The Renaissance Plan
An Initiative of Goal 3 of Envisioning 2024
The Renaissance Plan An Initiative of Goal 3 of Envisioning 2024 - - PowerPoint PPT Presentation
The Renaissance Plan An Initiative of Goal 3 of Envisioning 2024 Overview of the Renaissance Plan Ky Snyder VP Operations Zack Knipe Director Planning, Design and Construction James Miyashiro Chief Public Safety Andre Mallie Assistant
An Initiative of Goal 3 of Envisioning 2024
Ky Snyder VP Operations Zack Knipe Director Planning, Design and Construction James Miyashiro Chief Public Safety Andre Mallie Assistant Vice President Auxiliary Services
Construction Schedule: Five-Project Plan
Mixed-use educational facility featuring 24-hour collaborative study space, grab-n- go food service, and outdoor study space
Representative
Project Manager Meaghan Christman
Interior renovation of student study space, staff space, and collection
Stakeholder Representative
spaces
room
Project Manager Erin Borzage
Modernization and improvements to the original campus structures
meeting December 12, 2018
Representative
Project Manager Zachary Randel
meeting December 17, 2018
Representative
Project Manager Erin Borzage
being fully occupied
Knauss Center programming
fund raising efforts
Project Manager TBD
Transportation and Mobility Plan: June 2019 to August 23, 2019
Copley to The Immaculata
will be closed
Garage through exit (green line)
Transportation and Mobility Plan: August 23, 2019 to June 2020
Way, one-way traffic northbound and eastbound on Manion Way
spaces
and garage opens
Temporary Offices
Study Spaces
Dining Services: June 2019 to August 2019
Missions Café (July only)
Dining Services: September 2019 to May 2020
Housing / Conference Services: June 2019 to August 2019
Housing / Conference Services: September 2019 to May 2020
* Draft plan to be presented at September 24th and 26th Forums
* Final draft plan to be presented at December 3rd and 5th Forums
An Initiative of Goal 3 of Envisioning 2024