status of the crab cavity effort may 18 2016 on behalf of
play

Status of the Crab Cavity Effort May 18, 2016 On behalf of WP4 - PowerPoint PPT Presentation

Status of the Crab Cavity Effort May 18, 2016 On behalf of WP4 Joint USLARP CM26/Hi-Lumi Meeting, SLAC Outline Update on the Cavity + CM production SPS Test preparation RFD DQW Cost & Schedule Review (New Baseline) CM Review, Nov


  1. Status of the Crab Cavity Effort May 18, 2016 On behalf of WP4 Joint USLARP CM26/Hi-Lumi Meeting, SLAC

  2. Outline • Update on the Cavity + CM production • SPS Test preparation RFD DQW Cost & Schedule Review (New Baseline) CM Review, Nov 2015 (Basic design choices approved) SPS Test Day I 2

  3. Revised Planning • First Re-Baselining after C&S Review I • US cavities delayed (+ unresolved “conformity standards”) • CERN cavity production (DQW) for SPS is adopted as baseline • Impact on SPS is significant YETS – 8 weeks EYETS – 14 weeks EYETS YETS YETS Run 2 LS2 Run 3 LS3 Run 4 SPS test prototype (2 CM) preparation Tests (DQW) Tests (RFD) LHC pre-series (2 CM) LHC series production (8 Mod) Fabrication & tests Installation 3

  4. SPS Revised Planning 2016 2017 2018 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Jan 2 IOTs SM18 RF Power 2 IOTs in BA6 (FPC Conditioning) Deploy for BA6-SM18 Setup High Power & LLRF/Controls SM18-Vertical Tests Setup VTA deployment Cav 2 Fabrication + Cavity 1 Fabrication Dressed Cavities Cav 1 & 2 Treatment/Testing (Treatment + Cleanroom tooling) + Clean room assembly FPC Conditioning FPCs 2xFPCs in SM18 Cleanroom (TB) Cryostat & Tooling Cryomodule/Tooling Cryomodule CM Assembly Cold Tests SPS Design/Procurement Preparation Cryogenics Cryogenic Distribution & Valve Box SM18/SPS CM + VB Tests at CERN Movable Table Design & Manufacturing 4

  5. CM-Review Recommendations (A. Yamamoto et.al) • Clarify “the minimum functional requirement/goal” for the SPS test • Draft acceptance criteria prepared, being revised/approved • A decision/action on the ordering/implantation of the refrigerator • Done • The system integration workflow, including tooling, fixtures, and intermediate tests must be studied in greater detail • Now coordinated under a new WG • The critical components such as FPCs and tuners shall be individually reviewed (in 2016) • Cryogenic-safety and failure-mode analyses should be performed • 1 st safety analysis approved by HSE, will review again in Fall 2016 • Reinforce the supporting system & limiting forces on the FPCs. • Blade type supporting system was optimized 5

  6. DQW Production, Circular Trials (Lunette, Cuvette, Extrusion) See Talk: M. Garlasche SECT X+ Cu tests performed to explore shaping techniques & tooling (very systematic analysis) Circular samples show very good shape and thickness accuracies 6

  7. See Talk: M. Garlasche Example Shaping Simulations Dwg: LHCACFCA0067 7

  8. 16 complex welds to qualify & perform Weld Map (with tight tolerances) WELD 14 WELD 10 (x4) WELD 2 (X2) (x2) WELD 9 WELD 7 (X4) (x2) WELD 13 (x4) WELD 4 (x2) WELD 11 WELD 5 (x2) (x1) WELD 1 WELD 8 (x1) (x1) WELD 15 WELD 12 (x2) (x1) WELD 16 (X1) WELD 3 WELD 6 (x2) (x4) 8

  9. Welding Test Qualification Flow Chart Difficult Weld 9

  10. A Sample Weld Nb-Nb: W03A/B Final ellipsoidal welds : Welding in 3mm of thickness performed on 1 side. Two configurations tested: Key (Clé) and BW (Bords droits) BW INTERNAL SIDE - RF KEY INTERNAL SIDE - RF BOTH CONFIGURATIONS WITH SATISFACTORY RESULTS 10

  11. Status of US Cavities from Niowave Three welded assemblies of an 2-RFDs at Jlab RF, CMM, Radiography etc.. started Expect 1-RFD qualified and sent to CERN Mar 2017 DQWs parts being re-stamped and in a similar configuration to be sent to Jlab 11

  12. Helium Vessel Bolted/welded concept was chosen for structural integrity & minimal stress to cavity A dummy prototype was launched for experimental verification of assembly procedure, stress, vacuum integrity and other aspects. They are now verified 12

  13. Prototype Helium Vessel WELDING STEPS 1- Vertical welds 2- Welds around the top/bottom plate 3- Longitudinal Covers 4- Circular Covers & Beam pipe The vacuum levels remained at Pressure tests (2.6 bar) ≤ 10 −9 mbar (5 thermal cycles) . 13

  14. Tests vs. Simulations Mechanical Bolts Bonded Measurement Welds contacts Laboratory Friction 0.450 12 LVDT Position Sensors 0.400 0.388 0.350 0.345 0.319 0.300 0.311 0.281 0.277 0.250 0.246 0.237 MM 0.224 0.217 0.200 0.202 0.202 0.198 0.179 0.150 0.100 0.080 0.080 0.076 0.050 0.059 0.001 0.008 0.003 0.029 0.000 -0.013 -0.028 LPP UP CT_UP TP2 TP1 CB_LPP CB_TP1 CB_LP LP CT_TP2 LSP CT_LSP -0.050 PRESSURE 2.6 [BAR] 14

  15. Cavity Stress, cool down • ΔT max = 40 K top/bottom of tank (input constraint) • Stress on cavity is low ( ≤ 10% of allowable) • Slower cool-down rate can further reduce if necessary 15

  16. Cavity Chemistry, DQW & RFD DQW : Very light chemistry on Parts & RFD : Bulk Chemistry on Parts & Bulk Chemistry on assembled cavity Light Chemistry on assembled cavity Acid out Acid out Acid In Acid In 16

  17. CERN Setup, Cavity Chemistry (PoP) General procedure uses acid circulation between 10 − 15 0 C ( ~ 40 min, indicative) Small tilting for trapped gas removal

  18. Fluid Dynamics for Chemistry See Talk: T. Jones 1 2 3 4 5 6 = Inlet All other ports outlets Gravity acts down as shown in images Analysis 1 2 3 4 5 6 Range (cm/s) 0.63 1.82 0.90 0.65 1.23 0.92 Standard Deviation (cm/s) 0.21 0.40 0.24 0.21 0.26 0.23 Av. Velocity (cm/s) 0.29 0.38 0.33 0.31 0.36 0.28 Data taken for 21 points throughout the cavity for each orientation

  19. KEK Electro-polishing Status EP apparatus ready waiting for the cavity 19

  20. Frequency Tracking See Talk: S. De Silva, S. Verdu Target: 400.79 MHz (-60 kHz)

  21. 2K Internal Magnetic Shields RF Dipole Double QW • Internal magnetic shields already integrated by STFC-UK !! • 1 mm Cryophy, annealed after shaping, supported by Ti brakets • Controls done: dimensions, shielding reduction factor • At CERN waiting for cavities… 21

  22. Comparison of Data and Simulations Reduction factor ~65 Nominal input: Earth field ( ∼ 42 μT ) along beam axis SPS data taken in LSS6 zone from YETS

  23. HOM Couplers See Talk: M. Garlasche DQW Status • Niobium pieces & other ancillaries produced • Final metrology & welding tests ongoing before assembly RFD material at CERN, fabrication in 2016 HOM Testbox See Talk: J. Mitchell 23

  24. HOM Lines Load side (300 K) • Optimized for static/dynamic heat loads to 2K • Coax line for 1 kW, 316LN, Cu sputtered ( 5𝜈m ) • Flexibility using spherical joints & Test box themalization with alumina disk • Destructive tests for validation 2016 Cavity side (2K) 24

  25. Tuner Tests (on PoP) See Talk: A. Castilla Tuner preparation for Cold Tests planned during Jun 2016 • Assembly into SM18_V3 & protection for cooldown actions ongoing • PLC based control system successfully tested in a feedback loop Tuner motion Freq request Repeatability preceision ~0.5 μm ~ 100 Hz 25

  26. Tuning Fixtures • Warm frequency tuning limited by tuning fixture • Limiting factor is the strength of NbTi fixture and weld • CERN (NbTi), USLARP (Nb with reinforced shape) Nb fixture with helicoil DQW Pre-tuning: ≥ 0.3 mm RFD: ∼ 1.4 mm (7000 kN elastic limit) permanent deformation 26

  27. Power Coupler Most FPC parts (+spares) completed RFD DQW RF Test Box 2 DQW + 2 RFD Couplers by end of May (spares in Oct) RF Test box ready by Sept.  Clean room assembly in Oct Two DQW couplers ready April 2017 27

  28. RF Amplifier 2016: Important decision to adopt IOT as baseline for SPS Modification of the existing IOT station to 400 MHz New output cavities & new coupling elements (designed at CERN) Validation will establish IOTs as baseline for LHC (streamline integration) Reached 60 kW last Friday, limited by the exiting power supplies !

  29. Cavity Supports & Alignment Top plate – kinematic mount, option with levelling jacks as vertical supports Three point alignment which are blocked after Additional points for rigidity VERTICAL3 VERTICAL2 VERTICAL1 29

  30. Position monitoring system (BCAM + FSI) • BCAM + FSI (1:1) full system mock-up under construction • Irradiation campaign of reflective targets and collimators finished • FSI head prototypes designed and under manufacturing • BCAM → System performance initially validated on the mock -up. Tests and calibration of camera vacuum viewports pending • Cryogenic tests of reflective targets planned in the next 2 months • Fiducialisation of the helium tank mock-up on CMM and laboratory verification of full system performance • FSI head test in operation conditions (vacuum, reflector at 4K) • Irradiation campaign of FSI heads assemblies • SM18, SPS - DAQ and data processing software development • Measurements in SM18 – validation of the final system

  31. Top plate Warm Magnetic Shield • Field measured in SPS and applied to Warm Magnetic Shield Results with optimal proposed design • Gaps between plates induces field leaks, fine tuning Peak B ≤ 5 𝜈𝑈 @extremeties 31

  32. CM Thermal Shields • After several studies, Cu chosen as baseline • Connection between cooling pipe and plates under study • Design & integration finishing Pipe Temperature Pipe Convection Result T min (K) T max (K) T min (K) T max (K) Summary Al/SS Panels 64 81 70 87 Pipe 50 105 50 139 Panels 53 75 55 84 Cu Pipe 50 70 50 75 32

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend