Stonehedge Stormwater Improvements South Burlington, VT June 18, - - PowerPoint PPT Presentation

stonehedge stormwater improvements
SMART_READER_LITE
LIVE PREVIEW

Stonehedge Stormwater Improvements South Burlington, VT June 18, - - PowerPoint PPT Presentation

Stonehedge Stormwater Improvements South Burlington, VT June 18, 2013 Stonehedge Outline Project Objectives Background Financing Existing Stormwater System Proposed Improvements Next Steps and Schedule Page 1 Stonehedge


slide-1
SLIDE 1

Stonehedge Stormwater Improvements

South Burlington, VT

June 18, 2013

slide-2
SLIDE 2

Outline

  • Project Objectives
  • Background
  • Financing
  • Existing Stormwater System
  • Proposed Improvements
  • Next Steps and Schedule

Stonehedge

Page 1

slide-3
SLIDE 3

Project Objectives

  • Add stormwater treatment and control prior to

discharging to Potash Brook Will address State stormwater permit issues to facilitate transfer of system to the City

  • Improve the overall stormwater collection and

conveyance system as part of effort to provide treatment and control Will address some of the existing drainage/flooding problems

Stonehedge

Page 2

slide-4
SLIDE 4

Background

  • Stormwater system installed in phases beginning in 1970s
  • No stormwater treatment or control
  • Flooding and nuisance drainage problems now common
  • Condo Associations (and not City Stormwater Utility)

currently responsible for stormwater system

  • State stormwater permit issues

Original stormwater permit expired in 1985 Renewal not possible because discharge to “Stormwater Impaired” streams (Potash to the north, Bartlett to the South) Renewal process: State’s Engineering Feasibility Analysis to develop a “best-fit” solution

  • Previous conceptual study
  • Grant from the Corps of Engineers

for current project

Stonehedge

Page 3

slide-5
SLIDE 5

Financing (1/3)

Stonehedge

Page 4

  • Engineering Costs: ~$120,000
  • Construction: ~$530,000 (working estimate)
  • City has a project agreement with Army

Corps of Engineers (ACOE). ACOE will be responsible for 65% of project costs ($422,500).

  • South Burlington Stormwater Utility and

Stonehedge residents responsible for remaining 35% of project costs ($227,500).

slide-6
SLIDE 6

Financing (2/3)

Stonehedge

Page 5

  • The City of South Burlington owns 25% of the

impervious area that is covered by the State permit and will pay 25% of the remaining project costs ($56,875).

  • The Stonehedge homeowner associations own

75% of the impervious area that is covered by the State permits and will pay 75% of the remaining project costs ($170,625).

  • Public vote in March 2011 authorized a

Stormwater Special Assessment District.

slide-7
SLIDE 7

Financing (3/3)

Stonehedge

Page 6

$2,413 $845 Estimated Cost/Unit (202 units) $650,000 $650,000 Total Project Cost $162,500 $56,875 City Share of Project Cost $487,500 $170,625 Stonehedge Share of Project Cost $- $422,500 ACOE Share of Project Cost Without ACOE Funding With ACOE Funding

Construction costs are working estimates that will be refined as the design is advanced.

slide-8
SLIDE 8

Existing Stormwater System: Overall

Stonehedge

Page 7

  • Catch basins/pipes
  • Open swales
  • Off-site runoff
  • No treatment or

control

slide-9
SLIDE 9

Existing Stormwater System: Photos

Swale and Culvert

Stonehedge

Page 8

Roadside Ditch Cedar Glen Road Catch Basin Potash Brook Existing Swale

slide-10
SLIDE 10

Proposed Improvements: Overview

  • Refinement of L&D Conceptual Plan
  • Primary Components:

Improved capture of stormwater on Cedar Glen Drive Improved interception of off-site water Expanded closed-pipe system Three new bioretention areas New stormwater pond

Stonehedge

Page 9

slide-11
SLIDE 11

Stonehedge

Page 10

Proposed Improvements: Previous Concept

slide-12
SLIDE 12

Proposed Improvements: Current Site Plan

Stonehedge

Page 11

slide-13
SLIDE 13

Stonehedge

Page 12

Proposed Improvements: Bioretention

slide-14
SLIDE 14

Stonehedge

Proposed Improvements: Pond Site Plan

Page 13

slide-15
SLIDE 15

Stonehedge

Page 14

Proposed Improvements: Pond Profile

slide-16
SLIDE 16

Next Steps and Schedule

  • Complete design (late 2013)
  • Complete permitting (early 2014)
  • Select Contractor (Spring 2014)
  • Construction (Summer 2014)
  • Schedule dependent on Army Corps of Engineers

Stonehedge

Page 15