UTILITY STANDARDS - INTERCONNECTION PROCESSES - TIMELINES FOR SOLAR PROJECTS Bob Sisco 740-506-0906 bsisco@ohiopowersolutions.com UTILITY STANDARDS Bob Sisco 740-506-0906 bsisco@ohiopowersolutions.com UTILITY STANDARDS u UL 1741 u


slide-1
SLIDE 1

UTILITY STANDARDS - INTERCONNECTION PROCESSES

  • TIMELINES FOR SOLAR

PROJECTS

Bob Sisco – 740-506-0906 bsisco@ohiopowersolutions.com

slide-2
SLIDE 2

UTILITY STANDARDS

Bob Sisco – 740-506-0906 bsisco@ohiopowersolutions.com

slide-3
SLIDE 3

UTILITY STANDARDS

uUL 1741 uSystem Sizing uAC Disconnect Location uNet-Metering

Bob Sisco – 740-506-0906 bsisco@ohiopowersolutions.com

slide-4
SLIDE 4

INTERCONNECTION PROCESSES

uInterconnection Application uNet-Metering Application uInspection - AHJ uAgreements uMeter Swap

Bob Sisco – 740-506-0906 bsisco@ohiopowersolutions.com

slide-5
SLIDE 5

TIMELINES FOR SOLAR PROJECTS

u Interconnection Docs (4-6 Weeks) u Permitting Approval (2-3 Weeks) u Procurement (2-3 Days) u Installation (3-5 Days) u Final Inspection (1 Day) u Interconnection Agreements/Meter Swap (1-2 Weeks) u System Commissioned

Bob Sisco – 740-506-0906 bsisco@ohiopowersolutions.com