REFERENCE - FOTO PRESENTATION PROJECT: Construction of K7 and TG3 unit in Plzesk teplrensk, a.s. GREEN UNIT INVELT HOLDING Project management, interdisciplinary coordination and completion INVELT INVELT INVELT SERVIS


slide-1
SLIDE 1

REFERENCE - FOTO PRESENTATION PROJECT: Construction of K7 and TG3 unit in Plzeňská teplárenská, a.s. „GREEN UNIT“

slide-2
SLIDE 2
slide-3
SLIDE 3

INVELT ELEKTRO INVELT ENERGO INVELT SERVIS INVELT HOLDING

Project, manufacture, supply and commissioning

  • DCS (Honeywell)
  • TG3 turbine control system
  • Excitation system with ABB

UNITROL

  • Electrical protections,

measurement and synchronization (ABB) Project, manufacture, supply and commissioning

  • Output and neutral cubicle of

the TG3 11.5MWe generator

  • Generator breaker
  • MCC 400VAC, 220VDC

Project, manufacture, supply and commissioning

  • Technological equipment of

K7 biomass boiler

  • Field instrumentation

Project management, interdisciplinary coordination and completion

slide-4
SLIDE 4

Manufacture and installation of the boiler technological equipment

slide-5
SLIDE 5

K7 boiler, drum, wood chips combustion

slide-6
SLIDE 6

Field instrumentation – conductivity measurement, emission monitoring etc.

slide-7
SLIDE 7

Unit DCS system (Honeywell) - boiler house, machine room etc.

slide-8
SLIDE 8

TG3 turbine control system, Siemens Simatic S7 400

slide-9
SLIDE 9

Electrical room under TG3 – generator output and neutral cubicle (MTB), generator breaker, ABB excitation system, ABB electrical protections, measurement and synchronization

slide-10
SLIDE 10

MCC 400VAC, 220VDC