Use of Numerical Modelling to Mitigate Ground Risk CECA MEETING - - PowerPoint PPT Presentation

use of numerical modelling to mitigate ground risk
SMART_READER_LITE
LIVE PREVIEW

Use of Numerical Modelling to Mitigate Ground Risk CECA MEETING - - PowerPoint PPT Presentation

Use of Numerical Modelling to Mitigate Ground Risk CECA MEETING SEPT 2017 Gavin & Doherty Geosolutions Ltd. Overview Todays Presentation. o Introduction to GDG o Finite Element Modelling & Calibration o Case Studies o Flood


slide-1
SLIDE 1

Use of Numerical Modelling to Mitigate Ground Risk

Gavin & Doherty Geosolutions Ltd.

CECA MEETING – SEPT 2017

slide-2
SLIDE 2

Overview

  • Introduction to GDG
  • Finite Element Modelling & Calibration
  • Case Studies
  • Flood Defences
  • Retaining Walls
  • High rise foundations
  • Risk Analysis
  • Conclusions

Todays Presentation….

slide-3
SLIDE 3

GDG Introduction

  • Gavin & Doherty Geosolutions (GDG) is a specialist

geotechnical & civil engineering consultancy

  • Offices in London, Edinburgh, Dublin, and Belfast,
  • GDG was formed in 2011 in a challenging market
  • Grown throughout the last five years
  • Team of 40 highly talented engineers
  • Majority of our staff are PhD qualified
  • We provide innovative geotechnical solutions & efficient

civil engineering designs for challenging projects About us ….

slide-4
SLIDE 4

Engineering Design Services

Structures Infrastructure Offshore Renewables R&D

slide-5
SLIDE 5

Engineering Design Services

  • Concept Design
  • Site Investigation Scoping
  • Site Investigation

Interpretation

  • Civil Engineering Design
  • Temporary Works Design
  • Numerical Modelling (FEA)
  • Performance monitoring /

instrumentation analysis

  • Expert Witness Services
slide-6
SLIDE 6

INFRASTRUCTURE

slide-7
SLIDE 7

INFRASTRUCTURE

  • Geotechnical Interpretation & Ground

Modelling for Road, Railway and Flood Defence Schemes

  • Geological Assessments & Mapping
  • Earthworks Design
  • Material Suitability
  • Hydrogeological review
  • Civil Engineering Design
  • Numerical Modelling
  • Soil-Structure-Water Interaction Analysis
  • Back-analysis of failures & Root Cause Analysis

SERVICES & EXPERTISE

slide-8
SLIDE 8

URBAN STRUCTURES

slide-9
SLIDE 9

URBAN STRUCTURES

SERVICES & EXPERTISE

  • Basement & Foundation Engineering
  • Soil-Structure Interaction
  • Ground Movement Assessments
  • Retaining Wall Analysis
  • Excavation Support and Propping Design
  • Construction Sequencing & Temporary Works
  • Pile Design & Piled Raft Analysis
  • Tunnel and basement impact assessments
  • Ground Improvement Engineering
slide-10
SLIDE 10

OFFSHORE & MARINE

slide-11
SLIDE 11

OFFSHORE & MARINE

SERVICES & EXPERTISE

  • Analysis and Design of Ports & Harbours
  • Quay Wall Numerical Modelling
  • Offshore Substructure Analysis
  • Offshore wind foundation engineering
  • Gravity structures, monopiles, jacket piles, etc…
  • Pile Installation analysis & Interpretation of
  • ffshore driving data
  • Site suitability assessments
  • Jack-up vessel studies
  • Back-analysis of failures & Root Cause Analysis
slide-12
SLIDE 12
  • NNG Wind Farm
  • Rampion Wind Farm
  • Zawtika Gas Jacket Pile Analysis
  • Hornsea Met Mast
  • Firth of Forth Wind Farm Forensics
  • Dogger Bank Jackup Analysis
  • Shell Conductor Installation Studies North Sea
  • Horizont Jacket Pile FEED

RELEVANT PROJECTS RENEWABLES

slide-13
SLIDE 13

RENEWABLES

SERVICES & EXPERTISE

  • Site suitability and feasibility studies for
  • nshore wind and onshore solar farms
  • Geotechnical risk studies
  • Peat stability assessments
  • Earthworks engineering for roads, crane bases,

hardstands, etc.

  • Foundation design for gravity and piled bases
  • Interaction analysis for soil-structure-turbine

behaviour.

slide-14
SLIDE 14

Technical Presentation Sept 2017 www.gdgeo.com

  • What is Ground Risk ?

Ground Risk

slide-15
SLIDE 15

Technical Presentation Sept 2017 www.gdgeo.com

  • Analytical – Traditional Theoretical Hand (spreadsheet)

Calculations

  • Empirical – Traditional Approaches based on experience
  • f empirical evidence
  • Numerical – Finite Element (or Finite Difference)
  • Observational Design Approaches

Pick the most appropriate tool for your project (consider the limitations of the tool, the complexity of the project and the accuracy required)

Design Tools Available

slide-16
SLIDE 16

Technical Presentation Sept 2017 www.gdgeo.com

  • Numerical Modelling Procedure to Determine Soil-

Structure Response

  • Modern Software Capable of Considering Complex

Geometries

  • The geometry is discretised into a mesh and the stresses

and strains are resolved as loads/actions are applied

  • Can accurately determine ground movements and

structural stresses, provided the model is well calibrated

  • Calibration requires (a) DATA and (b) EXPERTISE

Finite Element Method

slide-17
SLIDE 17

Technical Presentation Sept 2017 www.gdgeo.com

  • Soil is highly non-linear

– Pick an appropriate constitutive model

Basics of Geotechnics

Stress Strain Real Soil Elastic-Plastic

slide-18
SLIDE 18

Technical Presentation Sept 2017 www.gdgeo.com

  • FEM CALIBRATION

– Simulation of Lab Testing – Look for repeatability – Use range of test types

Finite Element Method

slide-19
SLIDE 19

Technical Presentation Sept 2017 www.gdgeo.com

  • FEM CALIBRATION

– Simulation of Field Testing

Finite Element Method

slide-20
SLIDE 20

Technical Presentation Sept 2017 www.gdgeo.com

  • TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
  • Access Shaft for TBM
  • Complex Ground Conditions
  • Underlying Aquifer
  • Base Heave a Serious Concern !
  • Design Solution Needed

CASE STUDY 1

slide-21
SLIDE 21

Technical Presentation Sept 2017 www.gdgeo.com

  • Model Calibration

CASE STUDY 1

Non-Plastic Till Fine Sand to Silt Plastic Till Sand to Sand and Gravel 𝑬𝒔𝒃𝒋𝒐𝒃𝒉𝒇 𝑼𝒛𝒒𝒇

  • Drained

Drained Undrained Drained 𝑸𝒇𝒔𝒏𝒇𝒃𝒄𝒋𝒎𝒋𝒖𝒛 𝑛 𝑡 1 × 10−6 4 × 10−5 8 × 10−8 3 × 10−4 𝜹𝒗𝒐𝒕𝒃𝒖 𝑙𝑂 𝑛3 18 18 24 18 𝜹𝒕𝒃𝒖 𝑙𝑂 𝑛3 20 20 24.3 20 𝒇𝟏

  • 0.5

0.5 0.301 0.5 𝑭𝟔𝟏

𝒔𝒇𝒈

𝑁𝑄𝑏 30 30 20 30 𝑭𝒑𝒇𝒆

𝒔𝒇𝒈

𝑁𝑄𝑏 30 30 20 30 𝑭𝒗𝒔

𝒔𝒇𝒈

𝑁𝑄𝑏 90 90 80 90 𝑸𝒑𝒙𝒇𝒔 (𝒏)

  • 0.5

0.5 0.5 0.5 𝒅𝒔𝒇𝒈 𝑙𝑄𝑏 𝝌 ° 35 35 35.9 35 𝝎 ° 5 5 9 5 𝒒𝒔𝒇𝒈 𝑙𝑄𝑏 100 100 100 100 𝑺𝒈

  • 0.9

0.9 0.9 0.9 𝒍𝟏,𝒚

  • 1

0.8 1.2 0.8

slide-22
SLIDE 22

Technical Presentation Sept 2017 www.gdgeo.com

  • TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
  • Undrained versus Drained

CASE STUDY 1

slide-23
SLIDE 23

Technical Presentation Sept 2017 www.gdgeo.com

  • TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS

CASE STUDY 1

slide-24
SLIDE 24

Technical Presentation Sept 2017 www.gdgeo.com

  • TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS

CASE STUDY 1

slide-25
SLIDE 25

Technical Presentation Sept 2017 www.gdgeo.com

  • TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS

CASE STUDY 1

slide-26
SLIDE 26

Technical Presentation Sept 2017 www.gdgeo.com

  • TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
  • Pore Pressures

(a) End of Excavation (b) 10 weeks (c) 20 weeks (d) 50 weeks

CASE STUDY 1

(a) (b) (c) (d)

slide-27
SLIDE 27

Technical Presentation Sept 2017 www.gdgeo.com

  • TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
  • Failure Avoided
  • Facilitated Economic Construction Sequence
  • Observational Method Used to Minimise Risk

CASE STUDY 1

slide-28
SLIDE 28

Technical Presentation Sept 2017 www.gdgeo.com

  • NATIONAL GALLERY UNDERPINNING ANALYSIS

CASE STUDY 2

Facilitate basement extension

  • Geotechnical interpretation
  • Geophysical profiling
  • 3D Settlement Analysis of

Construction Stages

  • Recommendation about

underpinning construction

  • Final settlement design for

temporary and permanent works.

slide-29
SLIDE 29

Technical Presentation Sept 2017 www.gdgeo.com

  • NATIONAL GALLERY UNDERPINNING ANALYSIS

CASE STUDY 2

slide-30
SLIDE 30

Technical Presentation Sept 2017 www.gdgeo.com

  • NATIONAL GALLERY UNDERPINNING ANALYSIS

CASE STUDY 2

slide-31
SLIDE 31

Technical Presentation Sept 2017 www.gdgeo.com

  • NATIONAL GALLERY UNDERPINNING ANALYSIS

CASE STUDY 2

slide-32
SLIDE 32

Technical Presentation Sept 2017 www.gdgeo.com

  • NATIONAL GALLERY UNDERPINNING ANALYSIS

CASE STUDY 2

slide-33
SLIDE 33

Technical Presentation Sept 2017 www.gdgeo.com

  • NATIONAL GALLERY UNDERPINNING
  • Settlements predicted to be less than 10mm in worst

case

  • Generally less than 5 mm
  • Concrete underpinning shown to be appropriate,

however construction quality control critical

  • Monitoring system tailored to target critical area of the

building and critical point in the construction timeline

  • Constant monitoring compared to design predictions

with target levels set to stop construction if required.

CASE STUDY 2

slide-34
SLIDE 34

Technical Presentation Sept 2017 www.gdgeo.com

  • Flood Defences

CASE STUDY 3

slide-35
SLIDE 35

Technical Presentation Sept 2017 www.gdgeo.com

  • Flood Wall Analysis

CASE STUDY 3

  • Stability Modelling
  • Seepage Analysis

Deemed Critical

slide-36
SLIDE 36

Technical Presentation Sept 2017 www.gdgeo.com

  • Flood Defence Design

CASE STUDY 3

slide-37
SLIDE 37

Technical Presentation Sept 2017 www.gdgeo.com

  • Flood Risk Analysis

CASE STUDY 3

slide-38
SLIDE 38

Technical Presentation Sept 2017 www.gdgeo.com

  • Flood Risk Analysis

CASE STUDY 3

0.2 0.4 0.6 0.8 1 1.2 1 . 4 1.6 1.8 2 2.2 2 . 4 2.6

Design Flood Level

Gravel Gravel Silt

Peat

. 6 8 2 2 m ³ / d a y s 2.8537 m³/days 0.12612 m³/days

Distance (m)

5 10 15 20 25 30 35

Elevation (m)

  • 13.5
  • 12.5
  • 11.5
  • 10.5
  • 9.5
  • 8.5
  • 7.5
  • 6.5
  • 5.5
  • 4.5
  • 3.5
  • 2.5
  • 1.5
  • 0.5

0.5 1.5 2.5 3.5 4.5 5.5

slide-39
SLIDE 39

Technical Presentation Sept 2017 www.gdgeo.com

  • Flood Risk Analysis

CASE STUDY 3

0.2 0.4 0.6 0.8 1 1.2 1 . 4 1.6 1.8 2 2.2 2 . 4 2.6

Design Flood Level

Gravel Gravel Silt

Peat

. 6 8 2 2 m ³ / d a y s 2.8537 m³/days 0.12612 m³/days

Distance (m)

5 10 15 20 25 30 35

Elevation (m)

  • 13.5
  • 12.5
  • 11.5
  • 10.5
  • 9.5
  • 8.5
  • 7.5
  • 6.5
  • 5.5
  • 4.5
  • 3.5
  • 2.5
  • 1.5
  • 0.5

0.5 1.5 2.5 3.5 4.5 5.5 . 4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 2.2 2 . 4 2.6 2.8

Gravel Gravel Silt

Peat

Distance (m)

5 10 15 20 25 30 35

Elevation (m)

  • 13.5
  • 12.5
  • 11.5
  • 10.5
  • 9.5
  • 8.5
  • 7.5
  • 6.5
  • 5.5
  • 4.5
  • 3.5
  • 2.5
  • 1.5
  • 0.5

0.5 1.5 2.5 3.5 4.5 5.5

slide-40
SLIDE 40

Technical Presentation Sept 2017 www.gdgeo.com

  • Flood Risk Analysis

CASE STUDY 3

slide-41
SLIDE 41

Technical Presentation Sept 2017 www.gdgeo.com

  • Flood Wall Analysis

CASE STUDY 3

  • Conceptual hyrogeological model developed
  • Model Developed for Current Condition
  • Model Calibrated Against Dynamic Borehole Records

Current Ground Level

Current Low River Level 0.75 mOD Max Expected Tide appox. 1.60 mOD

Distance (m)

5 10 15 20 25 30 35 40 45 50 55

Elevation (m)

  • 9.55
  • 8.55
  • 7.55
  • 6.55
  • 5.55
  • 4.55
  • 3.55
  • 2.55
  • 1.55
  • 0.55

0.45 1.45 2.45 3.45 4.45 5.45

slide-42
SLIDE 42

Technical Presentation Sept 2017 www.gdgeo.com

  • Flood Wall Analysis

CASE STUDY 3

  • Calibration Process
  • Consider River Levels
  • Tidal Variations
slide-43
SLIDE 43

Technical Presentation Sept 2017 www.gdgeo.com

  • Flood Wall Analysis

CASE STUDY 3

  • Model Storm Events
  • Consider River Levels
  • Tidal Variations
  • Design Options
  • 1

1 2 3 4 5 6 12 18 24 30 36 Head (m) Time (hours)

The change in Head (m) over time (hours)

  • 0.2

0.2 . 4 0.6 1

Low River Level -0.20 mOD Gravel Design Flood Level 3.80 mOD Gravel Silt Swale River Wall Flood Defence Wall Golf Course Road Hight Tide 1.54 mOD

0.32512 m³/days . 2 8 5 2 9 m ³ / d a y s

Distance (m)

5 10 15 20 25 30 35 40 45 50 55

Elevation (m)

  • 9.55
  • 8.55
  • 7.55
  • 6.55
  • 5.55
  • 4.55
  • 3.55
  • 2.55
  • 1.55
  • 0.55

0.45 1.45 2.45 3.45 4.45 5.45

slide-44
SLIDE 44

Technical Presentation Sept 2017 www.gdgeo.com

  • Piled-Raft for High Rise Development

CASE STUDY 4

  • 32 Storey High Rise Development
  • Several Concentrated Column Loads

with very high forces

  • High wind moment on tower
  • Piled-Raft deemed most

appropriate solution

  • Stratigraphy consisted of London

Clay

slide-45
SLIDE 45

Technical Presentation Sept 2017 www.gdgeo.com

  • Piled-Raft for High Rise Development

CASE STUDY 4

slide-46
SLIDE 46

Technical Presentation Sept 2017 www.gdgeo.com

  • Piled-Raft for High Rise Development

CASE STUDY 4

  • Non-linear soil model used
  • Moment applied as an

eccentric force on a lever arm above the raft

  • Pile Design optimised

iteratively

slide-47
SLIDE 47

Technical Presentation Sept 2017 www.gdgeo.com

  • Piled-Raft for High Rise Development

CASE STUDY 4

  • Designed to a settlement criteria rather than

to a capacity value

  • S<35mm
slide-48
SLIDE 48

Technical Presentation Sept 2017 www.gdgeo.com

  • Piled-Raft for High Rise Development

CASE STUDY 4

  • Examine pile utilisation & optimise design
  • Piles shortened by 7m
slide-49
SLIDE 49

Technical Presentation Sept 2017 www.gdgeo.com

  • Piled-Raft for High Rise Development

CASE STUDY 4

  • Analyse the impact of

the new raft on existing contiguous wall along site boundary

  • Contig wall predicted

to displace by approximately 9 mm

  • Existing inclinometer

casings used as a cheap/efficient monitoring solution

slide-50
SLIDE 50

Technical Presentation Sept 2017 www.gdgeo.com

  • MARINA PILE SETTLEMENT ANALYSIS
  • Redevelopment of Harbour, involving residential & office buildings on

piled pier

  • Focus on estimating settlement of pipe piles

CASE STUDY 5

slide-51
SLIDE 51

Technical Presentation Sept 2017 www.gdgeo.com

  • MARINA PILE SETTLEMENT ANALYSIS

CASE STUDY 5

slide-52
SLIDE 52

Technical Presentation Sept 2017 www.gdgeo.com

  • MARINA PILE SETTLEMENT ANALYSIS

CASE STUDY 5

  • Using state of the art

settlement models to assess foundation performance (in-house design tools)

  • Excellent prediction
  • Confirmed pile

acceptability

slide-53
SLIDE 53

Technical Presentation Sept 2017 www.gdgeo.com

  • Risk Modelling on a Large Scale (Rail Network)

CASE STUDY 6

2,800Km Track 4,900 Earthworks 5,100 Bridges 900 Level Crossings

slide-54
SLIDE 54

Technical Presentation Sept 2017 www.gdgeo.com

Portarlington Derailment Aug 2008 Manulla Junction Landslide Aug 2007 Wicklow Derailment Nov 2009 Rushbrooke Rock Falls March 2014

  • Recent Failures

CASE STUDY 6

slide-55
SLIDE 55

Technical Presentation Sept 2017 www.gdgeo.com

Waterford Rockfall Dec 2013 Kilkenny Waterford Line Landslip Dec 2013 Tullamore Soil Slips and Rock Falls 2011/2012 Cabra Slope Failures 2012

CASE STUDY 6

slide-56
SLIDE 56

Technical Presentation Sept 2017 www.gdgeo.com

PROBABILISTIC MODELLING

  • High Level of Uncertainty Across the

Asset Characteristics

  • Consider COV of input parameters

depending on data source

  • Develop quantifiable risk profiles
  • Hasofer Lind method used to

calculate the probability of failure associated with each asset and its coupled limit state

  • Outputs: reliability index (β),

probability of failure

CASE STUDY 6

g(X) = R-S Pf probability

  • f failure

ßs[g(x)] E[g(x)] E[g(x)]

s[g(x)]

ß[g(x)] =

Outputs: reliability index (β), probability of failure

slide-57
SLIDE 57

Technical Presentation Sept 2017 www.gdgeo.com

  • Risk Modelling on a Large Scale (Rail Network)
  • Possible to quantify ground risk
  • 4000 Assets
  • No excuses for individual sites!

CASE STUDY 6

slide-58
SLIDE 58

Technical Presentation Sept 2017 www.gdgeo.com

  • Karst Risk Analysis
  • Importance of Desk study research

CASE STUDY 7

slide-59
SLIDE 59

Technical Presentation Sept 2017 www.gdgeo.com

CASE STUDY 7

Soil Profile from Intrusive Investigation Layer No. Depth below ground level (bgl) Soil Type Description 1 0.6 to 0.9 m Made Ground Grey sandy GRAVEL with cobbles 2 0.9 m to 4 m* Dynamic Probe No. T2 encountered soft soil to 11.1 m bgl. Glacial Till The till comprises reddish brown sandy gravelly, low plasticity CLAY. The fines content of the soil was between 35 and 50%. 3 Below 4 m Waulsortian Limestone Light Grey, massive reef

  • LIMESTONE. The rock is strong to

very strong, with strong evidence

  • f karst solution features
slide-60
SLIDE 60

Technical Presentation Sept 2017 www.gdgeo.com

CASE STUDY 7

Soil Profile from Intrusive Investigation Layer No. Depth below ground level (bgl) Soil Type Description 1 0.6 to 0.9 m Made Ground Grey sandy GRAVEL with cobbles 2 0.9 m to 4 m* Dynamic Probe No. T2 encountered soft soil to 11.1 m bgl. Glacial Till The till comprises reddish brown sandy gravelly, low plasticity CLAY. The fines content of the soil was between 35 and 50%. 3 Below 4 m Waulsortian Limestone Light Grey, massive reef

  • LIMESTONE. The rock is strong to

very strong, with strong evidence

  • f karst solution features
slide-61
SLIDE 61

Technical Presentation Sept 2017 www.gdgeo.com

CASE STUDY 7

  • Geophysics used to map risk
slide-62
SLIDE 62

Technical Presentation Sept 2017 www.gdgeo.com

CASE STUDY 7

  • Pragmatic Construction Regime Proposed
slide-63
SLIDE 63

Technical Presentation Sept 2017 www.gdgeo.com

SUMMARY

  • Advanced design tools have a place in the right projects
  • FEM can allow more efficient design, save money and decrease risk
  • Calibration is critical
  • Recommend numerical modelling coupled with observational

approach

  • Monitoring provides the confidence to allow construction to proceed
  • n time and in budget
slide-64
SLIDE 64

Technical Presentation Sept 2017 www.gdgeo.com

  • QUESTIONS ???

Contact: Paul Doherty pdoherty@gdgeo.com

Conclusions