STEPS TO COMPLETING THE SRF LOAN PROCESS
April 2015
Massachusetts Department of Environmental Protection
2015 Borrower Presentation
1
STEPS TO COMPLETING THE SRF LOAN PROCESS April 2015 Massachusetts - - PowerPoint PPT Presentation
STEPS TO COMPLETING THE SRF LOAN PROCESS April 2015 Massachusetts Department of Environmental Protection 2015 Borrower Presentation 1 Sue Perez Steven McCurdy Nate Keenan Joe Delaney Heather Saxelby ODonnell 2015 Borrower Presentation
April 2015
2015 Borrower Presentation
1
2015 Borrower Presentation
Sue Perez Nate Keenan Heather Saxelby O’Donnell Steven McCurdy Joe Delaney
2
2015 Borrower Presentation
3
2015 Borrower Presentation
Intended Use Plan - Done
4
2015 Borrower Presentation
5
2015 Borrower Presentation
6
1. Application Information - Authorized Representative, Loan Appropriation, etc. 2. Project Requirements - Plans and Specifications, Costs, Schedule, etc. 3. Supplemental Requirements - Permits, Planning, Professional Service Agreement, etc.
2015 Borrower Presentation
7
conditions
2015 Borrower Presentation
8
2015 Borrower Presentation
9
comply with the tax code as it applies to tax exempt bonds
verification form before permanent financing
instructions
2015 Borrower Presentation
10
that the local vote is legal
MCWT for interim and permanent loan
2015 Borrower Presentation
11
approves Disadvantaged Business Enterprise (DBE) participation
(Environmental Justice communities and renewable energy projects), contracts must be awarded by April 30, 2016 to be eligible.
2015 Borrower Presentation
12
2015 Borrower Presentation
13
As with the Project Approval Certificate, the Financing Agreement is voted at a Board of Trustees meeting. The Financing Agreement:
Once the Financing Agreement is approved, the questionnaire is returned and the green light is received, the Borrower will receive a package containing:
2015 Borrower Presentation
14
until the Trust goes to market for permanent financing.
2015 Borrower Presentation
15
2015 Borrower Presentation
*Rate calculated at time of bond sale, estimated between 2.4-2.9% ** To be determined at time of bond sale to offset costs
16
monthly
forwarded to MassDEP with the appropriate documentation (receipts, invoices, etc.)
available the next day
2015 Borrower Presentation
17
2015 Borrower Presentation Loan Number and MassDEP Project Number Total Interim Loan Amount Disbursement Number Approval Signature from MassDEP Payment Request Amount Signed and dated by Borrower
18
2015 Borrower Presentation
19
2015 Borrower Presentation
20
your community?
the community would save $738,144 over the life of the loan (using current market rates)
subsidy
2015 Borrower Presentation
21
liquid asphalt and portland cement in CIP concrete
the Clean Water program – both also continue to be applicable to Drinking Water program
provide cost and effectiveness certifications.
2015 Borrower Presentation
22
used for the construction, or repair of a public water system or treatment works unless all of the iron and steel products used in the project are produced in the United States.
(> 50% by cost) of iron or steel: lined or unlined pipes and fittings, manhole covers and other municipal castings, hydrants, tanks, flanges, pipe clamps and restraints, valves, structural steel, reinforced precast concrete, and construction materials.
2015 Borrower Presentation
23
source projects
electrical equipment among others
produced in the US in sufficient quantity or quality
than 5% of the material cost with no 1 item totaling 1% of the cost.
2015 Borrower Presentation
24
2015 Borrower Presentation
25
2015 Borrower Presentation
26