TSOs com pliance w ith transparency requirem ents from Regulation ( EC) No. 7 1 5 / 2 0 0 9 Focus on North-W est region Juan de Miguel ACER 1 0 th Stakeholder Group m eeting of GRI NW 2 3 Novem ber 2 0 1 2 Monitoring of transparency com


slide-1
SLIDE 1

TSOs com pliance w ith transparency requirem ents from Regulation ( EC)

  • No. 7 1 5 / 2 0 0 9

Focus on North-W est region

Juan de Miguel ACER

1 0 th Stakeholder Group m eeting of GRI NW

2 3 Novem ber 2 0 1 2

slide-2
SLIDE 2

10th SG meeting of GRI NW – 23 November 2012

  • Background
  • Scope of ACER analysis
  • Overview of results in NW countries
  • Detailed results per requirement
  • Detailed results per country and TSO
  • Main findings in the NW region
  • Issues identified and examples of good practice
  • Stakeholders’ feedback
  • Main conclusions
  • Way forward

Outline

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

slide-3
SLIDE 3

10th SG meeting of GRI NW – 23 November 2012

Background

  • Transparency is a vital element for well-functioning gas markets and a relevant

pre-requisite for a level playing field for all network users and market actors

  • In particular, a high level of transparency in system and market information is

desirable in order to achieve the following goals:

  • Increase competition and remove barriers for new entrants
  • Ensure effective access to gas transmission systems
  • Provide a minimum level of information for network users and market participants that

allows them to perform their activities

  • Enable market monitoring and support decision-making by national regulators and

supervisory authorities

  • Allow for lower costs for market participants
  • Provide network users with the information they need in relation to specific system

procedures (nomination, capacity booking, contracting services, balancing, etc.)

  • In the 20th Madrid Forum, ACER announced its intention of m onitoring the

im plem entation of transparency rules pursuant to Chapter 3, Annex I of Regulation 715/ 2009

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

slide-4
SLIDE 4

10th SG meeting of GRI NW – 23 November 2012

Scope of ACER analysis

  • The inquiry refers to the transparency obligations as established in EC

Decision of 1 0 Novem ber 2 0 1 0 , applicable since 3 March 2 0 1 1 :

  • Content of publication: system and services, capacity information, gas flows, etc.
  • Scope of information published: information for certain relevant points
  • Form at of publication: accessibility, frequency, user-friendliness
  • ACER presented preliminary results (based on TSOs’ self-assessment) in the

XXI Madrid Forum in March 2012 and the final results in the XXI I Madrid Forum in October 2012

  • The results presented today focus on the North-W est region and include a

recent update of compliance by German TSOs

  • The Gas Regional I nitiative has been a good instrument to help carrying out

this analysis. NRAs, TSOs and other stakeholders have contributed decisively to it

  • ACER full analysis covers 4 1 TSOs from 2 2 EU Mem ber States
  • This presentation covers 2 1 TSOs from 9 countries from the NW region

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

slide-5
SLIDE 5

10th SG meeting of GRI NW – 23 November 2012

NW region – Results per requirem ent ( 1 )

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

Notes:

  • Answers where “no” does not imply non-compliance are not considered (e.g. information published by third party)
  • Some results are still under revision with the concerned TSOs and NRAs (recent update for German TSOs)

3 6 9 12 15 18 21 (a) Website publicly accessible, free

  • f charge and

without registration (b) On a regular/rolling basis (c) In a user- friendly manner (d) Clear, quantifiable, easily accessible and non- discriminatory (e) In downloadable format allowing for quantitative analyses (f) In consistent units, in particular kWh for energy and m3 for volume (g) In the national language (g) In English Info on actual changes to information in a timely manner

Number of compliant TSOs

Section 3.1.1 - Form of publication

Yes Partially No Not applicable, forthcoming or exemption pending No data

slide-6
SLIDE 6

10th SG meeting of GRI NW – 23 November 2012

NW region – Results per requirem ent ( 2 )

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

3 6 9 12 15 18 21

a) Description of services a) Charges b) Types of transportation contracts c) Network code and/or standard conditions

  • 1. Harmonised transportation contracts
  • 2. Gas quality parameters (gross calorific value and Wobbe index)
  • 3. Pressure requirements
  • 4. Procedure for interruption of interruptible capacity

d) Harmonised procedures in the transmission system e).1. Capacity allocation e).2. Congestion management e).3. Anti-hoarding e).4. Reutilisation procedures f) Rules of secondary market g) Rules on balancing and calculation of imbalance charges h) Flexibility and tolerance levels included h) any flexibility additionally offered and charges i) Detailed description of gas system and relevant IPs i) Names of operators of interconnected systems j) Rules for connection to the system k) Information on emergency mechanisms l) Procedures agreed by TSOs at IPs l) Agreed procedures on nomination and matching l) Other agreed procedures (gas flow allocation and balancing) m) Description of methodology and process for capacity calculation Number of compliantTSOs

Section 3.1.2 - Content of publication

Yes Partially No Not applicable, forthcoming or exemption pending No data

slide-7
SLIDE 7

10th SG meeting of GRI NW – 23 November 2012

NW region – Results per requirem ent ( 3 )

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

3 6 9 12 15 18 21 (a) Technical capacity Is it published on a numerical basis? Is it in hourly or daily periods (smallest reference period)? Is it published and updated as soon as available to TSO (“near real time”)? Is it published for at least 18 months ahead? Do you publish historical information for the past five years? Aggregated information for single final customers and production facilities (b) Total contracted firm and interruptible capacity Is it published on a numerical basis? Is it in hourly or daily periods (smallest reference period)? Is it published and updated as soon as available to TSO (“near real time”)? Is it published for at least 18 months ahead? Do you publish historical information for the past five years? (c) Nominations and re-nominations Is it published on a numerical basis? Is it in hourly or daily periods (smallest reference period)? Is it published and updated as soon as available to TSO (“near real time”)? Do you publish historical information for the past five years? (d) Available firm and interruptible capacity Is it published on a numerical basis? Is it in hourly or daily periods (smallest reference period)? Is it published and updated as soon as available to TSO (“near real time”)? Is it published for at least 18 months ahead? Do you publish historical information for the past five years? (e) Actual physical flows Is it published on a numerical basis? Is it in hourly or daily periods (smallest reference period)? Is it published and updated as soon as available to TSO (“near real time”)? Do you publish historical information for the past five years? (f) Planned and actual interruption of interruptible capacity Is it published on a numerical basis? Is it in hourly or daily periods (smallest reference period)? Is it published and updated as soon as available to TSO (“near real time”)? Do you publish historical information for the past five years? (g) Planned and unplanned interruptions to firm services Are planned interruptions published at least 42 days in advance? Is it published as soon as available to you (“near real time”)? Do you publish historical information for the past five years?

Number of compliantTSOs

Section 3.3 - Information at all relevant points

Yes Partially No Not applicable, forthcoming or exemption pending No data
slide-8
SLIDE 8

10th SG meeting of GRI NW – 23 November 2012

NW region – Results per requirem ent ( 4 )

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

3 6 9 12 15 18 21 Secondary market: (a) interconnection point where capacity is sold Secondary market: (b) Type of capacity (entry, exit, firm, interruptible) Secondary market: (c) Quantity and duration of capacity rights Secondary market: (d) Type of sale (transfer or assignment) Secondary market: (e) Total number of trades/transfers Secondary market: (f) Any other conditions known to the TSO Secondary market: (a) Description of standardised products
  • Sec. market: (b) Lead time for implementation, acceptation and registration of secondary trades
  • Sec. market: (c) Notification to the TSO of name of seller and buyer and capacity specifications
Specific preliminary imbalance volumes and cost data per individual network user Final data of customers supplied according to standardised load profiles within 14 months Is confidentiality of commercially sensitive information respected? Are flexibility services offered, other than tolerances? If so, are daily forecasts published of maximum flexibility, booked flexibility and available flexibility? Ex-post information on the aggregate use of each flexibility service at the end of the day Amount of gas in the system at the start of each gas day Forecast of amount of gas in the system at the end of each gas day Amount of gas in the system on an hourly basis Hourly updates of forecast amount of gas for the end of the gas day Alternatively, aggregate imbalance position of users at the start of each balancing period Forecast of the aggregated imbalance position of all users at the end of gas day User-friendly instruments for calculating tariffs

Number of compliant TSOs

Section 3.4 - Information regarding the transmission system

Yes Partially No Not applicable, forthcoming or exemption pending No data
slide-9
SLIDE 9

10th SG meeting of GRI NW – 23 November 2012

NW region – Results per requirem ent ( and 5 )

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

3 6 9 12 15 18 21 Amount of gas in the system at the start of each gas day Forecast of amount of gas in the system at the end of each gas day Amount of gas in the system on an hourly basis Hourly updates of forecast amount of gas for the end of the gas day Alternatively, aggregate imbalance position of users at the start of each balancing period Forecast of the aggregated imbalance position of all users at the end of gas day User-friendly instruments for calculating tariffs

Number of compliant TSOs

Section 3.4 - Information on the transmission system 3.4.5. & 3.4.6. Information per balancing zone and tariff calculation tool

Yes Partially No Not applicable, forthcoming or exemption pending No data

slide-10
SLIDE 10

10th SG meeting of GRI NW – 23 November 2012

NW region – Results per country and TSO

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

Notes:

  • Answers where “no” does not imply non-compliance are not considered (e.g. information published by third party)
  • Some results are still under revision with the concerned TSOs and NRAs (recent update for German TSOs)

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Fluxys Energinet.DK GRTgaz Bayernets Gastransport Nord Gasunie Deutschland GRTgaz Deutschland Jordgas Nowega ONTRAS OGE Terranets BW Thyssengas National Grid Interconnector (UK) limited Gaslink BBL (Interconnector) GTS BGE (UK) Mutual Energy Swedagas & Svenska Kraftnät… AVERAGE

% of requirements met

Transparency monitoring (Annex I.3 of Reg. 715/2009) North-West region

Yes N/A, forthcoming or exemption request pending No No data

slide-11
SLIDE 11

10th SG meeting of GRI NW – 23 November 2012

NW region – Main findings

  • High degree of com pliance, in general, with Annex 1.3 of Regulation

(EC) No 715/ 2009, in particular in the case of information on:

 Description of transmission system and services  Network code – contracts, pressure requirements, interruption procedure  Provisions on CAM, CMP anti-hoarding and reutilisation  Nomination and matching procedures  Balancing rules and imbalance charges  Rules for connection to TSOs’ facilities  General information on technical/ booked-available/ firm-interruptible capacity  User-friendly instruments for calculating tariffs  Form of publication (easy access, user-friendliness, frequency of data, etc.)

  • On average, about 8 6 % of requirements met
  • Good example of compliance and user-friendliness: National Grid, Gasunie
  • Nine TSOs above 90% , 17 above 80% . None below 50%

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

slide-12
SLIDE 12

10th SG meeting of GRI NW – 23 November 2012

  • Certain lack of com pliance in information about:
  • Actual physical flows, planned and actual interruptions
  • Flexibility and tolerance levels
  • Emergency mechanisms
  • Methodology, process and parameters for capacity calculation
  • Information about the secondary market (N/ A in many cases)
  • Information in English in some cases
  • And only som e TSOs publish:

x Aggregate information on capacities for end customers and production facilities x Historical information on capacities, nominations, interruptions, physical flows x Amount of gas at the beginning of the day and forecast for the end of the day x Imbalance position of users at the start and end of the day

  • The results for some TSOs are still under review by ACER together with the

concerned TSOs and NRAs

NW region – Main findings

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

slide-13
SLIDE 13

10th SG meeting of GRI NW – 23 November 2012

Some issues identified when assessing compliance:

  • Links with restricted access (user/ password) or too generic
  • Compliance with some requirements is difficult to be checked (information

published close to real time or as soon as becomes available to the TSO)

  • Some requirements are considered as not applicable, as the information is not

relevant or yet available (e.g. information on secondary market, daily capacity data when only monthly allocation is offered, etc.)

  • Websites not available in English

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

Some examples of good practice:

  • Publish information with the same structure than the set of requirements in Annex

1 of Regulation 715/ 2009 in a section called “Transparency” in the TSO website

  • When information is published by a third party (another TSO, market area

manager) a direct link is provided in the TSO website

I ssues identified and exam ples of good practice

slide-14
SLIDE 14

10th SG meeting of GRI NW – 23 November 2012

NW region – Stakeholders feedback ( 1 )

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

  • Public consultation of TSOs’ answers run over November 2011 – January 2012
  • 11 responses were received from stakeholders
  • A public w orkshop was organised by ACER in Ljubljana on 13 September

General com m ents »

Remarkable efforts have been made by TSOs. There has been significant progress

»

However, there is room for improvement. Stakeholders don’t share the overall “green picture”

»

Compliance is not just a “tick-list” exercise, issues are beyond the quantitative analysis

»

TSOs await for specific guidance from NRAs to implement the requirements

Quality, consistency, frequency and availability of the inform ation » Despite overall compliance, large variety in the quality of information » Multiplicity of sources and websites make it hard to find and process information » Quality standards and a single transparency platform supported by many stakeholders

slide-15
SLIDE 15

10th SG meeting of GRI NW – 23 November 2012

NW region – Stakeholders feedback ( and 2 )

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region Accuracy of TSOs’ responses »

The questionnaires broadly reflect the information available, but not always its quality

»

Implicit degree of subjectivity and interpretation concerning some requirements

»

Compliance with some requirements is directly related to market design

User-friendliness of inform ation and free access »

The degree of user-friendliness of the websites and platforms differs

»

Standardisation of formats would improve ease of access

»

Information is free of charge, but registration is necessary in some cases

Availability close to real tim e »

Requirement difficult to assess, but in view of many users only a few TSOs publish data close to real time

»

Information on actual gas flows seems to be a major issue

»

Insufficient frequency of data publication in some TSO websites compared to others

slide-16
SLIDE 16

10th SG meeting of GRI NW – 23 November 2012

Main conclusions

  • In general, there is a good level of com pliance by TSOs against

the transparency requirements in Section 3, Annex 1 of Regulation 715/ 2009

  • In particular, the situation is satisfactory regarding information

about the system, services provided, system procedures and general data of technical and available/ booked capacities

  • However, there is a certain lack of com pliance in a number of

areas, such as information near real time, flexibility and tolerances, planned and actual interruptions, amounts of gas at start and end

  • f the gas day
  • Different perception by NRA and stakeholders in some instances
  • There are rem aining issues especially as regards information

near real tim e or as soon as available to the TSO (e.g. gas flows) and quality of information in some cases Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

slide-17
SLIDE 17

10th SG meeting of GRI NW – 23 November 2012

W ay forw ard

Work on these upcoming requirements has started already or will soon do it

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

  • Analysis of compliance with Regulation (EC) No 715/ 2009 (amended by EC Decision
  • f 10 November 2010) has revealed rem aining issues that need to be tackled
  • NRAs should take action to enforce com pliance, by analysing these issues

together with TSOs

  • Conclusion 5 from XXII Madrid Forum: NRAs and EC to assess where follow-up legal

action is necessary to achieve full compliance

  • The recent Com m ission Decision of 2 4 August 2 0 1 2 has added new

amendments to Annex I of Regulation 715/ 2009, introducing new guidelines on CMP as well as some further transparency obligations:

  • Dow nloadable form at agreed by TSOs and NRAs on the basis of an opinion by ACER on a

harmonised format that allows for quantitative analyses

  • All data to be available as of 1 October 2013 on a EU-w ide central platform , established

by ENTSOG on a cost-efficient basis

  • Further transparency obligations related to the new CMP guidelines (as of 1 October 2013)
slide-18
SLIDE 18

10th SG meeting of GRI NW – 23 November 2012

For any feedback or further com m ent:

TransparencyGas@acer.europa.eu

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

slide-19
SLIDE 19

10th SG meeting of GRI NW – 23 November 2012

Disclaim er

. The views expressed in this presentation are the views of the

speaker and do not necessarily reflect the views of the Agency for the Cooperation of Energy Regulators, or of any of its Boards.

. The Agency for the Cooperation of Energy Regulators does not

guarantee the accuracy of all data and information included in this presentation and accepts no responsibility for any consequence of their use.

Monitoring of transparency com pliance

Regulation ( EC) No. 7 1 5 / 2 0 0 9 - Focus on NW region

slide-20
SLIDE 20

Thank you for your attention

Thank you for your attention!

w w w .acer.europa.eu

slide-21
SLIDE 21

10th SG meeting of GRI NW – 23 November 2012

Annex Detailed results from the analysis

Colour tables in the NW region

Code key:

Transparency m onitoring

Com pliance w ith Chapter 3 , Annex I of Reg. 7 1 5 / 2 0 0 9

Yes Yes P Partially No No NA Not applicable, forthcoming or exemption request pending B No data

slide-22
SLIDE 22

10th SG meeting of GRI NW – 23 November 2012

Detailed results – NW region

Transparency m onitoring

Com pliance w ith Chapter 3 , Annex I of Reg. 7 1 5 / 2 0 0 9

Countr y Code BE DK FR GB I E NL SE GB/ NL GB/ B Do you publish the inform ation referred to under paragraph 3.1.2. in the following m anner: (a) on a website accessible to the public, free of charge and without any need to register or otherwise sign on with the transm ission system operator; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes (b) on a regular/ rolling basis; the frequency shall be according to the changes that take place and the duration of the service; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes (c) in a user-friendly m anner; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes (d) in a clear, quantifiable, easily accessible way and on a non- discrim inatory basis; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes (e) in downloadable form at that allows for quantitative analyses; Yes Yes Yes Yes Yes Yes No No Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes (f) in consistent units, in particular kWh (with a com bustion reference tem perature of 298,15 K) shall be the unit for energy content and m 3 (at 273,15 K and 1,01325 bar) shall be the unit for volum e. The constant conversion factor to energy content shall be provided. I n addition to the form at above, publication in other units is also possible; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes (g) in the official languages of the m em ber State and Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes No Yes (g) in English Yes Yes Yes Yes Yes Yes No No Yes Yes No Yes Yes Yes Yes Yes Yes Yes No Yes Yes 3.1.1.2. Do you provide details on actual changes to all inform ation referred to under paragraph 3.1.2 in a tim ely m anner as soon as available to you? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes AV their charges? Yes Yes Yes Yes Yes Yes B Yes Yes Yes Yes Yes Yes Yes B Yes Yes Yes B Yes Yes Yes Yes DE NI Ar ticle of Anne x 1 cha pte r 3 of Ga s Re gula tion 7 1 5 / 2 0 0 9 Tr a nspa r e ncy r e quir e m e nt Yes Yes Yes Yes Yes Yes Yes Yes BBL Com pany I nterconnector UK 3 .1 .1 . For m of publica tion: 3.1.1.1. 3 .1 .2 Conte nt of publica tion 3.1.2 a) Do you publish a detailed and com prehensive description of the different services offered and Sw edagas & Svenska Kraftnat Gaslink BGE ( UK) Mutual Energy GTS GRTgaz National Grid ONTRAS GRTgaz Deutschland OGE Terranets BW Thyssengas Jordgas Now ega Fluxys Energinet.DK Yes 3.1.2 b) Do you publish the different types of transportation contracts available for these services? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Gastransport Nord Gasunie Deutschland Bayernets
slide-23
SLIDE 23

10th SG meeting of GRI NW – 23 November 2012

Detailed results – NW region

Transparency m onitoring

Com pliance w ith Chapter 3 , Annex I of Reg. 7 1 5 / 2 0 0 9

Countr y Code BE DK FR GB I E NL SE GB/ NL GB/ B
  • 1. Harm onised transportation contracts and other relevant
docum ents; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No No
  • 3. if relevant for access to the system , for all relevant points
inform ation on pressure requirem ents; Yes NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes Yes Yes Yes Yes NA No Yes Do you publish provisions on
  • 1. capacity allocation,
Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
  • 2. congestion m anagem ent,
Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes
  • 3. anti-hoarding, and
Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes Yes
  • 4. reutilisation procedures?
Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes Yes 3.1.2.f) Do you publish the rules applicable for capacity trade on the secondary m arket vis-à-vis the transm ission system operator? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes Yes Yes NA Yes Yes 3.1.2.g) Do you publish rules on balancing and m ethodology for the calculation
  • f im balance charges?
Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes Yes Yes Yes Yes DE NI Ar ticle of Anne x 1 cha pte r 3 of Ga s Re gula tion 7 1 5 / 2 0 0 9 Tr a nspa r e ncy r e quir e m e nt Yes Yes Yes Yes Yes Yes Yes BBL Com pany I nterconnector UK 3 .1 .2 Conte nt of publica tion Sw edagas & Svenska Kraftnat Gaslink BGE ( UK) Mutual Energy GTS GRTgaz National Grid ONTRAS GRTgaz Deutschland OGE Terranets BW Thyssengas Jordgas Now ega Fluxys Energinet.DK 3.1.2.c) Do you publish the network code and/ or the standard conditions
  • utlining the rights and responsibilities of all network users including:
Yes Yes Yes Yes Yes Yes Yes
  • 2. if relevant for access to the system , for all relevant points as
defined in paragraph 3.2 of this Annex, a specification of relevant gas quality param eters, including at least the gross calorific value and the Wobbe index, and the liability or costs of conversion for network users in case gas is outside these specifications; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes 3.1.2 d) Do you publish the harm onised procedures applied when using the transm ission system , including the definition of key term s? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
  • 4. the procedure in the event of an interruption of interruptible
capacity, including, where applicable, the tim ing, extent, and ranking
  • f individual interruptions (for exam ple pro-rata or first-com e-last-
interrupted); Yes Yes Yes Yes Yes 3.1.2.e) Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Gastransport Nord Gasunie Deutschland Bayernets
slide-24
SLIDE 24

10th SG meeting of GRI NW – 23 November 2012

Detailed results – NW region

Transparency m onitoring

Com pliance w ith Chapter 3 , Annex I of Reg. 7 1 5 / 2 0 0 9

Countr y Code BE DK FR GB I E NL SE GB/ NL GB/ B I f applicable, do you publish the flexibility and tolerance levels included in transportation and other services without separate charge, as well as Yes Yes Yes Yes Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA NA NA Yes any flexibility offered in addition to this and the corresponding charges Yes Yes Yes Yes Yes Yes B Yes Yes Yes No Yes Yes NA Yes Yes Yes Yes NA NA Yes Do you publish a detailed description of the gas system of the transm ission system
  • perator and its relevant points of interconnection as defined in
paragraph 3.2 of this Annex, as well as Yes Yes Yes Yes Yes Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes the nam es of the operators of the interconnected system s or facilities? Yes Yes Yes Yes Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes 3.1.2.j) Do you publish the rules applicable for connection to the system
  • perated by the transm ission system operator?
Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes 3.1.2.k) Do you publish inform ation on em ergency m echanism s, as far as it is the responsibility of the transm ission system operator, such as m easures that can lead to the disconnection of custom ers groups and
  • ther general liability rules that apply to the transm ission system
  • perator?
Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA NA Do you publish procedures agreed upon by transm ission system operators at interconnection points, of relevance for access of network users to the transm ission system s concerned, relating to interoperability of the network, Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes agreed procedures on nom ination and m atching procedures and Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
  • ther agreed procedures that set out provisions in relation to gas flow
allocations and balancing, including the m ethods used? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes 3.1.2.m ) Do you publish a detailed and com prehensive description of the m ethodology and process, including inform ation on the param eters em ployed and the key assum ptions, used to calculate the technical capacity? Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No No Yes DE NI Ar ticle of Anne x 1 cha pte r 3 of Ga s Re gula tion 7 1 5 / 2 0 0 9 Tr a nspa r e ncy r e quir e m e nt BBL Com pany I nterconnector UK 3 .1 .2 Conte nt of publica tion Sw edagas & Svenska Kraftnat Gaslink BGE ( UK) Mutual Energy GTS GRTgaz National Grid ONTRAS GRTgaz Deutschland OGE Terranets BW Thyssengas Jordgas Now ega Fluxys Energinet.DK 3.1.2.h) 3.1.2.i) 3.1.2.l) Gastransport Nord Gasunie Deutschland Bayernets
slide-25
SLIDE 25

10th SG meeting of GRI NW – 23 November 2012

Detailed results – NW region

Transparency m onitoring

Com pliance w ith Chapter 3 , Annex I of Reg. 7 1 5 / 2 0 0 9

Countr y Code BE DK FR GB I E NL SE GB/ NL GB/ B 3 .3 I nfor m a tion to be publishe d a t a ll r e le v a nt points a nd the tim e sche dule a ccor ding to which this infor m a tion should be publishe d AV Do you publish at all relevant points the following inform ation for all services and ancillary services provided: (a) the technical capacity for flows in both directions; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes I s this inform ation published on a num erical basis? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes I s this inform ation in hourly or daily periods, equal to the sm allest reference period? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes I s this inform ation and updates published as soon as available to you (“near real tim e”)? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes I s this inform ation published for a period of at least 18 m onths ahead? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Do you publish historical inform ation on the technical capacity for flows in both directions for the past five years on a rolling basis? Yes Yes Yes No Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes I s inform ation for single final custom ers and for production facilities, that is excluded from the definition of relevant points as described under 3.2 (1)(a) published in aggregate form at at least per balancing
  • zone. The aggregation of single final custom ers and of production
facilities, excluded from the definition of relevant points as described under 3.2 (1)(a), shall for the application of this annex be considered
  • ne relevant point.
Yes Yes Yes No Yes NA B Yes Yes Yes Yes No Yes Yes Yes Yes NA Yes Yes NA NA (b) the total contracted firm and interruptible capacity in both directions Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes B Yes Yes Yes B Yes Yes I s this inform ation published on a num erical basis? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes I s this inform ation in hourly or daily periods, equal to the sm allest reference period? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes I s this inform ation and updates published as soon as available to you (“near real tim e”)? Yes Yes Yes Yes Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes I s this inform ation published for a period of at least 18 m onths ahead? Yes Yes Yes Yes Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Do you publish historical inform ation on the total contracted firm and interruptible capacity for flows in both directions for the past five years on a rolling basis? Yes Yes Yes No Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes 3.3.1., 3.3.2. and 3.3.3. DE NI Ar ticle of Anne x 1 cha pte r 3 of Ga s Re gula tion 7 1 5 / 2 0 0 9 Tr a nspa r e ncy r e quir e m e nt BBL Com pany I nterconnector UK Sw edagas & Svenska Kraftnat Gaslink BGE ( UK) Mutual Energy GTS GRTgaz National Grid ONTRAS GRTgaz Deutschland OGE Terranets BW Thyssengas Jordgas Now ega Fluxys Energinet.DK Gastransport Nord Gasunie Deutschland Bayernets
slide-26
SLIDE 26

10th SG meeting of GRI NW – 23 November 2012

Detailed results – NW region

Transparency m onitoring

Com pliance w ith Chapter 3 , Annex I of Reg. 7 1 5 / 2 0 0 9

Countr y Code BE DK FR GB I E NL SE GB/ NL GB/ B 3 .3 I nfor m a tion to be publishe d a t a ll r e le v a nt points a nd the tim e sche dule a ccor ding to which this infor m a tion should be publishe d AV (c) the nom inations and re-nom inations in both directions; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes I s this inform ation published on a num erical basis? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes I s this inform ation in hourly or daily periods, equal to the sm allest reference period? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes Yes Yes Yes I s this inform ation and updates published as soon as available to you (“near real tim e”)? Yes Yes Yes Yes Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes Yes Yes Yes Do you publish historical inform ation on the nom inations and re- nom inations in both directions for the past five years on a rolling basis? Yes Yes Yes No Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes No Yes (d) the available firm and interruptible capacity in both directions; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes B Yes Yes Yes B Yes Yes I s this inform ation published on a num erical basis? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes I s this inform ation in hourly or daily periods, equal to the sm allest reference period? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes B Yes No I s this inform ation and updates published as soon as available to you (“near real tim e”)? Yes Yes Yes Yes Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes B Yes No I s this inform ation published for a period of at least 18 m onths ahead? Yes Yes Yes Yes Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Do you publish historical inform ation on the available firm and interruptible capacity in both directions for the past five years on a rolling basis? Yes Yes Yes No Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes (e) actual physical flows; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes B Yes Yes Yes Yes Yes Yes I s this inform ation published on a num erical basis? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes NA Yes Yes I s this inform ation in hourly or daily periods, equal to the sm allest reference period? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes I s this inform ation and updates published as soon as available to you (“near real tim e”)? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Do you publish historical inform ation on actual physical flows for the past five years on a rolling basis? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes 3.3.1., 3.3.2. and 3.3.3. DE NI Ar ticle of Anne x 1 cha pte r 3 of Ga s Re gula tion 7 1 5 / 2 0 0 9 Tr a nspa r e ncy r e quir e m e nt BBL Com pany I nterconnector UK Sw edagas & Svenska Kraftnat Gaslink BGE ( UK) Mutual Energy GTS GRTgaz National Grid ONTRAS GRTgaz Deutschland OGE Terranets BW Thyssengas Jordgas Now ega Fluxys Energinet.DK Gastransport Nord Gasunie Deutschland Bayernets
slide-27
SLIDE 27

10th SG meeting of GRI NW – 23 November 2012

Detailed results – NW region

Transparency m onitoring

Com pliance w ith Chapter 3 , Annex I of Reg. 7 1 5 / 2 0 0 9

Countr y Code BE DK FR GB I E NL SE GB/ NL GB/ B 3 .3 I nfor m a tion to be publishe d a t a ll r e le v a nt points a nd the tim e sche dule a ccor ding to which this infor m a tion should be publishe d AV (f) planned and actual interruption of interruptible capacity; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes B Yes B Yes B Yes Yes I s this inform ation published on a num erical basis? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes NA Yes Yes I s this inform ation in hourly or daily periods, equal to the sm allest reference period? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes NA Yes Yes I s this inform ation and updates published as soon as available to you (“near real tim e”)? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes NA Yes Yes Do you publish historical inform ation on planned and actual interruptions of interruptible capacity for the past five years on a rolling basis? Yes Yes Yes No Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA NA NA Yes NA Yes Yes (g) planned and unplanned interruptions to firm services as well as the inform ation on restoration of the firm services (in particular, m aintenance of the system and the likely duration of any interruption due to m aintenance). Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes B NA NA Yes Yes Yes Yes Do you publish planned interruptions at least 42 days in advance? Yes Yes Yes No Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA NA NA Yes Yes Yes Yes I s this inform ation and updates published as soon as available to you (“near real tim e”)? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA NA NA Yes Yes Yes Yes Do you publish historical inform ation on planned and unplanned interruptions for the past five years on a rolling basis? Yes Yes Yes No Yes Yes NA Yes Yes Yes Yes Yes Yes Yes NA NA NA P No No Yes Do you publish m easured values of the gross calorific value or the Wobbe index at all relevant points, on a daily basis? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes NA Yes Yes Do you publish prelim inary figures at the latest 3 days following the respective gas day? Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes Yes Yes Yes Yes No Yes No Yes Yes Do you publish final figures within 3 m onths after the end of the respective m onth? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes 3.3.1., 3.3.2. and 3.3.3. DE NI Ar ticle of Anne x 1 cha pte r 3 of Ga s Re gula tion 7 1 5 / 2 0 0 9 Tr a nspa r e ncy r e quir e m e nt BBL Com pany I nterconnector UK Sw edagas & Svenska Kraftnat Gaslink BGE ( UK) Mutual Energy GTS GRTgaz National Grid ONTRAS GRTgaz Deutschland OGE Terranets BW Thyssengas Jordgas Now ega Fluxys Energinet.DK Gastransport Nord Gasunie Deutschland 3.3.4. Bayernets
slide-28
SLIDE 28

10th SG meeting of GRI NW – 23 November 2012

Detailed results – NW region

Transparency m onitoring

Com pliance w ith Chapter 3 , Annex I of Reg. 7 1 5 / 2 0 0 9

Countr y Code BE DK FR GB I E NL SE GB/ NL GB/ B 3 .3 I nfor m a tion to be publishe d a t a ll r e le v a nt points a nd the tim e sche dule a ccor ding to which this infor m a tion should be publishe d AV Do you publish for all relevant points, available capacities, booked and technical capacities, on an annual basis Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
  • ver all years where capacity is contracted plus 1 year, and
Yes Yes Yes Yes Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes B Yes Yes at least for the next 10 years. Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes B Yes Yes I s this inform ation updated at least every m onth or m ore frequently, if new inform ation becom es available? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes Does the publication reflect the period for which capacity is offered to the m arket? Yes Yes Yes Yes Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Do you publish the inform ation referred to under paragraph 3.3(1) to 3.3(5) in the following m anner: AVERAGE 3 .3 (a) on a website accessible to the public, free of charge and without any need to register or otherwise sign on with the transm ission system operator; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes (b) on a regular/ rolling basis; the frequency shall be according to the changes that take place and the duration of the service; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes (c) in a user-friendly m anner; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes (d) in a clear, quantifiable, easily accessible way and on a non- discrim inatory basis; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes (e) in downloadable form at that allows for quantitative analyses; Yes Yes Yes Yes Yes Yes No No Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes No Yes (f) in consistent units, in particular kWh (with a com bustion reference tem perature of 298,15 K) shall be the unit for energy content and m 3 (at 273,15 K and 1,01325 bar) shall be the unit for volum e. The constant conversion factor to energy content shall be provided. I n addition to the form at above, publication in other units is also possible; Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes (g) in the official languages of the m em ber State and Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes No Yes (g) in English Yes Yes Yes No Yes Yes No No Yes Yes No Yes Yes Yes Yes Yes Yes Yes No Yes Yes 3.1.1.2. Do you provide details on actual changes to all inform ation referred to under paragraph 3.3(1) to 3.3(5) in a tim ely m anner as soon as available to you? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes DE NI Ar ticle of Anne x 1 cha pte r 3 of Ga s Re gula tion 7 1 5 / 2 0 0 9 Tr a nspa r e ncy r e quir e m e nt BBL Com pany I nterconnector UK Sw edagas & Svenska Kraftnat Gaslink BGE ( UK) Mutual Energy GTS GRTgaz National Grid ONTRAS GRTgaz Deutschland OGE Terranets BW Thyssengas Jordgas Now ega Fluxys Energinet.DK Gastransport Nord Gasunie Deutschland 3.3.5. 3.1.1.1. Bayernets
slide-29
SLIDE 29

10th SG meeting of GRI NW – 23 November 2012

Detailed results – NW region

Transparency m onitoring

Com pliance w ith Chapter 3 , Annex I of Reg. 7 1 5 / 2 0 0 9

Countr y Code BE DK FR GB I E NL SE GB/ NL GB/ B 3 .4 I nfor m a tion to be publishe d r e ga r ding the tr a nsm ission sy ste m a nd the tim e sche dule a ccor ding to which this infor m a tion should be publishe d Do you publish on a daily basis and updated every day the following specifications re. the aggregated am ounts of capacities offered, and contracted on the secondary m arket (i.e. sold from one network user to another network user), where the inform ation is available to you: (a) interconnection point where the capacity is sold; Yes No NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes NA NA Yes (b) type of capacity, i.e. entry, exit, firm , interruptible; Yes No NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes NA NA Yes (c) quantity and duration of the capacity usage rights; Yes No NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes NA NA Yes (d) type of sale, e.g. transfer or assignm ent; Yes No NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes NA NA Yes (e) the total num ber of trades/ transfers; Yes No NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes NA NA Yes (f) any other conditions known to the transm ission system operator as m entioned in 3.3. NA No NA Yes Yes Yes Yes Yes Yes Yes Yes Yes NA NA Yes Yes NA NA NA NA Yes I s this inform ation provided by a third party? Do you publish the following specifications re. harm onised conditions under which capacity transactions (e.g. transfers and assignm ents) will be accepted: (a) a description of standardised products which can be sold on the secondary m arket; Yes Yes NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes NA Yes Yes (b) lead tim e for the im plem entation/ acceptation/ registration of secondary trades. I n case of delays the reasons have to be published; Yes Yes NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes NA Yes Yes (c) the notification to the transm ission system operator by the seller
  • r the third party as referred to under 3.4(1) about nam e of seller
and buyer and capacity specifications as outlined in 3.4(1). Yes Yes NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes NA NA Yes I s this inform ation provided by a third party? DE NI Ar ticle of Anne x 1 cha pte r 3 of Ga s Re gula tion 7 1 5 / 2 0 0 9 Tr a nspa r e ncy r e quir e m e nt BBL Com pany I nterconnector UK Sw edagas & Svenska Kraftnat Gaslink BGE ( UK) Mutual Energy GTS GRTgaz National Grid ONTRAS GRTgaz Deutschland OGE Terranets BW Thyssengas Jordgas Now ega Fluxys Energinet.DK Gastransport Nord Gasunie Deutschland 3.4.1. 3.4.2. Bayernets
slide-30
SLIDE 30

10th SG meeting of GRI NW – 23 November 2012

Detailed results – NW region

Transparency m onitoring

Com pliance w ith Chapter 3 , Annex I of Reg. 7 1 5 / 2 0 0 9

Countr y Code BE DK FR GB I E NL SE GB/ NL GB/ B 3 .4 I nfor m a tion to be publishe d r e ga r ding the tr a nsm ission sy ste m a nd the tim e sche dule a ccor ding to which this infor m a tion should be publishe d Regarding the balancing service of your system , do you provide to each network user, for each balancing period, its specific prelim inary im balance volum es and cost data per individual network user, at the latest 1 m onth after the end of the balancing period? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Do you provide final data of custom ers supplied according to standardised load profiles within 14 m onths later? Yes Yes NA NA Yes NA B Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA Yes NA NA Do you respect confidentiality of com m ercially sensitive inform ation while providing this inform ation? Yes Yes NA Yes Yes Yes B Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes NA NA I s this inform ation provided by a third party? Do you offer flexibility services, other than tolerances, for third party access? Yes Yes Yes No Yes Yes Yes Yes NA Yes No Yes Yes NA Yes Yes Yes Yes No No NA I f you do, do you publish daily forecasts on a day-ahead basis of the m axim um am ount of flexibility, the booked level of flexibility and the availability of flexibility for the m arket for the next gas day? Yes NA Yes No Yes Yes B Yes NA Yes No Yes NA NA Yes Yes No NA Yes NA NA Do you also publish ex-post inform ation on the aggregate utilisation
  • f every flexibility service at the end of each gas day?
Yes NA Yes No Yes Yes B Yes Yes Yes No Yes NA NA Yes Yes No NA No NA NA (5) Do you publish, per balancing zone: the am ount of gas in the transm ission system at the start of each gas day and NA NA NA No NA No NA NA NA NA NA NA Yes Yes NA No No NA No NA Yes the forecast of the am ount of gas in the transm ission system at the end of each gas day? NA NA NA No NA No NA NA NA NA NA NA Yes Yes NA No No NA No NA Yes Do you publish the am ount of gas in the transm ission system on an hourly basis? NA NA NA No NA No NA NA NA NA NA NA Yes NA NA No No NA No NA No Do you update the forecast am ount of gas for the end of the gas day
  • n an hourly basis throughout the gas day?
NA NA NA No NA No NA NA NA NA NA NA Yes Yes NA No No NA No NA Yes Alternatively, do you publish, per balancing zone the aggregate im balance position of all users at the start of each balancing period and Yes NA NA No NA No NA NA NA NA NA NA Yes Yes NA No No Yes No NA NA the forecast of the aggregated im balance position of all users at the end of each gas day? Yes NA NA No NA No NA NA NA NA NA NA Yes Yes NA No No Yes No NA NA 3.4.6. Do you provide user-friendly instrum ents for calculating tariffs? Yes No Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes No Yes DE NI Ar ticle of Anne x 1 cha pte r 3 of Ga s Re gula tion 7 1 5 / 2 0 0 9 Tr a nspa r e ncy r e quir e m e nt BBL Com pany I nterconnector UK Sw edagas & Svenska Kraftnat Gaslink BGE ( UK) Mutual Energy GTS GRTgaz National Grid ONTRAS GRTgaz Deutschland OGE Terranets BW Thyssengas Jordgas Now ega Fluxys Energinet.DK 3.4.4. 3.4.5. Gastransport Nord Gasunie Deutschland 3.4.3. Bayernets