Transport Public Accounts and Estimates Committee Friday 9 June 2006 Department of Infrastructure 2 Key Financials - 2006-07 Budget Parameters Operating Expenditure 2004-05 2005-06 2005-06 2006-07 Actual Budget Outturn Budget $m $m
Public Accounts and Estimates Committee
Friday 9 June 2006
Department of Infrastructure
2
Key Financials - 2006-07 Budget Parameters
Operating Expenditure
3,715 3,414 3,403 3,338* Transport only 3,829 3,513 3,470 3,408* Total Department* 2006-07 Budget $m 2005-06 Outturn $m 2005-06 Budget $m 2004-05 Actual $m
*Source: Budget Paper 4, Pages 73 **Includesone-off $336m resources provided free of charge
3
Key Financials - 2006-07 Budget Parameters
*Source: Budget Paper No.2 Appendix A or B for 2002-03 to 2003-04, Budget Paper no.3 Appendix A for 2004-05 to2006-07
314 336 2002-03 Budget $m
Asset Investment
2,437 660 619 317 Transport only 2,573 663 627 317 Transport and related TEI commitments* 2006-07 Budget $m 2005-06 Budget $m 2004-05 Budget $m 2003-04 Budget $m
4
Meeting Our Transport Challenges will deliver:
1.
A world class lifestyle
2.
Accessible, connected communities
3.
A safer and more secure system
4.
Reduced congestion
5.
Grow the whole state
6.
A plan for the future
5
4 years (2006-2010):
extend the hours of operation and more frequent services
the Red Orbital Smart Bus (Box Hill to Altona)
the Green Orbital Smart Bus (Nunawading to Airport West)
Buses
10 years:
extend local bus services
cross-town SmartBus network around Melbourne
services linking Doncaster with the CBD
6
SMARTBUS NETWORK
7
Trains – Building capacity
4 years (2006-2010):
–
$33.6 million for new late night train services
–
$5 million for new shoulder peak train services
–
$16.7 million for RailNet (expansion of the metro rail network) 10 years:
plus more trains & services
upgrading capacity
drivers.
8
RAIL CAPACITY PROGRAM
9
Trains – new stations and interchange upgrades
4 years (2006-2010):
Melbourne Station – to be largely completed by 2008
parks over the next two years at locations including Cranbourne, Pakenham and Wattle Glen
Darling and Upfield stations to premium stations 10 years:
Melbourne’s rail network
metropolitan stations to ‘premium’ status
transport interchanges
Ride spaces
10
Rail safety
4 years (2006-2010):
crossing upgrades
Metrol & communications systems 10 years:
system
upgrades
railway crossings including level crossings upgrades and grade separations
tech control and communications systems
11
Making transport easier to use for all Victorians
4 years:
transport more accessible for people with disabilities, older people and families with prams
seniors
10 years:
communities use existing transport infrastructure better
walking options
accessibility
12
Trams
4 years (2006-2010):
October 2006, including late night services
project 10 years:
Melbourne’s trams over the next 10 years
ThinkTram project and upgrade the St Kilda Rd tram corridor
trams
13
Roads
Bridge
14
Safety and Congestion targeted for Victorian Roads
reduce the number and severity of road crashes;
the recently announced Deer Park Bypass) to improve safety and reduce congestion in outer areas; and
connectivity and access to services across the State.
15