The George Hotel & Residences Gibsons BC Summary of Building - - PowerPoint PPT Presentation

the george hotel residences
SMART_READER_LITE
LIVE PREVIEW

The George Hotel & Residences Gibsons BC Summary of Building - - PowerPoint PPT Presentation

Presentation to Town of Gibsons COW - June 16, 2015 The George Hotel & Residences Gibsons BC Summary of Building Height Changes -Key Dates Purpose: The purpose of todays presentation is to review the changes to building height


slide-1
SLIDE 1

Presentation to Town of Gibson’s COW - June 16, 2015

The George Hotel & Residences

Gibsons BC

slide-2
SLIDE 2

Summary of Building Height Changes -Key Dates

The George Hotel & Residences Gibsons BC

Purpose: The purpose of today’s presentation is to review the changes to building height design in response to Geotechnical Investigations and other issues. Key Dates: Issued for Rezoning – September 2013 Response to ADP - December 2013 & February 2014 Response to Geotechnical Investigation #1 – September 2014 Response to Geotechnical Investigation #2 – May 2015

slide-3
SLIDE 3

Original Submission- Issued for Rezoning September, 2013

The George Hotel & Residences Gibsons BC

Height:

September 2013 Requested Building Height

  • Residential: 100’-2-1/2” (96’-2 ½”)
  • Hotel: 124’-4” (120’-4”)
  • 5 storey residential facing GP Road
  • 6 storey Hotel facing GP Road

Original Rendering

slide-4
SLIDE 4

Response to ADP- Issued for December 2013 & February 2014

The George Hotel & Residences Gibsons BC

Height:

  • September 2013 Requested Building Height

Residential: 100’-2-1/2” (96’-2 ½”) Hotel: 124’-4” (120’-4”)

  • December 2013 & February 2014 Revised requested building massing in

response to ADP Residential: 100’-2-1/2” (96’-2 ½”) Hotel: 124’-4” (120’-4”)

Key Features:

  • Stepping of Gower Point Road façade (6 storeys to stepped 5 storey)
  • Stepping of Hotel Roof line ( to break up horizontal line)
  • Improved form and character on the waterfront walk ( revised canopies, clock

tower, off line, signage, seating, public space etc.)

  • Addition of habitat pockets on waterfront
  • Revised form and character on waterfront restaurant ( to match Gibson’s

vernacular) Waterfront Walk rendering post ADP

slide-5
SLIDE 5

Response to ADP- Issued for December 2013 & February 2014

The George Hotel & Residences Gibsons BC

Original Section Revised Section showing stepped roof line & hotel units moved from Gower Point Road elevation

slide-6
SLIDE 6

Response to ADP- Issued for December 2013 & February 2014

The George Hotel & Residences Gibsons BC

New roof plan showing stepped roof and 5 storey landscaped roof deck on GP Road Stepped roof line Landscaped roof deck & 5 storeys on GP Road

slide-7
SLIDE 7

Response to ADP- Issued for December 2013 & February 2014

The George Hotel & Residences Gibsons BC

Post ADP submission with 4 hotel units occupying the space Original submission showing Storage and double height space

slide-8
SLIDE 8

Response to Geotechnical #1- September 2014

The George Hotel & Residences Gibsons BC

Height:

  • September 2013 Requested Building Height

Residential: 100’-2-1/2” (96’-2 ½”) Hotel: 124’-4” (120’-4”)

  • December 2013 & February 2014 Revised requested building massing in response to ADP

Residential: 100’-2-1/2” (96’-2 ½”) Hotel: 124’-4” (120’-4”)

  • September 2014 Revised requested building height based on June 2014 Horizon Report

Residential: 100’-5” Hotel: 124’-4” (121’-11”)

Key Changes: Flood construction level, parkade spot elevations to respond to Geotechnical report June 2014, revised building heights as a result of

raised FCL

slide-9
SLIDE 9

Response to Geotechnical #1- September 2014

The George Hotel & Residences Gibsons BC

  • Raised sea walk

from 12.70’ to 17.48’ to accommodate FCL ( + 4.78’)

  • Re-adjusted

parkade elevations to accommodate geotechnical investigations (various heights)

slide-10
SLIDE 10

Response to Geotechnical #1- September 2014

The George Hotel & Residences Gibsons BC

In order to keep building height down and accommodate a raise in the FCL from 12.7’ to 17.48’, we had to compress P1 and P2, adjust ground plane and reduce some floor to floor heights in parking and level 1 and 2 28.48’ Original 22.96’

slide-11
SLIDE 11

Response to Geotechnical #1- September 2014

The George Hotel & Residences Gibsons BC

  • Original ground

floor = 34.5’

  • New ground floor

reduced to 37.7’

  • 1’8” taken out of

level 1 and 2 to minimize building height for a net increase of approx. 1’7” of roofline to accommodate new below grade conditions and FCL 37.7’ Level 1 height Sept 2014 34.5’ Level 1 height Sept 2013

slide-12
SLIDE 12

Response to Geotechnical #2- May 2015

The George Hotel & Residences Gibsons BC

Height:

  • September 2013 Requested Building Height

Residential: 100’-2-1/2” (96’-2 ½”) Hotel: 124’-4” (120’-4”)

  • December 2013 & February 2014 Revised requested building massing in response to ADP

Residential: 100’-2-1/2” (96’-2 ½”) Hotel: 124’-4” (120’-4”)

  • September 2014 Revised requested building height based on June 2014 Horizon Report

Residential: 100’-5” Hotel: 124’-4” (121’-11”)

  • May 2015 Revised requested building height based on December 2014 Horizon Report

Residential: 103’-4” Hotel: 124’-4”

  • Height difference

Residential- Increase of 3’-1-1/2” feet from Sept 2013 Submittal Hotel – No net increase 0’-0” feet from Sept 2013 Submittal (4’0” increase of highest roof within the ‘ask’ envelope) Key Changes: Parkade spot elevations & building height in response to Geotechnical report # 2 December 2014 ( presented to COW May 2015)

slide-13
SLIDE 13

Response to Geotechnical #2- May 2015

The George Hotel & Residences Gibsons BC

The Town of Gibson’s tasked the design team to do further investigative work related to the sub surface conditions and aquifer

  • elevations. The work

performed by Horizon Engineering in December 2014 determined maximum lowest excavation level across the site for the design team to plan parkade and parkade levels.

slide-14
SLIDE 14

Response to Geotechnical #2- May 2015

The George Hotel & Residences Gibsons BC

The design team in response to raising the lowest level of excavation responded in taking flr to flr height out of P1 and P2, an additional 4”

  • ut of Level 1 and a

redesign of the parkade layout to respond to ground conditions. Net height increase

  • ver original highest

roof submission = 4’0”

  • ( no net increase within 124’4”

envelope height request

  • 8’0” total if we did not

redesign parking and take flr to flr height out)

12.75’ original P2 height 20.83’ new P2 height

Removed parking

slide-15
SLIDE 15

Response to Geotechnical #2- May 2015 Rendering

The George Hotel & Residences Gibsons BC

slide-16
SLIDE 16

Response to Geotechnical #2- May 2015 Geotechnical sub-surface investigation & maximum lowest excavation

The George Hotel & Residences Gibsons BC

Other key changes and how we responded:

  • Reassessment of lowest parkade elevations working with Geotechnical recommendations for

lowest excavation points.

  • Worked with the predominate slope of the land to minimize cut and fill and maintain

seawalk elevation height to respond to climate change and ocean rise.

  • Re-planned parkade entrances, plaza height, height of buildings and transition from public

spaces to plaza.

  • Reviewed and confirmed statistics, height, floor elevations and parking count.
  • Defined existing road elevation interface to property.
  • Improved urban design at street edge to respond to road elevation, drop off entry sequence,

provision of stepped landscape and ‘finer grained’ details at street level.

slide-17
SLIDE 17

Conclusion

The George Hotel & Residences Gibsons BC

Summary

  • Reduced massing height on Gower Point Road from 6 to 5 storeys
  • Reduced floor to floor height above grade and below grade to minimize increase in height

due to FCL and lowest excavation level for June 2014 Geotechnical Report #1

  • Additional changes to parkade design and reduction in height of building to accommodate

new lowest excavation level for December 2014 Geotechnical Report #2

  • Net reduction of height for buildings from original submission while raising the building due

to ground conditions = 4’-0” (net increase of 4’-0” over original submission height)

  • Hotel has NO NET increase and is 124’-4” Residential has 3’1-1/2” increase all working

within the narrow parameters of raising the lowest flood construction level The design team has worked to respond to the below grade conditions, minimize height where possible and maintain the technical and market standards that dictate flr to flr heights for buildings of this type.

slide-18
SLIDE 18

The George Hotel & Residences Gibsons BC

Thank You