transitway
play

TRANSITWAY Policy Advisory Group Meeting December 3, 2015 MEETING - PowerPoint PPT Presentation

WEST END TRANSITWAY Policy Advisory Group Meeting December 3, 2015 MEETING AGENDA Project Background 1 West End Transitway Key Elements 2 Completing the Current Phase of Work 3 Next Steps 4 Discussion 5


  1. WEST END TRANSITWAY Policy Advisory Group Meeting December 3, 2015

  2. MEETING AGENDA • Project Background 1 • West End Transitway Key Elements 2 • Completing the Current Phase of Work 3 • Next Steps 4 • Discussion 5 • 6 Resolution of Support 2

  3. 1 PROJECT BACKGROUND 3

  4. History of Transitway Decision Making 2008 2009 2011 2012 2010 2014 2016 4

  5. High Capacity Transit West End Transitway (Current Effort) Corridors Study (2011) • Participants • Advance West End Transitway project and o High Capacity Transit Corridor Work Group address Corridor Work o City residents Group caveats through: o City staff and leadership o Environmental document • Resolutions of Support o Conceptual engineering plans o High Capacity Transit Corridor (10% design) Work Group o Capital and operating costs o Transportation Commission o Re- concurrence of ‘Resolution of Support’ o Planning Commission o City Council o 2 caveats to be addressed in future work 5

  6. Project Purpose and Need Land Use and Economic Development Project Corridor Traffic Congestion Need Issues Transit Service 6

  7. Primary Goals of Current Work Underway • Re-concurrence by the City of the Locally-Preferred Alternative defining: • Transit technology • Route • Configuration • Refined planning-level project cost estimate • Approved environmental document o Decision is made by Federal Transit Administration in cooperation with other supporting agencies • The current work underway will not result in not a final engineering design, operating plan, phasing plan, or financial plan  those things come later. 7

  8. WEST END TRANSITWAY 2 KEY ELEMENTS 8

  9. By the Numbers 10

  10. COMPLETING 3 THE CURRENT PHASE OF WORK 12

  11. Project Policy Guidance • Minimize Impact to Private Property • Minimize Parking Impacts • Avoid Reconstruction of Bridges • Avoid Parklands • Avoid Natural Resources • Comply with New Stormwater Regulations • Consistency with Existing Land Use and Adopted Plans 13

  12. Recent Coordination • City Council • Alexandria Transit Company (DASH) Board • Transportation of Directors Commission • DASH and WMATA • Planning Commission • Arlington County • Parks and Recreation • Fairfax County Commission • Environmental Policy • Southern Towers Commission • Summers Grove • Bicycle and Pedestrian Advisory Committee • Budget and Fiscal Affairs Committee 14

  13. 2012 Council Resolution: Caveats Addressed Caveats Action Taken Transitway Recommendation Evaluated To enhance access to NVCC, project Optimize alignment to better serve the Northern multiple station includes: Virginia Community location and - Pedestrian safety/accommodation College (NVCC) alignment enhancements at Braddock Road alternatives - Stations at Fillmore and Braddock - Build Alternative does not preclude other (potential future) services from directly serving main campus No action Transportation Commission to discuss Monitor transition from Alternative D (Bus Rapid required at this when appropriate Transit) to Alternative G time by the (Streetcar) current project 15

  14. Other Key Items Addressed Key Item Action Taken Transitway Recommendation • Selected cross-sectional alternative with multiuse Multiple Provide Adequate Bicycle alternatives path along one side where corridor is modified • Updated layout to best address comments received Accommodation on S. evaluated Van Dorn Street (path width, intersection/driveway-related features) • Select alternative that reduces parking/property Minimize Multiple alternatives impacts from 33 spaces lost to 3 spaces lost. Land Parking/Property evaluated owner (JBG) supports this alternative as does the Impacts on Van Dorn Street near Sanger community. Avenue • Establish future policy ROW line Minimize Right-of- Multiple • Phased cross section implementation establishing Way/Property Impacts alternatives evaluated location of permanent Transitway and providing along S. Van Dorn minimum adequate bike/ped accommodations Street through corridor constrictions • Require redevelopment/development to build/provide funds for/ construct full cross section consistent with adopted plans (policies) • Reduced impacts along Van Dorn street (vicinity of Adjusted alignment Minimize residential and cross section Stevenson) and along Beauregard Street use parking impacts (overall) • Alignment will enter mall property and connect to the Establish Landmark Multiple Mall-related Alignment alternatives transit center • Locate station at or adjacent to transit center evaluated 16

  15. Other Key Items Addressed Key Item Action Taken Transitway Recommendation • Stop buses within Metrorail station bus facility Confirm that Van Dorn Worked with • Confirmed that station can support Transitway buses WMATA on station Metrorail Station has capacity for buses Adequate Bus Capacity Assessed project’s • Manage stormwater within right of way (ROW) Stormwater • Identification of specific treatments in specific Compliance of Project ability to meet current locations occurs in design phase • May also afford the city stormwater management requirements credits (will need future confirmation) • Match Small Area Plan (SAP) interim ROW Adjusted corridor Match Beauregard Plan SAP adopted layout/alignment interim ROW • Two-directional bus routing along Metro Road Optimize Southern Adjusted corridor • Reduced traffic impacts at Van Dorn Terminus Alignment alignment Road/Eisenhower Avenue (Metro Road) • Reduced impacts along Eisenhower Avenue • Refine during next phase of design: Minimize Multiple feasible o Parking/Property alternatives being Bus operations and access to transit o Impacts at Southern evaluated Traffic operations and parking impacts • No expected negative impact to West End Towers Transitway Project or Southern Towers 17

  16. Metro Road – Preliminary Concept 18

  17. Metro Road – Preferred Alignment 19

  18. Metro Road – Summary of Evaluation Design Option Eisenhower & Metro Road Bi-Directional Along Metro Road Criteria Best – Improves accommodation along Eisenhower Good – No ped/bike enhancements to Eisenhower Transit access Avenue Avenue Good – Highly visible, but along less-traveled Metro Transit visibility Best – Highly visible along Eisenhower Avenue Road Transit travel time (in minutes) between Van Best – Shorter travel time Good – Slightly longer travel time (+/- 40 sec) Dorn Metrorail Station and Edsall Road Traffic operations quality at S. Van Dorn Street/ Good – Transit operation adds to delay at intersection Eisenhower Avenue Best – No additional delay to intersection (+/- 23 sec) intersection in seconds of delay - AM (PM) Good – Requires additional widening of one block of Construction effects Best – Best uses existing infrastructure Eisenhower Avenue Good – Approximately $1 million more than Option 2 Best – Approximately $1 million less than Option 1 Cost Good – Within ROW, but reduces existing buffer Local community impact Best – No change to roadways along Summers Grove between Eisenhower Ave and Summers Grove 20

  19. Environmental Documentation Key Topics • Land Acquisition • Environmental Justice • Compliance with Local • Secondary & Cumulative Plans, Land Use, & Effects Zoning • Transportation • Neighborhoods & • Construction Effects Community Facilities • Economic Development Continuous coordination with FTA on development of Documented Categorical Exclusion (CE) 21

  20. Environmental Findings • No impacts to: o Air quality o Cultural Resources and Section 106 (National Historic Preservation Act) o Noise levels o Parks o Streams (no direct impact) o Vibration • Improved stormwater quality and reduced quantity in keeping with Virginia Water Control Law • Net increase in number of trees • Visual resources changes consistent with City-adopted plans • Hazardous and contaminated materials sites further analyzed prior to construction 22

  21. Project and Operating Costs • Refining initial cost estimates o Project cost estimates based on concept engineering Item Cost (2015 Dollars) Capital Construction (includes Roadway, stations, systems, ROW & utilities) $60 to 70 million Fleet (buses, including spares) $17 to 19.5 million Project Development (design, fees, permitting, legal, surveys, testing, etc.) $16 to 18.5 million Contingency $28 to 32 million Total Project Cost $121 to 140 million o Range of operating cost ($5 to 9 million) based on route and schedule assumptions 23

  22. Funding Plan • Funding sources and budget process o Highly rated in NVTA list of projects for regional funding o Anticipated application for Federal Transit Administration capital grant o City will work with Commonwealth regarding potential transit funding through I-395 HOT lane project 24

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend