THE GROSVENOR EXPERIENCE
January 2016
INTERNAL
THE GROSVENOR EXPERIENCE January 2016 INTERNAL Background & - - PowerPoint PPT Presentation
THE GROSVENOR EXPERIENCE January 2016 INTERNAL Background & Expected Conditions Our Experiences Major Review Future Works 2 INTERNAL GROSVENOR Mine Specifications 7 Mtpa Longwall coal operation Situated between
January 2016
INTERNAL
2 INTERNAL
3 INTERNAL
Mine Specifications
– 3 x ED25 – 2 x 12CM12
similar environments
4 INTERNAL
Geology and Geotechnical Environment
166 168 170
1 2 3 4A 4B 5T 5B
166 168 170
5.2m 1.2m 2.1m 0.8m 0.7m
Tonstein Band Ply 2 Band Ply 1 Band Seam Roof Seam Floor
5 INTERNAL
6 INTERNAL
Density plots of GRO and MNC outside split zone, highlighting difference of transitional coal roof
Inexistence of a Coal Roof “Beam”
7 INTERNAL
– Immediate roof strength impacted by seam split – Split zone interburden low strength (<10 MPa), thinly bedded, carbonaceous and/or tuffaceous claystone unit – Highly carbonaceous mudstones with sheared & polished bedding planes continues above/below ply 1
Low Strength Roof Environment
8 INTERNAL
50 100 150 200 250 300 350 400
20 40 60 80 100 120 140 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
DoC (m) Max Displacement (mm) Cut Through
Max Displacement per CT - TG101
90° Break – travel to belt rd Fenoflex Trial Truss Support Reasonably benign conditions < 220m DOC. No major Issues
Split Zone Begins
MW10 Trial Floor Cut to Increase Coal Beam MW10 Trial MW10’s Truss Support New Support Rules
9 INTERNAL
200 400
50 100 150 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425
– Cleat direction within 15° of roadway (triggered TARP to elevate support) – Roof Displacement thought to be due to Cut Through (CT) orientation
90° Breakaway – Stress Orientation
10 INTERNAL
200 400
50 100 150 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425
– 30mm Trigger to grout Megabolt (MW9) – 50mm Trigger install 1 x 8.2m C/L Megabolt (MW9) – All CT’s driven with 2 x 8.2m Megabolt (MW9) per m at minimum
Fenoflex – Arrest Roof Displacement
11 INTERNAL
200 400
50 100 150 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425
First CT Driven in Split Zone
12 INTERNAL
200 400
50 100 150 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425
Trusses Installed – Arrest Roof Displacement
13 INTERNAL
200 400
50 100 150 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425
– 2 x1000mm resins – Unbonded section of ~3.5m – 2m grout tubes installed
horizon)
First Trial MW10 Megabolt – Minimise Displacement
Minimal fracturing/shearing
14 INTERNAL
200 400
50 100 150 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425
Cut on Floor - Increase Coal Beam
15 INTERNAL
200 400
50 100 150 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425
– Generally in isolated areas (10-15m in length, CT’s more susceptible) – Difficult to quantify – estimated 300mm – Developed site specific floor heave potential index
Second Trial MW10 Megabolt – Minimise Displacement
Floor heave identified in TG101 18 C/T – floor simply ‘popped up’ during inspection
16 INTERNAL
200 400
50 100 150 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425
Cut into floor - Increase Coal Beam
17 INTERNAL
200 400
50 100 150 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425
– C/L support taken offline, no delays (successful)
Revised Support Rules
+34m +17m +17m
18 INTERNAL
19 INTERNAL
– Current market dictates need to drive efficiency into strata management
– Accept the roof displacement (plastic deformation) process and design accordingly
– In conjunction with numerous trials have resulted in our current support rules and TARP’s – Moved towards higher capacity Megabolt support with un-bonded section (MW10)
TG101 UCS Plot
20 INTERNAL
moving up a support level
displacement trigger (> 50mm in 12 hours)
Key Changes to MMSR and TARP Triggers
LOCATION SUPPORT DENISTY TELLTALE TRIGGER Gateroad Cut Throughs and Intersections 2 x 8.2m long cable per 1m <100mm As above + 1 x C/L 8.2m Megabolt per 1m 100mm – 130mm As above + 10m Trusses every 2m 130mm – 150mm Gateroads Headings 2 x 8.2m Megabolt per 4m <40mm 2 x 8.2m Megabolt per 2m 40mm – 60mm As above + C/L 8.2m Megabolt per 2m 60mm – 80mm
21 INTERNAL
22 INTERNAL
– Bolt length review: Would moving to a 2.1m bolt make a difference? – High capacity point anchored bolts: Could this be the answer to eventually reducing Megabolt density? – Analytical rating specific to Grosvenor that can be linked to required support density – Further development of ground deformation curves for weak roof environment: How much movement will happen regardless of support density? – New roof mesh trial – very high MPa and lightweight steel
centreline sag
throughs
Trials and Future Works
23 INTERNAL
Future Challenges Expected
25 INTERNAL
26 INTERNAL
14ct 9ct 10ct 11ct 8ct 12ct 13ct 16ct 17ct 19ct 16ct to 21ct based on cutting on the floor profile 21ct 25ct-26ct 29ct
27 INTERNAL
28 INTERNAL
Telltale Movement CT vs Hdgs
50 100 150 200 250 300 350 400
20 40 60 80 100 120 140
DoC (m) Max Displacement (mm) Heading
Max Displacement per Heading - TG101
50 100 150 200 250 300 350 400
20 40 60 80 100 120 140
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 DoC (m) Max Displacement (mm) Cut Through
Max Displacement per CT - TG101
29 INTERNAL
Centreline cracking and Roof Bagging
significant centreline crack – had 42mm holes drilled inside the cracks and inspected with borescope camera
cracking >50mm extended ~200-300mm into the roof and appeared to stop out at a bedding plane
LOCATION HEIGHT OF FRACTURING OBSERVED MG102 6CT 0.6m MG101 7CT 0.6m MG101 11CT 1.2m TG101 8CT 0.5m TG101 14CT 0.5m TG101 17CT 0.7m
30 INTERNAL
top of the ply 2 band
31 INTERNAL
development roof).