Sunnybrook Exit (MP 13.45-14.17) Presenters: Tom Hamstra (ODOT) - - PowerPoint PPT Presentation

sunnybrook exit mp 13 45 14 17
SMART_READER_LITE
LIVE PREVIEW

Sunnybrook Exit (MP 13.45-14.17) Presenters: Tom Hamstra (ODOT) - - PowerPoint PPT Presentation

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 Sunnybrook Exit (MP 13.45-14.17) Presenters: Tom Hamstra (ODOT) Nate Schroeder (DKS) Nicholas Polenske (OBEC) Presentation Outline Project Overview Schedule Overview Traffic


slide-1
SLIDE 1

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit (MP 13.45-14.17)

Presenters: Tom Hamstra (ODOT) Nate Schroeder (DKS) Nicholas Polenske (OBEC)

slide-2
SLIDE 2

Presentation Outline

  • Project Overview
  • Schedule Overview
  • Traffic Control Staging/Phasing

– Detour Routes (Night Ramp Closures) – Traffic Shifts

  • Vertical Clearance

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 2

slide-3
SLIDE 3

Project Overview

  • Widen NB I-205 to accommodate an auxiliary lane from

the OR224 (Sunrise) entrance to the Sunnybrook exit

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 3

slide-4
SLIDE 4

Project Overview – Southern Limits

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 4

slide-5
SLIDE 5

Project Overview – Northern Limits

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 5

slide-6
SLIDE 6

Schedule Overview

  • Bid open: 11/1/2018
  • Stage I: 3/11/2019 – 5/30/2019
  • Stage II, Phase 1: 5/30/2019 – 6/4/2019
  • Stage II, Phase 2: 6/4/2019 – 6/11/2019

– Only two (2) consecutive nights

  • Stage II, Phase 3: 6/11/2019 – 9/20/2019
  • Stage III: 9/20/2019 – 10/8/2019
  • Stage IV, Phase 1: 3/30/2020 – 4/15/2020
  • Stage IV, Phase 2: 4/15/2020 – 5/7/2020
  • Final Walkthrough: 5/22/2020

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 6

slide-7
SLIDE 7

Staging/Phasing Descriptions

  • Stage I: Widen inside shoulder to permanent location
  • Stage II, Phase 1: Restripe inside and center lane lines
  • Stage II, Phase 2: Close Sunnybrook exit ramp and

Sunrise entrance ramp to restripe outside lane

  • Stage II, Phase 3: Widen the outside shoulder to permanent

location

  • Stage III: Reconstruct the Sunnybrook exit gore
  • Stage IV, Phase 1: Grind and inlay the inside two lanes
  • Stage IV, Phase 2: Close Sunnybrook exit ramp, Sunrise

entrance ramp, and OR212 entrance ramp to grind and inlay the outside two lanes, Sunnybrook exit ramp, and Sunrise entrance ramp

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 7

slide-8
SLIDE 8

Detour Routes

  • Stage II, Phase 2 and Stage

IV, Phase 2 will require night closures of entrance and exit ramps

– Stage II will close the Sunnybrook/Sunnyside exit ramp and the Sunrise Expressway entrance ramp – Stage IV will close the same ramps and will also close the OR212 entrance ramp

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 8

slide-9
SLIDE 9

Stage II, Phase 2 Detour Route

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 9

slide-10
SLIDE 10

Stage IV, Phase 2 Detour Route

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 10

slide-11
SLIDE 11

Traffic Shifts

  • Stage I will shift traffic ~5’

east of the existing alignment

  • Stage II, Phase 3 will shift

traffic onto the newly constructed (Stage I) inside shoulder

  • Stages with traffic shifts will

maintain 3-12’ lanes and 2’ shoulders (2’ shoulders only

  • n side where work is
  • ccurring to maximize work

zone)

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 11

slide-12
SLIDE 12

Vertical Clearance

  • Two new cantilever sign

structures will be installed as part of the project – Both structures will be designed to have 19’ of vertical clearance

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 12

slide-13
SLIDE 13

Vertical Clearance – Continued

  • Only the inside lane vertical

clearance under the OR224 structure (structure 09718) will be reduced as part of the project due to the parabolic curve of the soffit

  • The clearance will still

maintain the minimum 17’-6”

– This clearance is measured at the edge of the inside shoulder

MAC Meeting 5/15/2018 K19721 I-205 NB: MP 13.3 – Sunnybrook Exit 13

slide-14
SLIDE 14

Questions?