Use of Numerical Modelling to Mitigate Ground Risk CECA MEETING - - PowerPoint PPT Presentation
Use of Numerical Modelling to Mitigate Ground Risk CECA MEETING - - PowerPoint PPT Presentation
Use of Numerical Modelling to Mitigate Ground Risk CECA MEETING SEPT 2017 Gavin & Doherty Geosolutions Ltd. Overview Todays Presentation. o Introduction to GDG o Finite Element Modelling & Calibration o Case Studies o Flood
Overview
- Introduction to GDG
- Finite Element Modelling & Calibration
- Case Studies
- Flood Defences
- Retaining Walls
- High rise foundations
- Risk Analysis
- Conclusions
Todays Presentation….
GDG Introduction
- Gavin & Doherty Geosolutions (GDG) is a specialist
geotechnical & civil engineering consultancy
- Offices in London, Edinburgh, Dublin, and Belfast,
- GDG was formed in 2011 in a challenging market
- Grown throughout the last five years
- Team of 40 highly talented engineers
- Majority of our staff are PhD qualified
- We provide innovative geotechnical solutions & efficient
civil engineering designs for challenging projects About us ….
Engineering Design Services
Structures Infrastructure Offshore Renewables R&D
Engineering Design Services
- Concept Design
- Site Investigation Scoping
- Site Investigation
Interpretation
- Civil Engineering Design
- Temporary Works Design
- Numerical Modelling (FEA)
- Performance monitoring /
instrumentation analysis
- Expert Witness Services
INFRASTRUCTURE
INFRASTRUCTURE
- Geotechnical Interpretation & Ground
Modelling for Road, Railway and Flood Defence Schemes
- Geological Assessments & Mapping
- Earthworks Design
- Material Suitability
- Hydrogeological review
- Civil Engineering Design
- Numerical Modelling
- Soil-Structure-Water Interaction Analysis
- Back-analysis of failures & Root Cause Analysis
SERVICES & EXPERTISE
URBAN STRUCTURES
URBAN STRUCTURES
SERVICES & EXPERTISE
- Basement & Foundation Engineering
- Soil-Structure Interaction
- Ground Movement Assessments
- Retaining Wall Analysis
- Excavation Support and Propping Design
- Construction Sequencing & Temporary Works
- Pile Design & Piled Raft Analysis
- Tunnel and basement impact assessments
- Ground Improvement Engineering
OFFSHORE & MARINE
OFFSHORE & MARINE
SERVICES & EXPERTISE
- Analysis and Design of Ports & Harbours
- Quay Wall Numerical Modelling
- Offshore Substructure Analysis
- Offshore wind foundation engineering
- Gravity structures, monopiles, jacket piles, etc…
- Pile Installation analysis & Interpretation of
- ffshore driving data
- Site suitability assessments
- Jack-up vessel studies
- Back-analysis of failures & Root Cause Analysis
- NNG Wind Farm
- Rampion Wind Farm
- Zawtika Gas Jacket Pile Analysis
- Hornsea Met Mast
- Firth of Forth Wind Farm Forensics
- Dogger Bank Jackup Analysis
- Shell Conductor Installation Studies North Sea
- Horizont Jacket Pile FEED
RELEVANT PROJECTS RENEWABLES
RENEWABLES
SERVICES & EXPERTISE
- Site suitability and feasibility studies for
- nshore wind and onshore solar farms
- Geotechnical risk studies
- Peat stability assessments
- Earthworks engineering for roads, crane bases,
hardstands, etc.
- Foundation design for gravity and piled bases
- Interaction analysis for soil-structure-turbine
behaviour.
Technical Presentation Sept 2017 www.gdgeo.com
- What is Ground Risk ?
Ground Risk
Technical Presentation Sept 2017 www.gdgeo.com
- Analytical – Traditional Theoretical Hand (spreadsheet)
Calculations
- Empirical – Traditional Approaches based on experience
- f empirical evidence
- Numerical – Finite Element (or Finite Difference)
- Observational Design Approaches
Pick the most appropriate tool for your project (consider the limitations of the tool, the complexity of the project and the accuracy required)
Design Tools Available
Technical Presentation Sept 2017 www.gdgeo.com
- Numerical Modelling Procedure to Determine Soil-
Structure Response
- Modern Software Capable of Considering Complex
Geometries
- The geometry is discretised into a mesh and the stresses
and strains are resolved as loads/actions are applied
- Can accurately determine ground movements and
structural stresses, provided the model is well calibrated
- Calibration requires (a) DATA and (b) EXPERTISE
Finite Element Method
Technical Presentation Sept 2017 www.gdgeo.com
- Soil is highly non-linear
– Pick an appropriate constitutive model
Basics of Geotechnics
Stress Strain Real Soil Elastic-Plastic
Technical Presentation Sept 2017 www.gdgeo.com
- FEM CALIBRATION
– Simulation of Lab Testing – Look for repeatability – Use range of test types
Finite Element Method
Technical Presentation Sept 2017 www.gdgeo.com
- FEM CALIBRATION
– Simulation of Field Testing
Finite Element Method
Technical Presentation Sept 2017 www.gdgeo.com
- TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
- Access Shaft for TBM
- Complex Ground Conditions
- Underlying Aquifer
- Base Heave a Serious Concern !
- Design Solution Needed
CASE STUDY 1
Technical Presentation Sept 2017 www.gdgeo.com
- Model Calibration
CASE STUDY 1
Non-Plastic Till Fine Sand to Silt Plastic Till Sand to Sand and Gravel 𝑬𝒔𝒃𝒋𝒐𝒃𝒉𝒇 𝑼𝒛𝒒𝒇
- Drained
Drained Undrained Drained 𝑸𝒇𝒔𝒏𝒇𝒃𝒄𝒋𝒎𝒋𝒖𝒛 𝑛 𝑡 1 × 10−6 4 × 10−5 8 × 10−8 3 × 10−4 𝜹𝒗𝒐𝒕𝒃𝒖 𝑙𝑂 𝑛3 18 18 24 18 𝜹𝒕𝒃𝒖 𝑙𝑂 𝑛3 20 20 24.3 20 𝒇𝟏
- 0.5
0.5 0.301 0.5 𝑭𝟔𝟏
𝒔𝒇𝒈
𝑁𝑄𝑏 30 30 20 30 𝑭𝒑𝒇𝒆
𝒔𝒇𝒈
𝑁𝑄𝑏 30 30 20 30 𝑭𝒗𝒔
𝒔𝒇𝒈
𝑁𝑄𝑏 90 90 80 90 𝑸𝒑𝒙𝒇𝒔 (𝒏)
- 0.5
0.5 0.5 0.5 𝒅𝒔𝒇𝒈 𝑙𝑄𝑏 𝝌 ° 35 35 35.9 35 𝝎 ° 5 5 9 5 𝒒𝒔𝒇𝒈 𝑙𝑄𝑏 100 100 100 100 𝑺𝒈
- 0.9
0.9 0.9 0.9 𝒍𝟏,𝒚
- 1
0.8 1.2 0.8
Technical Presentation Sept 2017 www.gdgeo.com
- TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
- Undrained versus Drained
CASE STUDY 1
Technical Presentation Sept 2017 www.gdgeo.com
- TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
CASE STUDY 1
Technical Presentation Sept 2017 www.gdgeo.com
- TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
CASE STUDY 1
Technical Presentation Sept 2017 www.gdgeo.com
- TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
CASE STUDY 1
Technical Presentation Sept 2017 www.gdgeo.com
- TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
- Pore Pressures
(a) End of Excavation (b) 10 weeks (c) 20 weeks (d) 50 weeks
CASE STUDY 1
(a) (b) (c) (d)
Technical Presentation Sept 2017 www.gdgeo.com
- TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
- Failure Avoided
- Facilitated Economic Construction Sequence
- Observational Method Used to Minimise Risk
CASE STUDY 1
Technical Presentation Sept 2017 www.gdgeo.com
- NATIONAL GALLERY UNDERPINNING ANALYSIS
CASE STUDY 2
Facilitate basement extension
- Geotechnical interpretation
- Geophysical profiling
- 3D Settlement Analysis of
Construction Stages
- Recommendation about
underpinning construction
- Final settlement design for
temporary and permanent works.
Technical Presentation Sept 2017 www.gdgeo.com
- NATIONAL GALLERY UNDERPINNING ANALYSIS
CASE STUDY 2
Technical Presentation Sept 2017 www.gdgeo.com
- NATIONAL GALLERY UNDERPINNING ANALYSIS
CASE STUDY 2
Technical Presentation Sept 2017 www.gdgeo.com
- NATIONAL GALLERY UNDERPINNING ANALYSIS
CASE STUDY 2
Technical Presentation Sept 2017 www.gdgeo.com
- NATIONAL GALLERY UNDERPINNING ANALYSIS
CASE STUDY 2
Technical Presentation Sept 2017 www.gdgeo.com
- NATIONAL GALLERY UNDERPINNING
- Settlements predicted to be less than 10mm in worst
case
- Generally less than 5 mm
- Concrete underpinning shown to be appropriate,
however construction quality control critical
- Monitoring system tailored to target critical area of the
building and critical point in the construction timeline
- Constant monitoring compared to design predictions
with target levels set to stop construction if required.
CASE STUDY 2
Technical Presentation Sept 2017 www.gdgeo.com
- Flood Defences
CASE STUDY 3
Technical Presentation Sept 2017 www.gdgeo.com
- Flood Wall Analysis
CASE STUDY 3
- Stability Modelling
- Seepage Analysis
Deemed Critical
Technical Presentation Sept 2017 www.gdgeo.com
- Flood Defence Design
CASE STUDY 3
Technical Presentation Sept 2017 www.gdgeo.com
- Flood Risk Analysis
CASE STUDY 3
Technical Presentation Sept 2017 www.gdgeo.com
- Flood Risk Analysis
CASE STUDY 3
0.2 0.4 0.6 0.8 1 1.2 1 . 4 1.6 1.8 2 2.2 2 . 4 2.6
Design Flood Level
Gravel Gravel Silt
Peat
. 6 8 2 2 m ³ / d a y s 2.8537 m³/days 0.12612 m³/days
Distance (m)
5 10 15 20 25 30 35
Elevation (m)
- 13.5
- 12.5
- 11.5
- 10.5
- 9.5
- 8.5
- 7.5
- 6.5
- 5.5
- 4.5
- 3.5
- 2.5
- 1.5
- 0.5
0.5 1.5 2.5 3.5 4.5 5.5
Technical Presentation Sept 2017 www.gdgeo.com
- Flood Risk Analysis
CASE STUDY 3
0.2 0.4 0.6 0.8 1 1.2 1 . 4 1.6 1.8 2 2.2 2 . 4 2.6
Design Flood Level
Gravel Gravel Silt
Peat
. 6 8 2 2 m ³ / d a y s 2.8537 m³/days 0.12612 m³/days
Distance (m)
5 10 15 20 25 30 35
Elevation (m)
- 13.5
- 12.5
- 11.5
- 10.5
- 9.5
- 8.5
- 7.5
- 6.5
- 5.5
- 4.5
- 3.5
- 2.5
- 1.5
- 0.5
0.5 1.5 2.5 3.5 4.5 5.5 . 4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 2.2 2 . 4 2.6 2.8
Gravel Gravel Silt
Peat
Distance (m)
5 10 15 20 25 30 35
Elevation (m)
- 13.5
- 12.5
- 11.5
- 10.5
- 9.5
- 8.5
- 7.5
- 6.5
- 5.5
- 4.5
- 3.5
- 2.5
- 1.5
- 0.5
0.5 1.5 2.5 3.5 4.5 5.5
Technical Presentation Sept 2017 www.gdgeo.com
- Flood Risk Analysis
CASE STUDY 3
Technical Presentation Sept 2017 www.gdgeo.com
- Flood Wall Analysis
CASE STUDY 3
- Conceptual hyrogeological model developed
- Model Developed for Current Condition
- Model Calibrated Against Dynamic Borehole Records
Current Ground Level
Current Low River Level 0.75 mOD Max Expected Tide appox. 1.60 mODDistance (m)
5 10 15 20 25 30 35 40 45 50 55
Elevation (m)
- 9.55
- 8.55
- 7.55
- 6.55
- 5.55
- 4.55
- 3.55
- 2.55
- 1.55
- 0.55
0.45 1.45 2.45 3.45 4.45 5.45
Technical Presentation Sept 2017 www.gdgeo.com
- Flood Wall Analysis
CASE STUDY 3
- Calibration Process
- Consider River Levels
- Tidal Variations
Technical Presentation Sept 2017 www.gdgeo.com
- Flood Wall Analysis
CASE STUDY 3
- Model Storm Events
- Consider River Levels
- Tidal Variations
- Design Options
- 1
1 2 3 4 5 6 12 18 24 30 36 Head (m) Time (hours)
The change in Head (m) over time (hours)
- 0.2
0.2 . 4 0.6 1
Low River Level -0.20 mOD Gravel Design Flood Level 3.80 mOD Gravel Silt Swale River Wall Flood Defence Wall Golf Course Road Hight Tide 1.54 mOD
0.32512 m³/days . 2 8 5 2 9 m ³ / d a y s
Distance (m)
5 10 15 20 25 30 35 40 45 50 55
Elevation (m)
- 9.55
- 8.55
- 7.55
- 6.55
- 5.55
- 4.55
- 3.55
- 2.55
- 1.55
- 0.55
0.45 1.45 2.45 3.45 4.45 5.45
Technical Presentation Sept 2017 www.gdgeo.com
- Piled-Raft for High Rise Development
CASE STUDY 4
- 32 Storey High Rise Development
- Several Concentrated Column Loads
with very high forces
- High wind moment on tower
- Piled-Raft deemed most
appropriate solution
- Stratigraphy consisted of London
Clay
Technical Presentation Sept 2017 www.gdgeo.com
- Piled-Raft for High Rise Development
CASE STUDY 4
Technical Presentation Sept 2017 www.gdgeo.com
- Piled-Raft for High Rise Development
CASE STUDY 4
- Non-linear soil model used
- Moment applied as an
eccentric force on a lever arm above the raft
- Pile Design optimised
iteratively
Technical Presentation Sept 2017 www.gdgeo.com
- Piled-Raft for High Rise Development
CASE STUDY 4
- Designed to a settlement criteria rather than
to a capacity value
- S<35mm
Technical Presentation Sept 2017 www.gdgeo.com
- Piled-Raft for High Rise Development
CASE STUDY 4
- Examine pile utilisation & optimise design
- Piles shortened by 7m
Technical Presentation Sept 2017 www.gdgeo.com
- Piled-Raft for High Rise Development
CASE STUDY 4
- Analyse the impact of
the new raft on existing contiguous wall along site boundary
- Contig wall predicted
to displace by approximately 9 mm
- Existing inclinometer
casings used as a cheap/efficient monitoring solution
Technical Presentation Sept 2017 www.gdgeo.com
- MARINA PILE SETTLEMENT ANALYSIS
- Redevelopment of Harbour, involving residential & office buildings on
piled pier
- Focus on estimating settlement of pipe piles
CASE STUDY 5
Technical Presentation Sept 2017 www.gdgeo.com
- MARINA PILE SETTLEMENT ANALYSIS
CASE STUDY 5
Technical Presentation Sept 2017 www.gdgeo.com
- MARINA PILE SETTLEMENT ANALYSIS
CASE STUDY 5
- Using state of the art
settlement models to assess foundation performance (in-house design tools)
- Excellent prediction
- Confirmed pile
acceptability
Technical Presentation Sept 2017 www.gdgeo.com
- Risk Modelling on a Large Scale (Rail Network)
CASE STUDY 6
2,800Km Track 4,900 Earthworks 5,100 Bridges 900 Level Crossings
Technical Presentation Sept 2017 www.gdgeo.com
Portarlington Derailment Aug 2008 Manulla Junction Landslide Aug 2007 Wicklow Derailment Nov 2009 Rushbrooke Rock Falls March 2014
- Recent Failures
CASE STUDY 6
Technical Presentation Sept 2017 www.gdgeo.com
Waterford Rockfall Dec 2013 Kilkenny Waterford Line Landslip Dec 2013 Tullamore Soil Slips and Rock Falls 2011/2012 Cabra Slope Failures 2012
CASE STUDY 6
Technical Presentation Sept 2017 www.gdgeo.com
PROBABILISTIC MODELLING
- High Level of Uncertainty Across the
Asset Characteristics
- Consider COV of input parameters
depending on data source
- Develop quantifiable risk profiles
- Hasofer Lind method used to
calculate the probability of failure associated with each asset and its coupled limit state
- Outputs: reliability index (β),
probability of failure
CASE STUDY 6
g(X) = R-S Pf probability
- f failure
ßs[g(x)] E[g(x)] E[g(x)]
s[g(x)]
ß[g(x)] =
Outputs: reliability index (β), probability of failure
Technical Presentation Sept 2017 www.gdgeo.com
- Risk Modelling on a Large Scale (Rail Network)
- Possible to quantify ground risk
- 4000 Assets
- No excuses for individual sites!
CASE STUDY 6
Technical Presentation Sept 2017 www.gdgeo.com
- Karst Risk Analysis
- Importance of Desk study research
CASE STUDY 7
Technical Presentation Sept 2017 www.gdgeo.com
CASE STUDY 7
Soil Profile from Intrusive Investigation Layer No. Depth below ground level (bgl) Soil Type Description 1 0.6 to 0.9 m Made Ground Grey sandy GRAVEL with cobbles 2 0.9 m to 4 m* Dynamic Probe No. T2 encountered soft soil to 11.1 m bgl. Glacial Till The till comprises reddish brown sandy gravelly, low plasticity CLAY. The fines content of the soil was between 35 and 50%. 3 Below 4 m Waulsortian Limestone Light Grey, massive reef
- LIMESTONE. The rock is strong to
very strong, with strong evidence
- f karst solution features
Technical Presentation Sept 2017 www.gdgeo.com
CASE STUDY 7
Soil Profile from Intrusive Investigation Layer No. Depth below ground level (bgl) Soil Type Description 1 0.6 to 0.9 m Made Ground Grey sandy GRAVEL with cobbles 2 0.9 m to 4 m* Dynamic Probe No. T2 encountered soft soil to 11.1 m bgl. Glacial Till The till comprises reddish brown sandy gravelly, low plasticity CLAY. The fines content of the soil was between 35 and 50%. 3 Below 4 m Waulsortian Limestone Light Grey, massive reef
- LIMESTONE. The rock is strong to
very strong, with strong evidence
- f karst solution features
Technical Presentation Sept 2017 www.gdgeo.com
CASE STUDY 7
- Geophysics used to map risk
Technical Presentation Sept 2017 www.gdgeo.com
CASE STUDY 7
- Pragmatic Construction Regime Proposed
Technical Presentation Sept 2017 www.gdgeo.com
SUMMARY
- Advanced design tools have a place in the right projects
- FEM can allow more efficient design, save money and decrease risk
- Calibration is critical
- Recommend numerical modelling coupled with observational
approach
- Monitoring provides the confidence to allow construction to proceed
- n time and in budget
Technical Presentation Sept 2017 www.gdgeo.com
- QUESTIONS ???