TAC/CAC, TPO Project Update February 2016 PRESENTATION FOOTERT - - PowerPoint PPT Presentation

tac cac tpo project update february 2016
SMART_READER_LITE
LIVE PREVIEW

TAC/CAC, TPO Project Update February 2016 PRESENTATION FOOTERT - - PowerPoint PPT Presentation

Multimodal Corridor Planning & Engineering Analysis Project A1A MULTIMODAL CORRIDOR PLANNING AND ENGINEERING ANALYSIS Florida Department of Transportation TAC/CAC, TPO Project Update February 2016 PRESENTATION FOOTERT Multimodal Corridor


slide-1
SLIDE 1

Multimodal Corridor Planning & Engineering Analysis Project

PRESENTATION FOOTERT

TAC/CAC, TPO Project Update February 2016

A1A MULTIMODAL CORRIDOR PLANNING AND ENGINEERING ANALYSIS Florida Department of Transportation

slide-2
SLIDE 2

Multimodal Corridor Planning & Engineering Analysis Project

Meeting Agenda – What We Plan To Discuss

– Project Background – New Analysis – RRR Projects – Improvement Concepts – Status – Questions and Comments

slide-3
SLIDE 3

Multimodal Corridor Planning & Engineering Analysis Project

Project Background

– Initiated by Space Coast TPO & Action Team – Addresses multimodal transportation along SR A1A – From the Pineda Causeway (SR 404) to SR 528 in Cape Canaveral – Goal: Develop Implementation Plan

slide-4
SLIDE 4

Multimodal Corridor Planning & Engineering Analysis Project

Project Constraints & Opportunities

– Most improvements are within the existing right-of-way

  • Limited by narrow road and lack of extra space

– Several improvements to be implemented by

  • thers
  • Land use changes
  • Utility improvements
  • Wayfinding signage
slide-5
SLIDE 5

Multimodal Corridor Planning & Engineering Analysis Project

Existing Conditions

  • Data Collection
  • Previous Studies
  • Identify Right-of-Way

(based on maps) Identification of Needs

  • Transportation Needs

Assessment

  • Stakeholder

Interviews

  • Public Charrette

Planning Phase - Visioning Planning Phase – Engineering Analysis Project Development Phase for Selected Improvements Implementation

Depending on the Project, Next Steps could include:

  • Drainage

Analysis

  • Environmental

Analysis

  • Design
  • Right-of-Way

Engineering Analysis

  • Identification of Range
  • f Improvements
  • Concept Plans
  • Cost Estimates
  • Evaluation Criteria
  • Comparative Analysis
  • Public Workshop
  • A1A Action Team

Mtg. Prepare Prioritized Project List

  • Conceptual Design

Plans

  • Refined Cost

Estimates

Public Meeting

Final Presentations

  • Stakeholders,
  • TPO
  • FDOT

Current Steps

slide-6
SLIDE 6

Multimodal Corridor Planning & Engineering Analysis Project

Wayfinding

– Implementation Guide

  • Resolutions
  • Examples
  • Potential Destinations
  • Recommended steps

– Cities to design & implement – FDOT to review

slide-7
SLIDE 7

Multimodal Corridor Planning & Engineering Analysis Project

Utilities

– Implementation Guide

  • Recommendations on Phased

Approach

  • Locations
  • Types of Changes
  • Potential Destinations
  • Recommended steps

– Cities to design & implement – FDOT to review

slide-8
SLIDE 8

Multimodal Corridor Planning & Engineering Analysis Project

Right of Way

– New Information – Most is similar to previous assumed ROW – Area near the Air Force Base is different

slide-9
SLIDE 9

Multimodal Corridor Planning & Engineering Analysis Project

New Pedestrian Analysis

– North end of One-Way Pairs – Results: Crosswalk included in RRR

slide-10
SLIDE 10

Multimodal Corridor Planning & Engineering Analysis Project

Recommendations – South to North

– Applications through TPO

  • Some sent by Cocoa Beach
  • Some sent by Cape Canaveral

– To be Prioritized / Funded, then Designed

RRR Project Streetscaping Sidewalk Sidewalk Sidewalk Modify Intersection Modify Intersection Median, Urban Profile Path

slide-11
SLIDE 11

Multimodal Corridor Planning & Engineering Analysis Project

Patrick Air Force Base

– Right-of-Way is significant concern – Improvements must be driven by the AFB. NEED SPONSOR

Right-of-Way Recommended Path

slide-12
SLIDE 12

Multimodal Corridor Planning & Engineering Analysis Project

RRR Project Details

– Public Meeting November 19 – Purpose is Resurfacing – Construction 2016

RRR Project Rec: Streetscaping Rec: Sidewalk – One-Way Pairs

slide-13
SLIDE 13

Multimodal Corridor Planning & Engineering Analysis Project

RRR Project Changes

– Based on additional funds from TPO and City – Sidewalk – fill in all gaps – Bulb outs – No Landscaping - TBD by City

RRR Project Rec: Streetscaping Rec: Sidewalk – One-Way Pairs

slide-14
SLIDE 14

Multimodal Corridor Planning & Engineering Analysis Project

Recommendations – Streetscaping / Drainage

slide-15
SLIDE 15

Multimodal Corridor Planning & Engineering Analysis Project

RRR Project Rec: Streetscaping Rec: Sidewalk – One-Way Pairs

60% Plans – Subject To Change 60% Plans – Subject To Change

slide-16
SLIDE 16

Multimodal Corridor Planning & Engineering Analysis Project

60% Plans – Subject To Change

slide-17
SLIDE 17

Multimodal Corridor Planning & Engineering Analysis Project

60% Plans – Subject To Change

slide-18
SLIDE 18

Multimodal Corridor Planning & Engineering Analysis Project

– Consider modifications to existing curbs?

  • More sidewalk space
  • Significant design

complexities

– Extend curb and gutter?

  • Between N 1st St and N 4th

St?

  • North beyond N 4th St?
  • South beyond existing

curb?

– Landscaping & Streetscaping?

Considerations after RRR is accomplished

slide-19
SLIDE 19

Multimodal Corridor Planning & Engineering Analysis Project

Recommendation: Sidewalk between Sunflower St and SR 520

Path RRR Project Streetscaping Sidewalk Sidewalk Sidewalk Modify Intersection Modify Intersection Median, Urban Profile

West Side – 8’ East Side – Existing (Summer 2015)

slide-20
SLIDE 20

Multimodal Corridor Planning & Engineering Analysis Project

Recommendation: SR 520 Intersection

RRR Project Streetscaping Sidewalk Sidewalk Sidewalk Modify Intersection Modify Intersection Median, Urban Profile Path

slide-21
SLIDE 21

Multimodal Corridor Planning & Engineering Analysis Project

RRR Project Streetscaping Sidewalk Sidewalk Sidewalk Modify Intersection Modify Intersection Median, Urban Profile

SR 520 Intersection – Status:

– Too many complexities to add to SR 520 RRR – Consider as stand alone improvement – Scope for Design is under way

Path

slide-22
SLIDE 22

Multimodal Corridor Planning & Engineering Analysis Project

Recommendation: Sidewalk between SR 520 and International / Atlantic

RRR Project Streetscaping Sidewalk Sidewalk Sidewalk Modify Intersection Modify Intersection Median, Urban Profile

West Side – 8’ East Side – 8’

Path

slide-23
SLIDE 23

Multimodal Corridor Planning & Engineering Analysis Project

RRR Project Streetscaping Sidewalk Sidewalk Sidewalk Modify Intersection Modify Intersection Median, Urban Profile

Sidewalk - SR 520 to Atlantic Ave – Status:

– Consider as stand alone improvement – Scope for Design is under way

Path

slide-24
SLIDE 24

Multimodal Corridor Planning & Engineering Analysis Project

RRR Project Streetscaping Sidewalk Sidewalk Sidewalk Modify Intersection Modify Intersection Median, Urban Profile

Recommendation: International / Atlantic Realignment

Path

slide-25
SLIDE 25

Multimodal Corridor Planning & Engineering Analysis Project

Recommendation: Boulevard from International / Atlantic to George King

RRR Project Streetscaping Sidewalk Sidewalk Sidewalk Modify Intersection Modify Intersection Median, Urban Profile

SW (West Side) – 8’ SW (East Side) – 8’ Median – 22’ or 19.5’ Bike Lane – 4’

Path

slide-26
SLIDE 26

Multimodal Corridor Planning & Engineering Analysis Project

RRR Project Streetscaping Sidewalk Sidewalk Sidewalk Modify Intersection Modify Intersection Median, Urban Profile

International Drive and Boulevard Improvements – Status:

– Will require additional coordination, analysis, and drainage considerations. – Being considered to move into design – Will not require a PD&E

Path

slide-27
SLIDE 27

Multimodal Corridor Planning & Engineering Analysis Project

Path RRR Project Streetscaping Sidewalk Sidewalk Sidewalk Modify Intersection Modify Intersection Median, Urban Profile

What’s The Status?

– Path in front of PAFB – working on agreement – Sidewalks in One-Way Pairs – in RRR – Streetscaping Projects Downtown Coca Beach – some elements in RRR – SR 520 - prioritized, scope is complete – International Drive Intersection – prioritized, scope is in development – Cape Canaveral median / Urban Profile – prioritized, scope is in development (PD&E not needed)

slide-28
SLIDE 28

Multimodal Corridor Planning & Engineering Analysis Project

Project Contacts

– Project Manager: Todd Davis at todd.davis@dot.state.fl.us or at 386- 943-5422 – Planning and Corridor Development Manager: Heather Garcia at heather.garcia@dot.state.fl.us or 386-943-5077 Check out the project website at www.actiona1a.com