update report
play

Update Report September 24 th , 2018 Raymond Design Associates 1 - PowerPoint PPT Presentation

Mitchell School Building Committee Meeting Schematic Design Update Report September 24 th , 2018 Raymond Design Associates 1 1 Existing Conditions Geotechnical / Environmental Clean Site Based on Historical Aerials, Site was


  1. Mitchell School Building Committee Meeting Schematic Design Update Report September 24 th , 2018 Raymond Design Associates 1 1

  2. Existing Conditions – Geotechnical / Environmental Clean Site • Based on Historical Aerials, Site was Undeveloped Until 1995/96 • Urban Fill is Not Anticipated • No Underground Storage Tanks • No Neighboring Sites that Pose an Environmental Risk to the Site Review of Previous Test Pit Data • Granular Fill Underlain by Course Sand and Gravel Over Glacial Till • No Cracks in Foundation • Should be Favorable for Supporting New Structures on Spread Footings • Excavated Soils Should Be Suitable for Structural and/or Common Fill • Borings Required to Confirm any Organic Matter Hazardous Materials In Building • No ACM Identified but Could Find Mastics, Caulking, and/or Ballasts 2

  3. Existing Conditions – Structural Roof • Wood Trusses Have Numerous Construction Deficiencies • Steel Bar Joists Are Flexible and Not Anchored Correctly to Steel Frame Steel Frame • Mixture of Lateral Resistance Systems • Several Masonry Walls Not Anchored to the Roof or Floor Structure Foundations and Slabs • Multiple Cracks in Floor Slabs Due to Flexibility of the Floor System • Lacks Expansion Joints Reuse • Extensive Modifications Would Be Required for Reuse / Reconfiguration • Must Be Brought Up to New Code if Plan or Roof are Reconfigured • Reinforce Moment Frames and Foundations Supporting Columns 3

  4. Existing Conditions – Mechanical Condition • 1996 – 22 Years Old and in Only FAIR Condition • Boiler Plant and Terminal Heating Devices are Very Near End of Service Life • Boilers Have 8-Yrs Left and Are Only 80% Efficient (new are 92%+) • Pumps and Valving Are in Poor Condition • Temperature Control System Provides Minimal Control • Poor Indoor Air Quality • Classroom Unit Ventilators are an Acoustic Issue • Ductwork and Units in Attic Will Be Expensive to Keep with Roof Replacement Recommendations • Complete New HVAC System that is Efficient and Provides Appropriate Control • New HVAC System that Provides Appropriate Indoor Air Quality • Only Piping MIGHT be Salvageable 4

  5. Existing Conditions – Plumbing / Fire Protection Plumbing • Water Service Adequate • Hot Water Boiler is Adequate – Redundant Storage Tanks Recommended • All Fixtures Need to Be Replaced with Water-Conserving Fixtures • All Storm Drainage Systems (gutter/downspouts) Should be Replaced • Any Roof-Supported Piping is Subject to Joint Cracks during Roof Replacement • Kitchen Plumbing and Gas Lines Should be Replaced to All Equipment Fire Protection • Remove and Replace All Fire Protection Heads • Any Roof-Supported Piping is Subject to Joint Cracks during Roof Replacement • BFD Should Provide a Complete System Review 5

  6. Existing Conditions – Electrical / Life Safety Existing Conditions • Service and Switchgear is in Fair to Good Condition • Power Distribution System is in Generally Fair Condition • Security and Communication Systems are Obsolete and Only Partially Intact • Emergency Standby System is No Longer Compliant due to Code Changes • Fire Alarm System is Obsolete and Does Not Meet Code, Including Voice Evac • Lighting Systems are Obsolete and Not Up to Energy Efficiency Standards • Most Equipment is Near the End of it’s 20-25 Year Service Life Recommendations • The Entire Electrical System Should be Replaced Under a Renovation Program • Install a Bi-Directional Antenna System • Install a Lightning Protection System • In a Pinch, Could Reuse and Supplement Switchboard, Panels, and Transformers • Need New Lighting, Life Safety, Security, and Communications Systems 6

  7. Opt A: Code Upgrade 7

  8. Opt A: Code Upgrade Scope • New LGM Truss Roof Structure with R-30 Cold Roof Panels – Same Configuration • New Steel Bar Joist Roof Structure at Media Center, Cafeteria, and Kitchen • Brace Existing CMU Bearing Walls Where Roofs Removed (i.e. Gymnasium) • New 40-Year Fiberglass Shingles with Metal Eaves & Soffits • Clean out Wall Cavities, New Brick Veneer, Cavity Sheathing, & Air Barrier System • Maintain Interior Drywall with Spray Foam Insulation into Stud Bays From Exterior • New Windows and Doors Integrated into the Air Barrier System • Expose Foundation and Install Waterproof Membrane Integrated into Air Barrier • New Interior GWB Where Studs are Exposed, Patch All Other Existing GWB • New Doors and Hardware Where Removed in the Damaged Areas • Paint All Wall Surfaces in Classroom Wings • New ACT Ceiling and Lighting Systems at Roof Removal and Damaged Areas • New VCT Flooring Where Removed in the Damaged Areas • New HVAC System Throughout the Entire School (roof removal & end of life) • New Life Safety Systems Throughout the Entire School • ADA and Elevator (2) Modernization Allowances • Electrical, Fire Protection, & Plumbing Repair/Upgrade Allowances 8

  9. Space Summary Update 9

  10. PK-2 Programming Update Proposed MSBA Guideline -1,530 gsf 10

  11. PK-3 Programming Update Proposed MSBA Guideline -405 gsf 11

  12. Preliminary PK-2 Floor Plan Organizations 12

  13. Opt 740 B.1: PK-2 Add/Reno 13

  14. Opt 740 B.1: PK-2 Add/Reno 2 nd Grade 2 nd Grade Two Pod Pod Floors 1 st Grade 1 st Grade Two Pod Floors Pod PK Pod Kindergarten Ground Floor Pod 14

  15. Opt 740 B.1: PK-2 Add/Reno 15

  16. Opt 740 B.1: PK-2 Add/Reno 16

  17. Opt 740 C.1: New PK-2 School 17

  18. 740 C.1: New PK-2 School 2 nd Grade Pod 1 st Grade Pod PK Pod Ground Floor Core Facilities PK Pod Ground Kindergarten Floor Pod 18

  19. Opt 740 D.1: New PK-2 School 19

  20. Opt 740 E.1: New PK-2 School 20

  21. Questions & Comments 21

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend