SW Capitol Hwy: Multnomah Village West Portland 95% Design Update - - PowerPoint PPT Presentation

sw capitol hwy multnomah village west portland 95 design
SMART_READER_LITE
LIVE PREVIEW

SW Capitol Hwy: Multnomah Village West Portland 95% Design Update - - PowerPoint PPT Presentation

SW Capitol Hwy: Multnomah Village West Portland 95% Design Update Capitol Highway Subcommittee December 4, 2019 Agenda 6:30pm Welcome & Introductions Chris Lyons (MNA), Steve Szigethy (PBOT), Fowler Team, All 6:45pm Major Project


slide-1
SLIDE 1

Capitol Highway Subcommittee December 4, 2019

SW Capitol Hwy: Multnomah Village – West Portland 95% Design Update

slide-2
SLIDE 2

Agenda

6:30pm Welcome & Introductions Chris Lyons (MNA), Steve Szigethy (PBOT), Fowler Team, All 6:45pm Major Project Updates Steve Szigethy 7:00pm 95% Plans - Overview and Discussion Steve Szigethy, All Key Topics:

  • Retaining walls and railings
  • Bike Lane, Sidewalk, and Multi-Use Path
  • Stormwater
  • Trees and landscaping
  • Public art

8:10pm Project Construction - Updates and Discussion Steve Szigethy, Fowler Team, All Key Topics:

  • Schedule
  • Sequencing/Phasing
  • Public Involvement

8:30pm Adjourn

slide-3
SLIDE 3

SW Capitol Hwy: Multnomah Village – West Portland Project

slide-4
SLIDE 4
  • All walls are cast-in-place concrete
  • Multnomah South stormwater facility

reshaped

  • Spot narrowing of improvements on

Capitol Hwy

  • Longitudinal delineation between

east side peds & bikes

  • Multnomah Blvd ped/bike

improvements defined

  • Right-of-way certification maps
  • Additional detail across all elements

Refinements in 95% Design:

slide-5
SLIDE 5
  • Smaller excavation area
  • Less impactful to properties
  • Aesthetic preference of many

in neighborhood

  • Historical reference to

neighborhood rockery walls Cast-in-Place Concrete Walls

slide-6
SLIDE 6

Multnomah South Stormwater Detention Basin

  • Smaller footprint
  • Saves 4 large

Doug firs

slide-7
SLIDE 7

Spot Narrowing of Capitol Highway Improvements 3’

slide-8
SLIDE 8

Longitudinal Delineation of East Side Ped and Bike Ways Where No Planter Strip is Proposed

slide-9
SLIDE 9

SW Multnomah Blvd Ped/Bike Improvements

  • 10’ concrete multi-use path on north side for 300’ west of 40th

Ave

  • Roadway-level protected bikeway/walkway on both sides

between 40th & 45th Aves

  • Reconstruction of all 4 corners of Multnomah/40th
slide-10
SLIDE 10

Right-of-Way Certification Maps

  • Shows all temporary & permanent easements needed to

construct and maintain the project.

slide-11
SLIDE 11

Visual Preference Survey: Influence on Design

Random rounded wall pattern Black powder-coated square tube rail Various approved trees Black bike lane Stamped concrete-style furnishing zone Various approved shrubs

slide-12
SLIDE 12

Construction Team

  • Owner / Lead Bureau:
  • Bureau Partners:
  • Construction Manager / General Contractor:
  • Construction Public Involvement:
  • Contracting Equity Consultant:
slide-13
SLIDE 13

Current Picture of Construction Sequencing & Schedule

  • CM/GC Pre-Con Deliverables

Jan-Feb 2020

  • Construction Open House

January 30, 2020

  • Early Work Packages

February-March 2020

  • Final Plans & Price

March 2020

  • Major Construction Starts

March-April 2020

  • Substantial Completion

Summer 2021

slide-14
SLIDE 14

Public Involvement Before/During Construction

  • Project Newsletter #4 – January 2020
  • Construction Open House – Thurs., Jan. 30, 2020

– Multnomah Arts Center 6:00-8:30pm

  • Weekly/bi-weekly e-bulletins with maps
  • Residential doorhangers
  • Business outreach
  • Project newsletters at key milestones
  • CHS meetings and other group briefings
  • Lawn signs during construction
  • Tabling at events
  • Ongoing outreach and responsive support

– april@jla.us.com or 503-235-5881

slide-15
SLIDE 15

Agenda

6:30pm Welcome & Introductions Chris Lyons (MNA), Steve Szigethy (PBOT), Fowler Team, All 6:45pm Major Project Updates Steve Szigethy 7:00pm 95% Plans - Overview and Discussion Steve Szigethy, All Key Topics:

  • Retaining walls and railings
  • Bike Lane, Sidewalk, and Multi-Use Path
  • Stormwater
  • Trees and landscaping
  • Public art

8:10pm Project Construction - Updates and Discussion Steve Szigethy, Fowler Team, All Key Topics:

  • Schedule
  • Sequencing/Phasing
  • Public Involvement

8:30pm Adjourn

slide-16
SLIDE 16

Thank You!

Steve Szigethy, Capital Program Manager Portland Bureau of Transportation steve.szigethy@portlandoregon.gov 503.823.5117