1 1 1
The Norwegian governance scheme for major public investment projects
Gro Holst Volden, Research Director Concept research program Norwegian University of Science and Technology Trondheim, Norway
The Norwegian governance scheme for major public investment projects - - PowerPoint PPT Presentation
The Norwegian governance scheme for major public investment projects Gro Holst Volden, Research Director Concept research program Norwegian University of Science and Technology Trondheim, Norway 1 1 1 Public project failure Cost
1 1 1
Gro Holst Volden, Research Director Concept research program Norwegian University of Science and Technology Trondheim, Norway
2 2 2
– e.g. Morris and Hough, 1991, MacDonald, 2002, Flyvbjerg et al., 2003.
– Berg et al., 1999
– technical – cognitive – Political/strategic
3 3 3
Project
Operational success Tactical and strategic success
Conceptual solution Project plan Delivery Effect
4 4 4
– Clearly defined project phases – Clearly defined decision points – Quality assured basis for the decisions – Simplicity – A certain standardization and common terminology
5 5 5
Pre-project Project Parliament approval Cabinet decision Pre-study
QA1 QA2
Quality assurance of conceptual solution Quality assurance of cost and steering frames
6 6 6
Pre-project Project Pre-study
QA1 QA2 The content of the QA Documentation to be produced by Ministry/ agency responsible for the project
documentation, check for consistency and exploitation of
uncertainty analysis and CBA
documentation
uncertainty analysis
recommendations regarding cost frame and steering frame
Conceptual Appraisal Document CAD
requirements
management document (steering document)
contract strategies
7 7 7
Number of projects Hereof completed Number of projects subjected to QA1 (2005-2015) 76 Number of projects subjected to QA2 (2000-2015) 183 89 Number of projects subjected to QA1 and QA2 (2005-2015) 15 Total number of reviews 232 89
8 8 8 road rail defence ICT constuction
9 9 9
10 10 10
CAD
11 11 11
target cost
12 12 12
0,0 10,0 20,0 30,0 40,0 50,0
Cost
(%) Cost savings (%) Cost deviation relative to the P85 budget (percentages)
N = 78
13 13 13
Cost
(%) Cost savings (%) Cost deviation relative to P50 estimates (percentages)
10 20 30 40 50
N = 68
14 14 14
Transportation
Construction Defence
N = 47 N = 13 N = 7
15 15 15
Cost
(%) Cost savings (%) Cost deviation relative to the size of the P50 budget (percentages)
16 16 16
Cost deviation relative to the P50 budget for projects approved by Parliament 2001 ‐ 2011
17 17 17
– Health sector investments – Electricity transmission line projects – Investments at municipal level – Other countries are inspired by the Norwegian scheme
18 18 18
QA2 QA1
19 19 19
Samset et al., 2016
20 20 20
21 21 21
22 22 22
projects?” Transport Review, 2003, Vol. 23, No. 1, 71-88
Sons, Chichester, UK, ISBN 0-471-91551-3
countries, Concept report no. 47
projects that have been subjected to external quality assurance, Concept report no. 36