Sunnybrook Exit (MP 13.45-14.17) Presenters: Tom Hamstra (ODOT) - - PowerPoint PPT Presentation
Sunnybrook Exit (MP 13.45-14.17) Presenters: Tom Hamstra (ODOT) - - PowerPoint PPT Presentation
MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 Sunnybrook Exit (MP 13.45-14.17) Presenters: Tom Hamstra (ODOT) Nate Schroeder (DKS) Nicholas Polenske (OBEC) Presentation Outline Project Overview Schedule Overview Traffic
Presentation Outline
- Project Overview
- Schedule Overview
- Traffic Control Staging/Phasing
– Detour Routes (Night Ramp Closures) – Traffic Shifts
- Vertical Clearance
MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 2
Project Overview
- Widen NB I-205 to accommodate an auxiliary lane from
the OR224 (Sunrise) entrance to the Sunnybrook exit
MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 3
Project Overview – Southern Limits
MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 4
Project Overview – Northern Limits
MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 5
Schedule Overview
- Bid open: 11/1/2018
- Stage I: 3/11/2019 – 5/30/2019
- Stage II, Phase 1: 5/30/2019 – 6/4/2019
- Stage II, Phase 2: 6/4/2019 – 6/11/2019
– Only two (2) consecutive nights
- Stage II, Phase 3: 6/11/2019 – 9/20/2019
- Stage III: 9/20/2019 – 10/8/2019
- Stage IV, Phase 1: 3/30/2020 – 4/15/2020
- Stage IV, Phase 2: 4/15/2020 – 5/7/2020
- Final Walkthrough: 5/22/2020
MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 6
Staging/Phasing Descriptions
- Stage I: Widen inside shoulder to permanent location
- Stage II, Phase 1: Restripe inside and center lane lines
- Stage II, Phase 2: Close Sunnybrook exit ramp and
Sunrise entrance ramp to restripe outside lane
- Stage II, Phase 3: Widen the outside shoulder to permanent
location
- Stage III: Reconstruct the Sunnybrook exit gore
- Stage IV, Phase 1: Grind and inlay the inside two lanes
- Stage IV, Phase 2: Close Sunnybrook exit ramp, Sunrise
entrance ramp, and OR212 entrance ramp to grind and inlay the outside two lanes, Sunnybrook exit ramp, and Sunrise entrance ramp
MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 7
Detour Routes
- Stage II, Phase 2 and Stage
IV, Phase 2 will require night closures of entrance and exit ramps
– Stage II will close the Sunnybrook/Sunnyside exit ramp and the Sunrise Expressway entrance ramp – Stage IV will close the same ramps and will also close the OR212 entrance ramp
MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 8
Stage II, Phase 2 Detour Route
MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 9
Stage IV, Phase 2 Detour Route
MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 10
Traffic Shifts
- Stage I will shift traffic ~5’
east of the existing alignment
- Stage II, Phase 3 will shift
traffic onto the newly constructed (Stage I) inside shoulder
- Stages with traffic shifts will
maintain 3-12’ lanes and 2’ shoulders (2’ shoulders only
- n side where work is
- ccurring to maximize work
zone)
MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 11
Vertical Clearance
- Two new cantilever sign
structures will be installed as part of the project – Both structures will be designed to have 19’ of vertical clearance
MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 12
Vertical Clearance – Continued
- Only the inside lane vertical
clearance under the OR224 structure (structure 09718) will be reduced as part of the project due to the parabolic curve of the soffit
- The clearance will still
maintain the minimum 17’-6”
– This clearance is measured at the edge of the inside shoulder
MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 13