Sydney Football Stadium Redevelopment Community Consultative Committee Meeting 8 23 September 2019 Agenda 1. Welcome, introductions and apologies Margaret Harvie 2. Declarations of pecuniary and other interests All 3. Report on


  1. Sydney Football Stadium Redevelopment Community Consultative Committee – Meeting 8 23 September 2019

  2. Agenda 1. Welcome, introductions and apologies – Margaret Harvie 2. Declarations of pecuniary and other interests – All 3. Report on Actions from last meeting – Tom Gellibrand 4. Project Update Construction – Tom Gellibrand 5. Response to Submissions – Tom Kennedy 6. Project Update Demolition – Angus Morten 7. Correspondences directed to the CCC/Chairperson – Marg a ret Harvie 8. What we are hearing from the community - All 9. Next meeting – Margie Harvey 10. Final questions - All

  3. Actions from the previous meeting • Update on communication with the Disability Council of NSW and the Australian Human Rights Commission. • Status of consultation with the SGSA.

  4. Project Update – Stage 2 Construction Contractor • Multiplex and John Holland continuing to participate in competitive tender process. • Weekly interactives are taking place at the tenderers request. • Tender process will conclude in October 2019. • Contract award is expected in December 2019.

  5. Response to Submissions • 84 submissions received • 12 submissions from NSW and Commonwealth agencies • 3 submissions from local councils • 69 submissions from community organisations, general public and non-Government stakeholders

  6. CCC Feedback • Driver Avenue Stairs • Overshadowing of Moore Park and Kippax Lake • Pedestrian access between Moore Park Road and Driver Avenue • Lower Roof • Parking • Heritage

  7. Driver Avenue Stairs

  8. Overshadowing 9am 10am

  9. Pedestrian Access

  10. Roof Design

  11. Transport

  12. Heritage

  13. Project Update – Stage 1 Demolition • Total demolition is approximately 80% complete • Demolition is near competition at the former Waratahs, Roosters and Sheridan buildings • Demolition at the Indoor Cricket Centre commenced in early September with internal strip out. Hard demolition works to commence from early October • Stormwater diversion works to take place later this year to relocate a Sydney Water asset in readiness for construction • The site continues to be cleared of residual structures and footings

  14. Project Update – Stage 1 Demolition Community Complaints Register to August 2019 • One complaint received about high levels of dust on 7 September during weekend of wind gusts in excess of 100km/h. • Lendlease implemented the following mitigation measures to supress the dust: • A water ring main was installed around site to provide water points to manage dust suppression around site • Static water sprinklers were set at strategic locations to suppress dust at each workface • Specific demolition plant was fitted with pipework designed to disperse water at the machine attachment location directly at the point of demolition • Water tankers were also utilised on site to manage haul roads and general areas which are not currently under demolition

  15. Next meeting • Next meeting proposed for Wednesday, 13 November or Wednesday, 4 December

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.