Update Report September 24 th , 2018 Raymond Design Associates 1 - - PowerPoint PPT Presentation

update report
SMART_READER_LITE
LIVE PREVIEW

Update Report September 24 th , 2018 Raymond Design Associates 1 - - PowerPoint PPT Presentation

Mitchell School Building Committee Meeting Schematic Design Update Report September 24 th , 2018 Raymond Design Associates 1 1 Existing Conditions Geotechnical / Environmental Clean Site Based on Historical Aerials, Site was


slide-1
SLIDE 1

September 24th, 2018

Update Report

Mitchell School Building Committee Meeting

Raymond Design Associates

Schematic Design

1

1

slide-2
SLIDE 2

2

Existing Conditions – Geotechnical / Environmental

Clean Site

  • Based on Historical Aerials, Site was Undeveloped Until 1995/96
  • Urban Fill is Not Anticipated
  • No Underground Storage Tanks
  • No Neighboring Sites that Pose an Environmental Risk to the Site

Review of Previous Test Pit Data

  • Granular Fill Underlain by Course Sand and Gravel Over Glacial Till
  • No Cracks in Foundation
  • Should be Favorable for Supporting New Structures on Spread Footings
  • Excavated Soils Should Be Suitable for Structural and/or Common Fill
  • Borings Required to Confirm any Organic Matter

Hazardous Materials In Building

  • No ACM Identified but Could Find Mastics, Caulking, and/or Ballasts
slide-3
SLIDE 3

3

Existing Conditions – Structural

Roof

  • Wood Trusses Have Numerous Construction Deficiencies
  • Steel Bar Joists Are Flexible and Not Anchored Correctly to Steel Frame

Steel Frame

  • Mixture of Lateral Resistance Systems
  • Several Masonry Walls Not Anchored to the Roof or Floor Structure

Foundations and Slabs

  • Multiple Cracks in Floor Slabs Due to Flexibility of the Floor System
  • Lacks Expansion Joints

Reuse

  • Extensive Modifications Would Be Required for Reuse / Reconfiguration
  • Must Be Brought Up to New Code if Plan or Roof are Reconfigured
  • Reinforce Moment Frames and Foundations Supporting Columns
slide-4
SLIDE 4

4

Existing Conditions – Mechanical

Condition

  • 1996 – 22 Years Old and in Only FAIR Condition
  • Boiler Plant and Terminal Heating Devices are Very Near End of Service Life
  • Boilers Have 8-Yrs Left and Are Only 80% Efficient (new are 92%+)
  • Pumps and Valving Are in Poor Condition
  • Temperature Control System Provides Minimal Control
  • Poor Indoor Air Quality
  • Classroom Unit Ventilators are an Acoustic Issue
  • Ductwork and Units in Attic Will Be Expensive to Keep with Roof Replacement

Recommendations

  • Complete New HVAC System that is Efficient and Provides Appropriate Control
  • New HVAC System that Provides Appropriate Indoor Air Quality
  • Only Piping MIGHT be Salvageable
slide-5
SLIDE 5

5

Existing Conditions – Plumbing / Fire Protection

Plumbing

  • Water Service Adequate
  • Hot Water Boiler is Adequate – Redundant Storage Tanks Recommended
  • All Fixtures Need to Be Replaced with Water-Conserving Fixtures
  • All Storm Drainage Systems (gutter/downspouts) Should be Replaced
  • Any Roof-Supported Piping is Subject to Joint Cracks during Roof Replacement
  • Kitchen Plumbing and Gas Lines Should be Replaced to All Equipment

Fire Protection

  • Remove and Replace All Fire Protection Heads
  • Any Roof-Supported Piping is Subject to Joint Cracks during Roof Replacement
  • BFD Should Provide a Complete System Review
slide-6
SLIDE 6

6

Existing Conditions – Electrical / Life Safety

Existing Conditions

  • Service and Switchgear is in Fair to Good Condition
  • Power Distribution System is in Generally Fair Condition
  • Security and Communication Systems are Obsolete and Only Partially Intact
  • Emergency Standby System is No Longer Compliant due to Code Changes
  • Fire Alarm System is Obsolete and Does Not Meet Code, Including Voice Evac
  • Lighting Systems are Obsolete and Not Up to Energy Efficiency Standards
  • Most Equipment is Near the End of it’s 20-25 Year Service Life

Recommendations

  • The Entire Electrical System Should be Replaced Under a Renovation Program
  • Install a Bi-Directional Antenna System
  • Install a Lightning Protection System
  • In a Pinch, Could Reuse and Supplement Switchboard, Panels, and Transformers
  • Need New Lighting, Life Safety, Security, and Communications Systems
slide-7
SLIDE 7

7

Opt A: Code Upgrade

slide-8
SLIDE 8

8

Opt A: Code Upgrade Scope

  • New LGM Truss Roof Structure with R-30 Cold Roof Panels – Same Configuration
  • New Steel Bar Joist Roof Structure at Media Center, Cafeteria, and Kitchen
  • Brace Existing CMU Bearing Walls Where Roofs Removed (i.e. Gymnasium)
  • New 40-Year Fiberglass Shingles with Metal Eaves & Soffits
  • Clean out Wall Cavities, New Brick Veneer, Cavity Sheathing, & Air Barrier System
  • Maintain Interior Drywall with Spray Foam Insulation into Stud Bays From Exterior
  • New Windows and Doors Integrated into the Air Barrier System
  • Expose Foundation and Install Waterproof Membrane Integrated into Air Barrier
  • New Interior GWB Where Studs are Exposed, Patch All Other Existing GWB
  • New Doors and Hardware Where Removed in the Damaged Areas
  • Paint All Wall Surfaces in Classroom Wings
  • New ACT Ceiling and Lighting Systems at Roof Removal and Damaged Areas
  • New VCT Flooring Where Removed in the Damaged Areas
  • New HVAC System Throughout the Entire School (roof removal & end of life)
  • New Life Safety Systems Throughout the Entire School
  • ADA and Elevator (2) Modernization Allowances
  • Electrical, Fire Protection, & Plumbing Repair/Upgrade Allowances
slide-9
SLIDE 9

Space Summary Update

9

slide-10
SLIDE 10

10

PK-2 Programming Update

Proposed

MSBA Guideline

  • 1,530 gsf
slide-11
SLIDE 11

11

PK-3 Programming Update

Proposed

MSBA Guideline

  • 405 gsf
slide-12
SLIDE 12

Preliminary PK-2 Floor Plan Organizations

12

slide-13
SLIDE 13

13

Opt 740 B.1: PK-2 Add/Reno

slide-14
SLIDE 14

14

Opt 740 B.1: PK-2 Add/Reno

Kindergarten Pod 1st Grade Pod 2nd Grade Pod 2nd Grade Pod 1st Grade Pod PK Pod Ground Floor Two Floors Two Floors

slide-15
SLIDE 15

15

Opt 740 B.1: PK-2 Add/Reno

slide-16
SLIDE 16

16

Opt 740 B.1: PK-2 Add/Reno

slide-17
SLIDE 17

17

Opt 740 C.1: New PK-2 School

slide-18
SLIDE 18

18

2nd Grade Pod Kindergarten Pod 1st Grade Pod PK Pod Ground Floor PK Pod Ground Floor Core Facilities

740 C.1: New PK-2 School

slide-19
SLIDE 19

19

Opt 740 D.1: New PK-2 School

slide-20
SLIDE 20

20

Opt 740 E.1: New PK-2 School

slide-21
SLIDE 21

Questions & Comments

21