the grosvenor experience
play

THE GROSVENOR EXPERIENCE January 2016 INTERNAL Background & - PowerPoint PPT Presentation

THE GROSVENOR EXPERIENCE January 2016 INTERNAL Background & Expected Conditions Our Experiences Major Review Future Works 2 INTERNAL GROSVENOR Mine Specifications 7 Mtpa Longwall coal operation Situated between


  1. THE GROSVENOR EXPERIENCE January 2016 INTERNAL

  2. • Background & Expected Conditions • Our Experiences • Major Review • Future Works 2 INTERNAL

  3. GROSVENOR Mine Specifications • 7 Mtpa Longwall coal operation • Situated between existing Moranbah North mine & Moranbah South Project • Goonyella Middle (GM) Seam in Moranbah Coal Measures • Development achieved 26 km in 2015 with: – 3 x ED25 – 2 x 12CM12 • Longwall mining to commence May 2016 • Designed on the back of mining experiences with similar environments 3 INTERNAL

  4. GROSVENOR Geology and Geotechnical Environment 166 166 Seam Roof 1 0.7m Ply 1 Band 2 0.8m Ply 2 Band 168 168 3 2.1m 5.2m 4A 4B 5T 170 170 Tonstein Band 5B 1.2m Seam Floor 4 INTERNAL

  5. • Background & Expected Conditions • Our Experiences • Major Review • Future Works 5 INTERNAL

  6. OUR EXPERIENCES I nexistence of a Coal Roof “Beam” • Not a typical coal beam as seen in Moranbah North (MNC) • Grosvenor Ply 1 classed as transitional from coal to the overlying carbonaceous mudstone above • Geotechnically low strength coal roof – is transitional by nature containing multiple bands 6 Density plots of GRO and MNC outside split zone, highlighting difference of transitional coal roof INTERNAL

  7. OUR EXPERIENCES Low Strength Roof Environment • Roof – Immediate roof strength impacted by seam split – Split zone interburden low strength (<10 MPa), thinly bedded, carbonaceous and/or tuffaceous claystone unit – Highly carbonaceous mudstones with sheared & polished bedding planes continues above/below ply 1 7 INTERNAL

  8. DEVELOPMENT EXPERIENCE Max Displacement per CT - TG101 140 400 Split Zone Begins 350 120 300 100 Max Displacement (mm) 250 80 Floor Cut to Increase Coal Beam DoC (m) 200 90° Break – travel to belt rd 60 150 New Support Rules 40 Truss Support 100 Truss Support Fenoflex Trial MW10 Trial MW10 Trial MW10’s 20 50 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Cut Through Reasonably benign conditions 8 < 220m DOC. No major Issues INTERNAL

  9. 150 400 100 200 TG101 8 CT 50 0 0 90° Breakaway – Stress Orientation 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425 • DoC 220m • Driven 90° - Prove driving into principal stress improves productivity (unsuccessful) – Cleat direction within 15° of roadway (triggered TARP to elevate support) – Roof Displacement thought to be due to Cut Through (CT) orientation • Support: 6 x 1.8m bolt per m and 2 x 6.2m Megabolt (MW9) every 2m • 50mm trigger: 1 x 8.2m Centreline (C/L) Megabolt (MW9) every 2m • Maximum Total Displacement (MTD) 70mm 9 INTERNAL

  10. 150 400 100 200 TG101 10 CT 50 0 0 Fenoflex – Arrest Roof Displacement 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425 • DoC 245m • Changed primary support - 8 bolt pattern (inbye 9 CT) • Megabolts in belt road intersection grouted prior to breakoff (previously grouting TARP driven) • TARP revision for CT’s: – 30mm Trigger to grout Megabolt (MW9) – 50mm Trigger install 1 x 8.2m C/L Megabolt (MW9) – All CT’s driven with 2 x 8.2m Megabolt (MW9) per m at minimum • Displacement > 70mm resulted in Fenoflex to be injected belt road side of CT (unsuccessful) • MTD 96mm 10 INTERNAL

  11. 150 400 100 200 TG101 13 CT 50 0 0 First CT Driven in Split Zone 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425 • DoC 280m • Primary support 8 bolt pattern with 2 x 8.2m Megabolt (MW9) per m • Megabolts grouted at 30mm, completed CT, tell-tales stable at 40mm • During 14CT driveage, roof reactivated, installed C/L Megabolts (MW9) • After second surge CT stabilised • MTD 72mm 11 INTERNAL

  12. 150 400 100 200 TG101 14 CT 50 0 0 Trusses Installed – Arrest Roof Displacement 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425 • DoC 290m • High rate of displacement (40mm in 24 hours) – no sign of arresting • At 50mm displacement installed 8.2m C/L Megabolts (MW9) • To pre-empt 80mm displacement Trusses installed at 2m spacing (successful) • MTD 84mm 12 INTERNAL

  13. 150 400 100 200 TG101 15 CT 50 0 0 First Trial MW10 Megabolt – Minimise Displacement 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425 • DoC 300m • Trial of higher capacity Megabolt (69t MW10 compared to 60t MW9) • MW10 – 2 x1000mm resins – Unbonded section of ~3.5m – 2m grout tubes installed • Least amount of movement of a CT in the split zone (inconclusive due to sandstone in Megabolt horizon) • MTD 18mm Minimal fracturing/shearing 13 INTERNAL

  14. 150 400 100 200 TG101 16 CT 50 0 0 Cut on Floor - Increase Coal Beam 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425 • DoC 310m • Cut on floor to increase coal beam thickness by 300mm • Significant bagging & C/L cracking observed – comparable to outbye C/T’s • At 50mm movement, 1 week after driveage installed C/L Megabolt (MW9) • Trial of full column grouting of Megabolts (MW9) every window – no sign of arresting displacement • Observed shearing at 2 - 4m roof horizon • Cut on floor with MW9s (unsuccessful) • MTD 71mm 14 INTERNAL

  15. 150 400 100 200 TG101 18 CT 50 0 0 Second Trial MW10 Megabolt – Minimise Displacement 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425 • DoC 320m • Continued to cut on floor with retrial MW10’s • First sign of floor heave – Generally in isolated areas (10-15m in length, CT’s more susceptible) – Difficult to quantify – estimated 300mm – Developed site specific floor heave potential index • MTD 28mm Floor heave identified in TG101 18 C/T – floor simply ‘popped up’ during inspection 15 INTERNAL

  16. 150 400 100 200 TG101 20 CT 50 0 0 Cut into floor - Increase Coal Beam 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425 • DoC 350m • Cut 400mm into floor to increase coal beam thickness by 700mm (C 19-20 & 20 CT) (unsuccessful) • High rate of displacement (>30mm in 12 hours) – no sign of arresting • Excessive rib spalls >0.5m due to Tonstein higher in ribs • Slippery stone floor, blocky when broken • At 115mm displacement installed Trusses • MTD 131mm 16 INTERNAL

  17. 150 400 100 200 TG101 22 CT 50 0 0 Revised Support Rules 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425 • DoC 360m • First CT driven with revised support rules and TARPs – fundamental changes • MW10s grouted every window • To pre-empt 100mm displacement C/L Megabolts (MW10) installed at 90mm (2m spacing) • High displacement triggers allowed completion of CT before C/L’s – C/L support taken offline, no delays (successful) • MTD 122mm +17m +17m +34m 17 INTERNAL

  18. • Background & Expected Conditions • Our Experiences • Major Review • Future Works 18 INTERNAL

  19. MAJOR REVIEW • Grosvenor geotechnically characterised as a low strength roof environment (CMRR ranges 30-35) • Conditions have been managed successfully to date – Current market dictates need to drive efficiency into strata management • Grosvenor’s low strength roof: – Accept the roof displacement (plastic deformation) process and design accordingly • Major review undertaken by external consultants about key strategies to follow – I n conjunction with numerous trials have resulted in our current support rules and TARP’s – Moved towards higher capacity Megabolt support with un-bonded section (MW10) 19 INTERNAL TG101 UCS Plot

  20. MAJOR REVIEW Key Changes to MMSR and TARP Triggers • No coal beam thickness trigger – Grosvenor does not have a coal beam • Strategy based around moving towards a suspension type model • Increased telltale triggers • Relaxed centreline crack trigger - > 50mm cracking in addition to other deformation signs results in moving up a support level • Post groutable un-bonded Megabolt (MW10) with routine grouting every 24 hours, unless specified by displacement trigger (> 50mm in 12 hours) LOCATION SUPPORT DENISTY TELLTALE TRIGGER 2 x 8.2m long cable per 1m <100mm Gateroad Cut Throughs 100mm – 130mm and Intersections As above + 1 x C/L 8.2m Megabolt per 1m 130mm – 150mm As above + 10m Trusses every 2m 2 x 8.2m Megabolt per 4m <40mm Gateroads Headings 40mm – 60mm 2 x 8.2m Megabolt per 2m 60mm – 80mm As above + C/L 8.2m Megabolt per 2m 20 INTERNAL

  21. • Background & Expected Conditions • Our Experiences • Major Review • Future Works 21 INTERNAL

  22. WHERE ARE WE GOING? Trials and Future Works • Number of key areas we are investigating – Bolt length review: Would moving to a 2.1m bolt make a difference? – High capacity point anchored bolts: Could this be the answer to eventually reducing Megabolt density? – Analytical rating specific to Grosvenor that can be linked to required support density – Further development of ground deformation curves for weak roof environment: How much movement will happen regardless of support density? – New roof mesh trial – very high MPa and lightweight steel  Act as a strap across the roadway to combat centreline sag  Address tearing issue in heavily deformed cut throughs 22 INTERNAL

  23. WHERE ARE WE GOING? Future Challenges Expected • Depth of cover increasing to deepest in QLD (currently mining MG102 to 480m) • Bottom rib bolt issues – spalling lower rib • High gas content inbye LW102 • LW startup early May – mine optimised for LW retreat, however what conditions will we encounter? 23 INTERNAL

  24. THANK YOU

  25. APPENDICIES 25 INTERNAL

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend