v
FINAL DESIGN PRESENTATION SCHOOL BOARD INFORMATION ITEM
ABINGDON ELEMENTARY SCHOOL
ADDITION + RENOVATION
FEBRUARY 18, 2016
v ABINGDON ELEMENTARY SCHOOL ADDITION + RENOVATION Agenda 01 - - PowerPoint PPT Presentation
FEBRUARY 18, 2016 FINAL DESIGN PRESENTATION SCHOOL BOARD INFORMATION ITEM v ABINGDON ELEMENTARY SCHOOL ADDITION + RENOVATION Agenda 01 Project Introduction 02 Educational Enhancements 03 Transportation Study 04 Final Design 2 PROJECT
ADDITION + RENOVATION
FEBRUARY 18, 2016
01 Project Introduction 02 Educational Enhancements 03 Transportation Study 04 Final Design
2
PROJECT INTRODUCTION
3
PROJECT MILESTONES:
4 OVERALL PROJECT SCHEDULE
589 – current capacity (building only) 729 – projected capacity 140 additional seats
5
ABINGDON ELEMENTARY SCHOOL: PROJECT SCOPE OVERVIEW
6
ABINGDON BLPC & PFRC MEETINGS
BLPC: 15 MEETINGS
PFRC: 8 MEETINGS
Hord Coplan Macht’s Baltimore Location 7
EDUCATIONAL ENHANCEMENTS
Goal 1: Challenge and Engage All Students
stimulate students and enhance engagement
alternative learning environments for instruction.
distributed within the building will allow for breakaway instruction enhancing focused instruction to small groups of students.
8
8
APS STRATEGIC GOALS THROUGH CAPACITY PROJECTS: EDUCATIONAL ENHANCEMENTS
Goal 4: Provide Optimal Learning Environments
instruction nooks to take advantage of all potential learning spaces
through active dashboards and visible construction / systems
and flexible furniture
fluctuating enrollment
Goal 5: Meet the Needs of the Whole Child
physical activities
9
APS STRATEGIC GOALS THROUGH CAPACITY PROJECTS: EDUCATIONAL ENHANCEMENTS
10
Howard Gardner’s Multiple Intelligences Project GIFT
All-inclusive – Grade Level Classrooms Abingdon Wheel Courses:
OPTIMAL LEARNING ENVIRONMENTS …. WHAT?
11
OPTIMAL LEARNING ENVIRONMENTS …. HOW?
Hord Coplan Macht’s Baltimore Location 12
TRANSPORTATION STUDY
Raised crosswalk with curb extensions
Raised crosswalk with curb extensions
Priority School Access Improvement (Community Amenity Fund)
Hord Coplan Macht’s Baltimore Location 15
FINAL DESIGN
SITE PLAN
16
FLOOR PLAN
17 FINAL DESIGN Main Level & Second Level Lower Level Third Level
EXTERIOR PERSPECTIVE
18 FINAL DESIGN ENTRANCE + GYMNASIUM
EXTERIOR PERSPECTIVE
19 FINAL DESIGN CAFETERIA + CLASSROOM ADDITION
INTERIOR FINSHES
20 FINAL DESIGN
It is of the utmost importance that we recognize and nurture all of the varied human intelligences, and all of the combinations of intelligences. ~ Howard Gardner
GRAPHIC PANELS
21 FINAL DESIGN
Graphic panels are preliminary and additional refinements are anticipated during further coordination with APS staff.
INTERIOR PERSPECTIVES
22 FINAL DESIGN
MAIN ENTRY ADDITION GYMNASIUM ADDITION LIBRARY RENOVATION
INTERIOR PERSPECTIVES
23 FINAL DESIGN
CAFETERIA RENOVATION STAIR CLASSROOM CORRIDOR
24 FINAL DESIGN
FINAL DESIGN – FUNDING AVAILABLE
2014 Bond (Per FY2015-2024 CIP) $28,750,000 Maintenance LTP & MC/MM Funding:
$750,000
$800,000
$402,000
$103,000
$70,000
$115,365
$200,000
$51,000 Subtotal LTP & MC/MM $2,491,365 Capital Reserve** $400,000 County/School Board Joint Fund***
$600,000
$600,000 Subtotal Joint Fund $1,200,000
Grand Total Funding Available $32,841,365
Total APS Funding $32,241,365 Total County Funding $600,000 Notes: * Not included at the Schematic Design phase. ** Not included at the Schematic Design phase. APS Staff coverage for 33 months (July 2015 through March 2018). *** Pending final negotiation with County
25 FINAL DESIGN
FINAL DESIGN – COST ESTIMATE
Construction Costs* $24,390,000 Construction Contingency $1,950,000 Soft Costs $6,101,365 APS Staff Costs $400,000
Estimated Total Project Cost $32,841,365
Total Funding Available $32,841,365 Over (Under) Funding Available $0
Note: * Based on two independent professional cost estimates; one from the A/E firm and one from the Construction Management firm.
26