TOWN OF BERLIN STORMWATER MANAGEMENT PROJECTS UPDATE Prepared for: T own of Berlin Mayor and Council Prepared by: February 26, 2018 TIER I COMPLETED / UNDER CONSTRUCTION PROJECTS 2 TIER 1 - COMPLETED PROJECTS PROJECT 1 - HUDSON BRANCH


  1. TOWN OF BERLIN STORMWATER MANAGEMENT PROJECTS UPDATE Prepared for: T own of Berlin Mayor and Council Prepared by: February 26, 2018

  2. TIER I – COMPLETED / UNDER CONSTRUCTION PROJECTS 2

  3. TIER 1 - COMPLETED PROJECTS PROJECT 1 - HUDSON BRANCH AT FLOWER STREET OFFLINE WETLANDS 3

  4. TIER 1 - COMPLETED PROJECTS PROJECT 2 - HUDSON BRANCH AT FLOWER STREET CULVERT REPLACEMENT 4

  5. TIER 1 - COMPLETED PROJECTS PROJECT 3 - HUDSON BRANCH AT WILLIAM STREET OFFLINE WETLANDS 5

  6. TIER 1 - COMPLETED PROJECTS PROJECT 4 - HUDSON BRANCH AT WILLIAM STREET CULVERT REPLACEMENT 6

  7. TIER 1 – NEARING START OF CONSTRUCTION PROJECT 5 - HUDSON BRANCH AT PINE, FRANKLIN, GRICE AND NELSON STREETS 7

  8. TIER 2 - PROJECTS 8

  9. TIER 2 – RECOMMENDED ORDER Hudson Branch Projects Project 1 – Complete Pine, Franklin, Grice and Nelson Streets Project 2 – Bottle Branch Road – Channel Stabilization Bottle Branch Projects Project 3 – Bottle Branch at Henry’s Green and Henry’s Mill Project 4 – Bottle Branch at West Street and Abbey Lane Project 5 - Bottle Branch at Decatur Street 9

  10. PROJECT 1 – COMPLETION OF HUDSON BRANCH ALONG PINE, FRANKLIN, GRICE AND NELSON STREETS 10

  11. PROJECT 2 - HUDSON BRANCH AT BOTTLE BRANCH ROAD – CHANNEL STABILIZATION AND RESTORATION 11

  12. PROJECT 3 – BOTTLE BRANCH AT HENRYS MILL AND HENRYS GREEN 12

  13. PROJECT 4 – BOTTLE BRANCH AT WEST STREET AND ABBEY LANE 13

  14. PROJECT 5 – BOTTLE BRANCH AT DECATUR STREET – STEAM RELOCATION AND RESTORATION 14

  15. NEXT STEPS Grant Applications Department of Natural Resources – “Chesapeake and Atlantic Coastal Bays Trust Fund” 1. Grant Application Due March 30, 2018 • Project Selection - July 1, 2018 • DNR/NOAA/EPA/CCS - “Community Resilience Grant Program” 2. Grant Application Due March 2, 2018 • Project Selection - April 13, 2018 • U.S. Department of Agriculture 3. Requires submission of a Preliminary Engineering Report • USDA reviews PER and submits to National for funding request. • No specific award timeline • 15

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.