The Norwegian governance scheme for major public investment projects - - PowerPoint PPT Presentation

the norwegian governance scheme for major public
SMART_READER_LITE
LIVE PREVIEW

The Norwegian governance scheme for major public investment projects - - PowerPoint PPT Presentation

The Norwegian governance scheme for major public investment projects Gro Holst Volden, Research Director Concept research program Norwegian University of Science and Technology Trondheim, Norway 1 1 1 Public project failure Cost


slide-1
SLIDE 1

1 1 1

The Norwegian governance scheme for major public investment projects

Gro Holst Volden, Research Director Concept research program Norwegian University of Science and Technology Trondheim, Norway

slide-2
SLIDE 2

2 2 2

Public project failure

  • Cost overruns, delays, benefits not realized, hidden agendas, etc.
  • Especially cost overruns have been a common problem across

countries and over time. Well documented in the literature

– e.g. Morris and Hough, 1991, MacDonald, 2002, Flyvbjerg et al., 2003.

  • Norwegian study (background for the scheme)

– Berg et al., 1999

  • Common explanations

– technical – cognitive – Political/strategic

slide-3
SLIDE 3

3 3 3

Project

Operational success Tactical and strategic success

Measuring Project Success

Conceptual solution Project plan Delivery Effect

slide-4
SLIDE 4

4 4 4

Project governance

  • “The term ”project governance” refers to the processes, systems

and regulations that society (the financing party) must have in place to ensure that projects are successful” (Samset and Volden, 2013)

  • Minimum requirements for a project governance scheme (Haanæs

et al., 2006)

– Clearly defined project phases – Clearly defined decision points – Quality assured basis for the decisions – Simplicity – A certain standardization and common terminology

slide-5
SLIDE 5

5 5 5

Project Governance in Norway

Pre-project Project Parliament approval Cabinet decision Pre-study

QA1 QA2

Quality assurance of conceptual solution Quality assurance of cost and steering frames

  • The Quality Assurance scheme introduced in year 2000/2005

applies to major public projects (> 750 mill. NOK)

slide-6
SLIDE 6

6 6 6

Pre-project Project Pre-study

QA1 QA2 The content of the QA Documentation to be produced by Ministry/ agency responsible for the project

  • Review the

documentation, check for consistency and exploitation of

  • pportunities
  • Independant

uncertainty analysis and CBA

  • Review the

documentation

  • Independent

uncertainty analysis

  • Give

recommendations regarding cost frame and steering frame

Conceptual Appraisal Document CAD

  • Needs analysis
  • Project goals and

requirements

  • Possibility study
  • Cost-Benefit Analysis
  • Overall project

management document (steering document)

  • Complete cost estimate
  • Analysis of alternative

contract strategies

slide-7
SLIDE 7

7 7 7

Projects subjected to external quality assurance

Number of projects Hereof completed Number of projects subjected to QA1 (2005-2015) 76 Number of projects subjected to QA2 (2000-2015) 183 89 Number of projects subjected to QA1 and QA2 (2005-2015) 15 Total number of reviews 232 89

slide-8
SLIDE 8

8 8 8 road rail defence ICT constuction

  • ther

Projects subjected to external quality assurance

slide-9
SLIDE 9

9 9 9

Lessons regarding QA1

  • The evaluation of effects is years ahead.
  • CAD/QA1 has led to a more systematic approach to early

project assessment.

  • The quality of the analyses have improved steadily over time
  • A shift from bottom-up process guided by local stakeholders, to

more power to the administration and Cabinet

  • However, not many projects are rejected, despite low

profitability, and when recommendations from an autority and the QA conflict, the Cabinet more often follows the agency.

slide-10
SLIDE 10

10 10 10

Lessons regarding QA1

CAD

slide-11
SLIDE 11

11 11 11

Lessons regarding QA2

The reviewers’ recommended cost frames are based on stocastic estimation techniques. Cost frame – P85 Target cost – P50

target cost

slide-12
SLIDE 12

12 12 12

  • 50,0
  • 40,0
  • 30,0
  • 20,0
  • 10,0

0,0 10,0 20,0 30,0 40,0 50,0

Cost

  • verrun

(%) Cost savings (%) Cost deviation relative to the P85 budget (percentages)

N = 78

Lessons regarding QA2

  • 17 cost overruns and the rest, about 80 % with cost savings.
  • The total net savings amount to 6 % of the total investments.
slide-13
SLIDE 13

13 13 13

Cost

  • verrun

(%) Cost savings (%) Cost deviation relative to P50 estimates (percentages)

  • 50
  • 40
  • 30
  • 20
  • 10

10 20 30 40 50

N = 68

Lessons regarding QA2

slide-14
SLIDE 14

14 14 14

Transportation

Cost deviation relative to P50 estimates in three sectors

Construction Defence

N = 47 N = 13 N = 7

slide-15
SLIDE 15

15 15 15

Cost

  • verrun

(%) Cost savings (%) Cost deviation relative to the size of the P50 budget (percentages)

slide-16
SLIDE 16

16 16 16

Cost deviation relative to the P50 budget for projects approved by Parliament 2001 ‐ 2011

slide-17
SLIDE 17

17 17 17

Spin-offs and broader benefits of the scheme

  • Ministries and agencies spend more resources in the front-end and

invest in competence.

  • Some agencies exempted from the QA regime have voluntarily

introduced variants of it.

– Health sector investments – Electricity transmission line projects – Investments at municipal level – Other countries are inspired by the Norwegian scheme

  • Extensive research and education in the area of project governance

at university level.

slide-18
SLIDE 18

18 18 18

A remaining challenge…

  • Cost creep between QA1 and QA2

QA2 QA1

slide-19
SLIDE 19

19 19 19

Other countries with similar schemes

Samset et al., 2016

slide-20
SLIDE 20

20 20 20

Conclusions

  • After QA2 was introduced, 80 % of public projects are

completed within budget. Operational project success is definitely improved.

  • No QA1 projects have yet been completed. Its effect on tactical

and strategic performance therefore remains to be seen

 ?

slide-21
SLIDE 21

21 21 21

Thank you for your attention www.ntnu.no/concept

slide-22
SLIDE 22

22 22 22

References

  • Berg, P. et.al. (1999): Styring av statlige investeringer. Sluttrapport fra styringsgruppen, Finansdepartementet, 10 February 1999.
  • Flyvbjerg, B., M. K. Skamris Holm and S. L. Buhl (2003): “How common and how large are cost overruns in transport infrastructure

projects?” Transport Review, 2003, Vol. 23, No. 1, 71-88

  • Haanæs, S., E. Holte and S. Larsen (2005): Beslutningsunderlag og beslutninger i store statlige investeringsprosjekter, Concept report
  • No. 3
  • MacDonald, M., 2002. Review of Large Public Procurement in the UK. London: HM Treasury.
  • Morris, P.W.G. and Hough, G.H. (1991): The Anatomy of Major Projects. A Study of the Reality of Project Management, John Wiley &

Sons, Chichester, UK, ISBN 0-471-91551-3

  • Samset et al., 2016, Governance schemes for major public investment projects: A comparative study of principles and practices in six

countries, Concept report no. 47

  • Samset, K. and Volden, G.H., 2013, Investing for impacts. Lessons with the Norwegian State Project Model and the first investment

projects that have been subjected to external quality assurance, Concept report no. 36