FY 09 AES Phase I Crab Cavity SBIR Progress Michael Cole (AES), - - PowerPoint PPT Presentation

fy 09 aes phase i crab cavity sbir progress
SMART_READER_LITE
LIVE PREVIEW

FY 09 AES Phase I Crab Cavity SBIR Progress Michael Cole (AES), - - PowerPoint PPT Presentation

Advanced Energy Systems, Inc. FY 09 AES Phase I Crab Cavity SBIR Progress Michael Cole (AES), Rama Calaga (BNL), Zenghai Li (SLAC) Prototype Crab Cavity SBIR Objectives Advanced Energy Systems, Inc. Collaborators are AES, BNL, SLAC, and


slide-1
SLIDE 1

Advanced Energy Systems, Inc.

FY 09 AES Phase I Crab Cavity SBIR Progress

Michael Cole (AES), Rama Calaga (BNL), Zenghai Li (SLAC)

slide-2
SLIDE 2

Advanced Energy Systems, Inc.

Prototype Crab Cavity SBIR Objectives

  • Collaborators are AES, BNL, SLAC, and LBL
  • Phase 1

– Preliminary Design of Cavity (3 man months supported by SBIR)

  • Coordinate transfer of Physics Design - Complete
  • Develop initial mechanical solid model - Complete
  • Perform Initial Thermal and Structural Analysis – Underway

– Principle issue currently is cooling requirement for coaxial beam pipes

  • Preliminary Mechanical Design and Fabrication Feasibility Study –

Largely Complete

  • Phase 2

– Complete mechanical design with supporting thermal/structural analysis. – Generate complete fabrication drawing package for the Crab Cavity. – Fabricate Prototype Crab Cavity – Perform BCP and HPR on Prototype Crab Cavity at AES if our facilities can accommodate it. We anticipate that we will be able accommodate an 800 MHz elliptical crab cavity. – Support Crab Cavity VTF testing at BNL

slide-3
SLIDE 3

Advanced Energy Systems, Inc.

Overall Cavity Configuration

Most of the cavity will be surrounded by a LHe vessel in the operational design but not in the prototype. Cooling of the Beam Pipe Inner Conductors could be flood cooled 2K LHe

  • r forced 5K He, this question is currently being addressed.

5K He adds significant complications for VTA testing

ADJACENT BEAM PIPE, Accounted for but not included SHORT END GROUP FPC PORT PORTS FOR LOM/HOM-v COUPLER FPC END GROUP Coaxial Beam Pipes Double Walled Beam Pipe Inner Conductors

slide-4
SLIDE 4

Advanced Energy Systems, Inc.

Parted out Welded Assembly

39 Welding steps joining 32 parts will be required to fabricate each cavity. In addition there are machining operations between many of the welds.

slide-5
SLIDE 5

Advanced Energy Systems, Inc.

Welding Sequence A: Inner & Outer Conductor

8 Welding steps required to fabricate the inner conductor 6 Welding steps required to fabricate the outer conductor 2 Welding steps required to connect the inner and outer conductor

slide-6
SLIDE 6

Advanced Energy Systems, Inc.

Welding Sequence B: End Groups

9 Welding steps required to fabricate FPC side End Group 2 Welding steps required to fabricate short side End Group

slide-7
SLIDE 7

Advanced Energy Systems, Inc.

Welding Sequence C: Coax BP ICs

3 Welding steps are required to fabricate each double walled beam pipe inner conductor. Fabricating the inner conductors in the fashion is actually cheaper than machining them from bar. They are too thick to roll and seam weld.

slide-8
SLIDE 8

Advanced Energy Systems, Inc.

RF Analysis: Normalization

Magnetic Field (HY)

  • 4.0E+04
  • 3.0E+04
  • 2.0E+04
  • 1.0E+04

0.0E+00 1.0E+04 2.0E+04 3.0E+04 4.0E+04 0.0 0.2 0.4 0.6 0.8 1.0 Disatance Along Center of Cavity meters Magnetic Field A/m Scaled for Transverse voltage of 5MV/cavity

Magnetic field on Axis used to normalize cavity fields. Surface Fields will be used to calculate heat loads

slide-9
SLIDE 9

Advanced Energy Systems, Inc.

RF Analysis: Surface H Fields and Initial Wall Powers

2.14e-2 9.14e3 1.82e4 2.74e4 3.65e4 4.56e4 5.47e4 6.38e4 7.29e4 8.21e4 Magnetic Field A/m

Surface Power Loss 2K = 11.2 watts 4.2K = 70.5 watts

slide-10
SLIDE 10

Advanced Energy Systems, Inc.

Work Remaining

  • Phase 2 proposal due May 20
  • Complete mechanical design work and determine

fabrication cost for cavity

  • Complete thermal and structural analysis, primary concern

will be cooling requirement for coaxial beam pipes

  • We are on track for May 20