use of rational and modified rational method in texas
play

UseofRationalandModified RationalMethodinTexas - PowerPoint PPT Presentation

UseofRationalandModified RationalMethodinTexas T.G.Cleveland,TexasTechUniversity X.Fang,AuburnUniversity W.H.Asquith,USGeologicalSurvey


  1. Use
of
Rational
and
Modified
 Rational
Method
in
Texas
 T.G.
Cleveland,
Texas
Tech
University
 X.
Fang,
Auburn
University
 W.
H.
Asquith,
US
Geological
Survey
 D.
B.
Thompson,
R.O.
Anderson,
Inc.
 Project
0‐6070.

May
28,
2009


  2. Outline
 • Introduction
 • Definitions
 • What
We
Have
Done/What
We
Have
Learned
 – Activities/Evidence
 • Summary
 • Where
We
are
Headed


  3. Introduction
 • Rational
Equation
 
 

 
 
Qp
=
C
i
A
 
 
Q p 
=
peak
discharge
(L^3/T)
 
 
C
=
runoff
coefficient

 
 
i
=
rainfall
intensity
(L/T)
 
 
A
=
contributing
area
(L^2)


  4. Introduction
 • Rational
(and
Modified
Rational)
method
 abridged
sequence.
 – (A)
Choose
a
risk
level.
 – (B)
Determine
a
characteristic
time
for
drainage
 area.
(need
to
specify
area
and
time)
 – (C)
Rainfall
intensity
(Needs
(A)
and
(B)
a‐priori)
 – (D)
Choose
a
runoff
generation
coefficient
 – (E)
Compute
Qp
(or
a
hydrograph
if
using
modified
 rational
method
–
peak
value
is
Qp)


  5. Introduction
 • Rational
Method

 http://onlinemanuals.txdot.gov/txdotmanuals/hyd/the_rational_method.htm
 – Determine
drainage
area.
 – Determine
time
of
concentration.
 – Verify
appropriate
with
stated
assumptions.
 – Determine
e,b
and
d
values
for
desired
design
 frequency.
 – Compute
rainfall
intensity.
 – Select
runoff
coefficients.
 – Calculate
estimated
peak
discharge. 


  6. Introduction
 • Modified
Rational
 Method
 – Similar
approach
but
 generates
a
triangular
or
 trapezoidal
hydrograph
 depending
on
rainfall
 duration
as
related
to
the
 watershed
characteristic
 time
(Tc).
 – Largest
possible
peak
 discharge
is
same
as
 rational
method
if:
 • Td
>=
Tc


  7. Introduction
 • Modified
Rational
 Method
 – Similar
approach
but
 generates
a
triangular
or
 trapezoidal
hydrograph
 depending
on
rainfall
 duration
as
related
to
the
 watershed
characteristic
 time
(Tc).
 – Largest
possible
peak
 discharge
is
same
as
 rational
method
if:
 • Td
>=
Tc


  8. Introduction
 • Assumptions
(current)
 – The
rate
of
runoff
resulting
from
any
constant
 rainfall
intensity
is
maximum
when
the
duration
of
 rainfall
equals
the
time
of
concentration.
 • This
assumption
is
a
statement
of
mass
conservation
in
 a
system
where
loss
rates
after
some
time
become
 constant.

It
[the
assumption]
is
probably
valid
for
most
 hydrologic
scales
with
the
qualification
that
requisite
 inputs
may
not
ever
occur
in
nature,
and
constant
loss
 rates
may
never
be
realized.


  9. Introduction
 • Assumptions
(current)
 – The
frequency
of
peak
discharge
is
the
same
as
 the
frequency
of
the
rainfall
intensity
for
the
given
 time
of
concentration.
 • Known
non‐linearity
in
hydrologic
systems
such
that
 response
does
not
scale
at
the
same
rate
as
input.




  10. Introduction
 • Assumptions
(current)
 – The
rainfall
intensity
is
uniformly
distributed
over
 the
entire
drainage
area.

 • In
reality,
rainfall
intensity
varies
spatially
and
 temporally
during
a
storm.

 • For
small
areas,
the
assumption
of
uniform
distribution
 is
reasonable.

 • For
larger
areas
partial
contribution
may
be
applicable
 –
hard
to
quantify
for
design
use.


  11. Introduction
 • Assumptions
(current)
 – The
fraction
(C)
of
rainfall
that
becomes
runoff
is
 independent
of
rainfall
intensity
or
volume.
 • This
assumption
is
important
to
be
consistent
with
the
 first
assumption.


  12. Definitions
 • Time
Concepts
 – Rainfall
duration
 • How
long
a
constant
rainfall
rate
is
applied
‐‐‐
 numerically
the
same
as
Tc,
conceptually
different.
 T2
 Single
pulse
of
rainfall
over
T2
 5
pulses
of
rainfall,
T1
units
long,
in
a
row.
 T1


  13. Definitions
 • Time
Concepts
 – Watershed
 characteristic
 times
 • Concentration
 • Peak
 • Lag


  14. Definitions
 • Runoff
Coefficients
 ∫ Q ( t ) dt – Volumetric
 C V = ∫ p ( t ) dt C R = Q p – Rational

 i ( t d ) A

  15. Definitions
 • Runoff
Coefficients
 • Coefficients
are
related
to
basin
characteristics.


  16. Definitions
 • Watershed
Characteristics
 – Area
(already
in
rational
equation)
 – Slope
 – Channel
Length
 – Basin
Development
Factor
 – Percent
Impervious
 – Land
Use
(Descriptive)


  17. Definitions
 • Basin
Development
Factor
(BDF)
 – Reflects
improvement
in
drainage
network.
 – Correlates
with
development,
makes
no
 assumptions
about
land
use
surrounding
the
 network
per‐se


  18. Definitions
 • BDF
 – Channel
 modification
 – Channel
lining
 – Storm
drain
 – Curb‐gutter


  19. What
We
Have
Done
 • Table
of
C std 
values
from
an
extensive
 literature
review.
 – These
were
presented
in
TM1
 – They
will
be
repeated
with
further
commentary
in
 TM2
(in
progress,
due
soon)


  20. What
We
Have
Done
 • Table
of
C std 
values
from
an
extensive
 literature
review.
 – These
were
presented
in
TM1
 – They
will
be
repeated
with
further
commentary
in
 TM2
(in
progress,
due
soon)


  21. What
We
Have
Done
 • Determined
(by
literature
review
and
 numerical
experiments)
that
the
modified
 rational
method
is
a
special
case
of
the
unit
 hydrograph
method.
 – A
valuable
consequence
of
this
determination
is
to
 remove
a
conceptual
decoupling
of
the
methods,
 instead
there
is
a
continuum
of
methodology.


 – Care
is
still
required
with
regards
to
the
scale
of
 applicability.


  22. What
We
Have
Done
 • Rational
Method
is
a
 Unit
Hydrograph
 – Watershed
is
 represented
as
a
 linear,
time‐invariant
 system

 – Assumptions
1
and
4
 of
current
method.


  23. What
We
Have
Done
 • Invested
in
clarifying
the
different
concepts
in
 the
rational
method
especially
the
time
and
 the
runoff
coefficients.
 – These
are
to
be
explained
in
detail
in
TM2.


  24. What
We
Have
Done
 • Forward
computation
of
Cv.
 – Application
of
rational
method
as
if
ungaged
 watershed.
 – Assumed
that
rational
method
is
a
unit
hydrograph.
 – Substitute
the
rectangular
kernel
in
the
convolution
 integral.


  25. What
We
Have
Done
 Modified
Rational
Method
 Gamma
UH


  26. What
We
Have
learned
 • Forward
computation
of
Cv.
 – Rational
method
is
a
unit
hydrograph.
 – Size
limitation
is
arbitrary
(from
standpoint
of
linear
 systems
theory).
 – Current
limitation
is
meaningful
for
other
reasons
 (uniform
rainfall,
storage,
etc.)


  27. What
We
Have
Done
 • Backward
computation
of
Cv
for
Texas
 watersheds.
 – Compute
best
Cv
to
explain
observations.
 – Same
kind
of
simulations
as
just
presented.
 – Again
assume
rational
method
is
a
unit
 hydrograph.


  28. What
We
Have
Done
 10000
 Modeled
Q p 
(cfs)
 1000
 100
 1:1
line
 C
from
the
ratio
of
runoff
and
 rainfall
 10
 10
 100
 1000
 10000
 Observed
Q p 
(cfs)


  29. What
We
Have
Learned
 • Backward
computation
of
Cv
for
Texas
 watersheds.
 Using
Cv
–
backcomputed
 Using
Cstd


  30. What
We
Have
Learned
 • Backward
computation
of
Cv
for
Texas
 watersheds.
 – Evidence
over‐prediction
potential
of
peak
 discharge.
 – Evidence
suggests
bias
towards
smaller
areas
‐‐‐
 exactly
where
the
method
is
intended
to
be
 applied.
 – Median
C
value
from
literature
based
approach
is
 nearly
two
times
larger
than
for
back
computed.


  31. What
We
Have
Done
 • Back
compute
Cr
values
from
Texas
+
ARS.
 – Used
Tr
as
the
characteristic
time
value,
removes
 ambiguity
for
specification
of
Tc
 T R hrs = A sq . mi . • Not
dimensionally
homogeneous.
 • Consistent
with
a
watershed
integrated
“velocity”
of
1
 mile
per
hour.
(~1.46
ft/sec)


Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend