tullamarine landfill community meeting
play

Tullamarine Landfill Community Meeting 18 October 2017 Recently - PowerPoint PPT Presentation

Tullamarine Landfill Community Meeting 18 October 2017 Recently Completed Activities Groundwater sampling at new wells completed, letter report currently being prepared Snap shot of In Situ parameters on all groundwater boreholes


  1. Tullamarine Landfill Community Meeting 18 October 2017

  2. Recently Completed Activities � Groundwater sampling at new wells completed, letter report currently being prepared � Snap shot of In Situ parameters on all groundwater boreholes completed, report currently being prepared � Groundwater sampling, all boreholes, completed � Review of Bore Network Depths, data sent to Auditor � Stormwater connection design concept completed, consultation commencing

  3. Tullamarine Planned Activities � Ambient Air Testing [Underway] � Install Landfill Gas Extraction Wells on Mound 3 [Design Phase] � Next groundwater technical review [Late 2018 / Early 2019], Technical Review for Auditor Review [TRAR] Grey = task underway; Blue = task commencing

  4. Email Question 1 Q1. In July 2015, at the invitation of Kieren, Julie Law and I attended the obtaining of water samples from bores on the Buffer land. To date the report arising from that testing has not, I believe, been presented to the community. When can the community expect to receive that report? Over two years is an inordinately long time. A1. The groundwater results are assessed holistically every 3 years. The next assessment report will be completed in 2018 for all sampling completed in the period late 2014 to December 2017.

  5. Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump. When can the community expect the preliminary results from that testing? It is nearly 12 months. Ample time to have results. A2. The results have been incorporated into a letter report. The report is currently being reviewed and will be made available in the next four weeks.

  6. Tullamarine Stormwater Connection

  7. Protecting Moonee Ponds Ck and Growling Grass Frog

  8. Original Concept Concrete Pipe [0.75 m to 1.0 m diameter] Concrete Pipe [0.75 m to 1.0 m diameter] Concrete Pits/Formwork

  9. New Concept Hard Edge Wetlands Pipes Smaller or Replaced with Open Channel / Swale / Rock Pipe and Open Channel Swale No change to Creek Soft Edge connection. Wetlands

  10. Defined Wetland

  11. Pipe and Grass Swale

  12. Wetland Example Constructed Wetlands Handbook, Melbourne Water, July 2017

  13. Stormwater Management & Grass Existing Stormwater System Establishment

  14. North Wall Landscaping Designed by Western Plains Flora May 2013 May 2012

  15. Mound 1 Leachate Well Gas Collection Manifold Drainage Swale

  16. Kangaroos on Mound 3

  17. Echidnas near the Flare

  18. Benefits � Improved water quality � Increased habitat � Increased biodiversity � Softer design � Opportunity to work with Melb Water / Friends Groups / Council � Savings?

  19. Thank you for your time.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend