transparent sdn update scheduling
play

Transparent SDN Update Scheduling Peter Pereni @ EPFL Maciej - PowerPoint PPT Presentation

ESPRES: Transparent SDN Update Scheduling Peter Pereni @ EPFL Maciej Kuzniar @ EPFL Marco Canini @ UCLouvain Dejan Kosti @ KTH Network events trigger big updates Topology changes Network events trigger big updates Topology changes


  1. ESPRES: Transparent SDN Update Scheduling Peter Perešíni @ EPFL Maciej Kuzniar @ EPFL Marco Canini @ UCLouvain Dejan Kostić @ KTH

  2. Network events trigger big updates Topology changes

  3. Network events trigger big updates Topology changes

  4. Network events trigger big updates Topology changes

  5. Network events trigger big updates Topology changes

  6. Network events trigger big updates Topology changes Traffic Engineering Policy changes

  7. Network events trigger big updates Topology changes Traffic Engineering Policy changes Many rule modifications ⇨ updates take time

  8. What if we reorder installations... Update touching two (independent) flows ● blue - 3 changes on a switch ● red - 2 changes on a switch

  9. What if we reorder installations... Update touching two (independent) flows ● blue - 3 changes on a switch ● red - 2 changes on a switch

  10. What if we reorder installations... Update touching two (independent) flows ● blue - 3 changes on a switch ● red - 2 changes on a switch

  11. What if we reorder installations... Update touching two (independent) flows ● blue - 3 changes on a switch ● red - 2 changes on a switch vs

  12. What if we reorder installations... Update touching two (independent) flows ● blue - 3 changes on a switch total time same ● red - 2 changes on a switch but different ordering of rule installation matters vs

  13. Some challenges Scheduling sounds easy but ● multiple switches affected o and switch-speeds are different over time ● rule dependencies o e.g. update ingress only after core installed ● control channel is FIFO o no reordering

  14. ESPRES overview (See paper for more details) ● Keep backlog of rule installations in ESPRES o enables re-ordering on control channel ● Schedule rules to be installed next o react on-the-fly to current switch conditions o needs to be fast o support flexible goals

  15. Possible scheduling goals Already illustrated: ● install majority of flows sooner See paper: ● decrease mid-update rule overhead ● decrease transient instabilities

  16. A taste of results 1000 new flows; 18 switches

  17. A taste of results 1000 new flows; 18 switches ➢ No scheduling (send rule when dependencies are met)

  18. A taste of results 1000 new flows; 18 switches ➢ No scheduling (send rule when dependencies are met) ➢ Espres A ➢ Espres B ➢ Optimal (Offline)

  19. A taste of results 1000 new flows; 18 switches We reduce completion time by ≥40% for half of flows ➢ No scheduling (send rule when dependencies are met) ➢ Espres A ➢ Espres B ➢ Optimal (Offline)

  20. Summary ● Updates touch many flows ● Changing rule installation order helps achieve different goals ESPRES ➢ Maintain backlog of rule installations at the controller ➢ Schedule their order on-the-fly

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend