in place before network • operational 4

  5. CTI Statement of Work Multiple rounds of revisions • Current revision under review by ISED • Agreement in place within weeks • Kings to own assets • Contract VCFNA to operate network • Organizational changes not strictly required • 5

  6. Support Structure Agreements Agreements in place • VCFNA & Nova Scotia Power • VCFNA & Bell • Allows make ready submission • 6

  7. Make Ready Requests submitted • Under review by NS Power & Bell • Process managed by VistaCare • 7

  8. Project Status Engineering work 82% complete • Networking equipment selected • Nearing 20% pre-SOW contribution limit • Need SOW complete before proceeding further • Project financed with short-term debt • CTI portion reimbursed based on progress reports • 8

  9. Last-mile service MOU & fibre lease agreement under review • 3-way agreement – Kings, VCFNA, Cross Country • Must be finalized before network operational • 9

  10. Construction Tender to be released later this week • June – Award Contract • Summer 2020 – Winter 2021 – Construction • Risks • COVID-19 - Supply chain issues • 10

  11. Summary Transition Plan • Needed for VCFNA long-term viability • Not strictly required for CTI project • Simplifies network operation when in place • 11

  12. Develop Nova Scotia Round 2 Funding Application Chad West, Manager of IT Committee of the Whole April 21, 2020

  13. Origin Municipality pre-qualified through RFSQ • Did not submit Round 1 application • 2

  14. Round 2 Connections up to June 2022 • Following areas eligible • No household service meeting CRTC guidelines • Not covered under ISED, CRTC or Round 1 • Applications due May 22nd • 3

  15. Proposal Extend from CTI network • Open-access middle mile network • Build to all remaining areas of the Municipality • Construct in 2021 • 4

  16. 5

  17. Financial Implications Bid requires 10% letter of credit • Project budget depends on awarded funding • Partial awards are possible • Municipal contribution up to $2,200,000 • Required in 2021/22 and 2022/23 • 6

  18. Alternatives Do not bid • Build up to $1,000,000 last-mile fibre • 7

  19. Implementation May 22 – Application due • Summer – Awards announced • + 60 days – Contract negotiation • Work would start Q1 fiscal 2021/22 • 8

  20. Recommendation That Committee of the Whole recommend Municipal Council direct the CAO to submit a response to DNS-1920-0002 (Develop Nova Scotia - Internet for Nova Scotia Initiative). 9

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend