September 24th, 2018
Update Report
Mitchell School Building Committee Meeting
Raymond Design Associates
Schematic Design
1
1
Update Report September 24 th , 2018 Raymond Design Associates 1 - - PowerPoint PPT Presentation
Mitchell School Building Committee Meeting Schematic Design Update Report September 24 th , 2018 Raymond Design Associates 1 1 Existing Conditions Geotechnical / Environmental Clean Site Based on Historical Aerials, Site was
September 24th, 2018
Mitchell School Building Committee Meeting
Raymond Design Associates
Schematic Design
1
1
2
Clean Site
Review of Previous Test Pit Data
Hazardous Materials In Building
3
Roof
Steel Frame
Foundations and Slabs
Reuse
4
Condition
Recommendations
5
Plumbing
Fire Protection
6
Existing Conditions
Recommendations
7
8
9
10
Proposed
MSBA Guideline
11
Proposed
MSBA Guideline
12
13
14
Kindergarten Pod 1st Grade Pod 2nd Grade Pod 2nd Grade Pod 1st Grade Pod PK Pod Ground Floor Two Floors Two Floors
15
16
17
18
2nd Grade Pod Kindergarten Pod 1st Grade Pod PK Pod Ground Floor PK Pod Ground Floor Core Facilities
19
20
21