Tullamarine Landfill Community Meeting 18 October 2017 Recently - - PowerPoint PPT Presentation

tullamarine landfill community meeting
SMART_READER_LITE
LIVE PREVIEW

Tullamarine Landfill Community Meeting 18 October 2017 Recently - - PowerPoint PPT Presentation

Tullamarine Landfill Community Meeting 18 October 2017 Recently Completed Activities Groundwater sampling at new wells completed, letter report currently being prepared Snap shot of In Situ parameters on all groundwater boreholes


slide-1
SLIDE 1

Tullamarine Landfill Community Meeting

18 October 2017

slide-2
SLIDE 2

Recently Completed Activities

Groundwater sampling at new wells completed,

letter report currently being prepared

Snap shot of In Situ parameters on all groundwater

boreholes completed, report currently being prepared

Groundwater sampling, all boreholes, completed Review of Bore Network Depths, data sent to Auditor Stormwater connection design concept completed,

consultation commencing

slide-3
SLIDE 3

Tullamarine Planned Activities

Ambient Air Testing [Underway] Install Landfill Gas Extraction Wells on Mound 3

[Design Phase]

Next groundwater technical review [Late 2018 / Early

2019], Technical Review for Auditor Review [TRAR] Grey = task underway; Blue = task commencing

slide-4
SLIDE 4

Email Question 1

  • Q1. In July 2015, at the invitation of Kieren, Julie Law

and I attended the obtaining of water samples from bores on the Buffer land. To date the report arising from that testing has not, I believe, been presented to the community. When can the community expect to receive that report? Over two years is an inordinately long time.

  • A1. The groundwater results are assessed holistically

every 3 years. The next assessment report will be completed in 2018 for all sampling completed in the period late 2014 to December 2017.

slide-5
SLIDE 5

Email Question 2

  • Q2. In November 2016 a number of bores were

installed in the housing area east of the dump. When can the community expect the preliminary results from that testing? It is nearly 12 months. Ample time to have results.

  • A2. The results have been incorporated into a letter
  • report. The report is currently being reviewed and will

be made available in the next four weeks.

slide-6
SLIDE 6

Tullamarine Stormwater Connection

slide-7
SLIDE 7

Protecting Moonee Ponds Ck and Growling Grass Frog

slide-8
SLIDE 8

Original Concept

Concrete Pipe [0.75 m to 1.0 m diameter] Concrete Pipe [0.75 m to 1.0 m diameter] Concrete Pits/Formwork

slide-9
SLIDE 9

New Concept

Hard Edge Wetlands Soft Edge Wetlands Pipe and Open Channel Swale

Pipes Smaller or Replaced with Open Channel / Swale / Rock No change to Creek connection.

slide-10
SLIDE 10

Defined Wetland

slide-11
SLIDE 11

Pipe and Grass Swale

slide-12
SLIDE 12

Wetland Example

Constructed Wetlands Handbook, Melbourne Water, July 2017

slide-13
SLIDE 13

Stormwater Management & Grass Establishment

Existing Stormwater System

slide-14
SLIDE 14

North Wall Landscaping

May 2012 May 2013 Designed by Western Plains Flora

slide-15
SLIDE 15

Mound 1

Gas Collection Manifold Leachate Well Drainage Swale

slide-16
SLIDE 16

Kangaroos on Mound 3

slide-17
SLIDE 17

Echidnas near the Flare

slide-18
SLIDE 18

Benefits

Improved water quality Increased habitat Increased biodiversity Softer design Opportunity to work with Melb Water / Friends

Groups / Council

Savings?

slide-19
SLIDE 19

Thank you for your time.