Sydney Football Stadium Redevelopment Community Consultative - - PowerPoint PPT Presentation

sydney football stadium redevelopment
SMART_READER_LITE
LIVE PREVIEW

Sydney Football Stadium Redevelopment Community Consultative - - PowerPoint PPT Presentation

Sydney Football Stadium Redevelopment Community Consultative Committee Meeting 8 23 September 2019 Agenda 1. Welcome, introductions and apologies Margaret Harvie 2. Declarations of pecuniary and other interests All 3. Report on


slide-1
SLIDE 1

Sydney Football Stadium Redevelopment

Community Consultative Committee – Meeting 8 23 September 2019

slide-2
SLIDE 2

Agenda

  • 1. Welcome, introductions and apologies – Margaret Harvie
  • 2. Declarations of pecuniary and other interests – All
  • 3. Report on Actions from last meeting – Tom Gellibrand
  • 4. Project Update Construction – Tom Gellibrand
  • 5. Response to Submissions – Tom Kennedy
  • 6. Project Update Demolition – Angus Morten
  • 7. Correspondences directed to the CCC/Chairperson – Margaret

Harvie

  • 8. What we are hearing from the community - All
  • 9. Next meeting – Margie Harvey
  • 10. Final questions - All
slide-3
SLIDE 3

Actions from the previous meeting

  • Update on communication with the Disability Council of NSW and the Australian Human Rights

Commission.

  • Status of consultation with the SGSA.
slide-4
SLIDE 4

Project Update – Stage 2 Construction Contractor

  • Multiplex and John Holland continuing to participate in competitive tender process.
  • Weekly interactives are taking place at the tenderers request.
  • Tender process will conclude in October 2019.
  • Contract award is expected in December 2019.
slide-5
SLIDE 5

Response to Submissions

  • 84 submissions received
  • 12 submissions from NSW and Commonwealth agencies
  • 3 submissions from local councils
  • 69 submissions from community organisations, general public and non-Government

stakeholders

slide-6
SLIDE 6

CCC Feedback

  • Driver Avenue Stairs
  • Overshadowing of Moore Park and Kippax Lake
  • Pedestrian access between Moore Park Road and Driver Avenue
  • Lower Roof
  • Parking
  • Heritage
slide-7
SLIDE 7

Driver Avenue Stairs

slide-8
SLIDE 8

Overshadowing

9am 10am

slide-9
SLIDE 9

Pedestrian Access

slide-10
SLIDE 10

Roof Design

slide-11
SLIDE 11

Transport

slide-12
SLIDE 12

Heritage

slide-13
SLIDE 13

Project Update – Stage 1 Demolition

  • Total demolition is approximately 80% complete
  • Demolition is near competition at the former Waratahs, Roosters and Sheridan buildings
  • Demolition at the Indoor Cricket Centre commenced in early September with internal strip out.

Hard demolition works to commence from early October

  • Stormwater diversion works to take place later this year to relocate a Sydney Water asset in

readiness for construction

  • The site continues to be cleared of residual structures and footings
slide-14
SLIDE 14

Project Update – Stage 1 Demolition Community Complaints

  • One complaint received about high levels of dust on 7

September during weekend of wind gusts in excess of 100km/h.

  • Lendlease implemented the following mitigation

measures to supress the dust:

  • A water ring main was installed around site to

provide water points to manage dust suppression around site

  • Static water sprinklers were set at strategic

locations to suppress dust at each workface

  • Specific demolition plant was fitted with pipework

designed to disperse water at the machine attachment location directly at the point of demolition

  • Water tankers were also utilised on site to

manage haul roads and general areas which are not currently under demolition

Register to August 2019

slide-15
SLIDE 15

Next meeting

  • Next meeting proposed for Wednesday, 13 November or Wednesday, 4 December