Summer 2012 In Site
By Kevin Greene, Inga Hall, Nicola Ellis, Laura Ludlow & Lee Forsyth
Welcome to the Summer 2012 edition of In Site. This edition covers the following topics: NEC3 issues for 2012; Recent natural justice cases, the use of adjudicator initiative and adjudicator “forum shopping”; Hot topics in the world of PPP/PFI as they impact on the construction and engineering sector; and a case update covering the scope of legal professional privilege, the developing law on severability of adjudicators’ decisions, and implied terms. For more information on any of these articles, or on any other issue relating to construction and engineering law, please contact any of the authors or your usual K&L Gates’ contact.
NEC issues for 2012: Olympics, heavy rain and challenging payment
Olympic delays With recent reports that the Olympic Park has successfully been delivered on time and within budget, this is good press for NEC3, being the contract of choice for the Olympic venues. The bad news for other construction sites in the capital is the significant disruption expected to the roads during the Olympics. The road closures and heavy traffic expected in the lead-up to, and during, the Olympics are likely to result in delays in goods, materials and equipment being delivered to construction sites. It is difficult to predict the extent of these delays. Some employers and contractors will have agreed terms in their contracts to deal with this, or perhaps may have incorporated such anticipated delays in their programme. Where this is not the case, who bears the risk? Under NEC3, unless a compensation event occurs as set out in clause 60.1, it is likely that the contractor will bear the risk and resulting cost of any Olympic related delays. A contractor may say that the delays fall within the category of “prevention events” dealt with in clause 60.1(19), but in order to do so successfully, must jump the 3 hurdles in clause 19, namely demonstrate (i) that the “event” (and query whether the event is the congestion or the Olympics themselves) has either stopped the contractor from completing by the completion date or completing the works at all, (ii) that the event was one that neither party could prevent, and (iii) that it would have been unreasonable for an experienced contractor, at the contract date, to have allowed for it. These are difficult hurdles to overcome, and an employer may say that an experienced contractor would have foreseen delays arising from transport difficulties during the Olympics, even if a contract was entered into before the publication of the Olympic Route Network (published in July 2010, and setting out road closures and restrictions). An issue between parties could well be whether, even from July 2005 when it was announced that London would host the 2012 Olympics, it is arguable that an experienced contractor would foresee the likelihood of disruption. In any event, the contractor should mitigate any delays and losses arising. It should give an early warning as soon as possible of anticipated delays, and should consider, with the employer, whether steps such as re-programming deliveries and activities (possibly outside normal working hours),
Summer 2012
Construction and Engineering