Statement 2014 Disclaimer This presentation has been prepared by - - PowerPoint PPT Presentation

statement 2014
SMART_READER_LITE
LIVE PREVIEW

Statement 2014 Disclaimer This presentation has been prepared by - - PowerPoint PPT Presentation

OCTOBER 2014 Second Interim Management Statement 2014 Disclaimer This presentation has been prepared by the management of Nyrstar NV (the "Company"). It does not constitute or form part of, and should not be construed as, an offer,


slide-1
SLIDE 1

OCTOBER 2014

Second Interim Management Statement 2014

slide-2
SLIDE 2

This presentation has been prepared by the management of Nyrstar NV (the "Company"). It does not constitute or form part of, and should not be construed as, an

  • ffer, solicitation or invitation to subscribe for, underwrite or otherwise acquire, any securities of the Company or any member of its group nor should it or any part of

it form the basis of, or be relied on in connection with, any contract to purchase or subscribe for any securities of the Company or any member of its group, nor shall it or any part of it form the basis of or be relied on in connection with any contract or commitment whatsoever. The information included in this presentation has been provided to you solely for your information and background and is subject to updating, completion, revision and amendment and such information may change materially. Unless required by applicable law or regulation, no person is under any obligation to update or keep current the information contained in this presentation and any opinions expressed in relation thereto are subject to change without notice. No representation or warranty, express or implied, is made as to the fairness, accuracy, reasonableness or completeness of the information contained herein. Neither the Company nor any other person accepts any liability for any loss howsoever arising, directly or indirectly, from this presentation or its contents. This presentation includes forward-looking statements that reflect the Company's intentions, beliefs or current expectations concerning, among other things, the Company’s results of operations, financial condition, liquidity, performance, prospects, growth, strategies and the industry in which the Company operates. These forward-looking statements are subject to risks, uncertainties and assumptions and other factors that could cause the Company's actual results of operations, financial condition, liquidity, performance, prospects, growth or opportunities, as well as those of the markets it serves or intends to serve, to differ materially from those expressed in, or suggested by, these forward-looking statements. The Company cautions you that forward-looking statements are not guarantees of future performance and that its actual results of operations, financial condition and liquidity and the development of the industry in which the Company operates may differ materially from those made in or suggested by the forward-looking statements contained in this presentation. In addition, even if the Company's results of

  • perations, financial condition, liquidity and growth and the development of the industry in which the Company operates are consistent with the forward-looking

statements contained in this presentation, those results or developments may not be indicative of results or developments in future periods. The Company and each

  • f its directors, officers and employees expressly disclaim any obligation or undertaking to review, update or release any update of or revisions to any forward-

looking statements in this presentation or any change in the Company's expectations or any change in events, conditions or circumstances on which these forward- looking statements are based, except as required by applicable law or regulation. This document and any materials distributed in connection with this document are not directed to, or intended for distribution to or use by, any person or entity that is a citizen or resident or located in any locality, state, country or other jurisdiction where such distribution, publication, availability or use would be contrary to law or regulation or which would require any registration or licensing within such jurisdiction. The distribution of this document in certain jurisdictions may be restricted by law and persons into whose possession this document comes should inform themselves about, and observe any such restrictions. The Company’s shares have not been and will not be registered under the US Securities Act of 1933 (the “Securities Act”) and may not be offered or sold in the United States absent registration under the Securities Act or exemption from the registration requirement thereof.

2

Disclaimer

slide-3
SLIDE 3

3

Heinz Eigner

Chief Financial Officer

Michael Morley

Chief Corporate and Development Officer, Senior Vice President, Metals Processing

Bob Katsiouleris

Senior Vice President, Marketing, Sourcing and Sales Acting SVP Mining

slide-4
SLIDE 4

4

Highlights

  • Continued solid operational performance for Metals Processing
  • Zinc market metal production of 269,000 tonnes in Q3 2014, up 1% quarter-on-quarter;

821,000 tonnes in 9M 2014, up 4% year-on-year1

  • Improving operational performance for Mining
  • Zinc in concentrate production (own mines) of 70,000 tonnes in Q3 2014, up 4% quarter-on-

quarter; 210,000 tonnes in 9M 2014, up 3% year-on-year

  • Full year production guidance maintained
  • Remain on track to deliver against previously announced annualised Project Lean savings

target of EUR 75m by the end of 2014

  • Q3 2014 average zinc price of USD 2,311/t, up 11% quarter-on-quarter
  • Near term zinc price trading conditions remain volatile. Nyrstar remains confident in the

underlying fundamentals of the zinc market in the medium term

  • Zinc premia and treatment charge outlook favourable for smelters
  • Nyrstar successfully completed its Comprehensive Strategic Financing to continue its strategy

execution while enhancing the Company’s financial position

  • In early October Nyrstar successfully completed the forward sale of a portion of the

incremental future silver production of the redeveloped Port Pirie for AUD 120 million, which is the second component of the funding package for the Redevelopment

Second Interim Management Statement 2014

1 Historical zinc metal production adjusted to reflect the closure of the zinc plant at Port Pirie in July 2014.

slide-5
SLIDE 5

5

1,200 1,450 1,700 1,950 2,200 2,450 Jan 12 Apr 12 Jul 12 Oct 12 Jan 13 Apr 13 Jul 13 Oct 13 Jan 14 Apr 14 Jul 14 Oct 14

LME Zinc Price USD LME Zinc Price Euro Q3 Avg

15 20 25 30 35 40 45 50 55 60 1,000 1,250 1,500 1,750 2,000 Jan 12 Apr 12 Jul 12 Oct 12 Jan 13 Apr 13 Jul 13 Oct 13 Jan 14 Apr 14 Jul 14 Oct 14

Gold (RHS) Silver (LHS)

LME zinc price

USD 2,025 EUR 1,544

LBMA silver & gold prices USD / OZ

USD 1,927 EUR 1,501 USD 1,885 EUR 1,507 USD 1,947 EUR 1,501 USD 2,033 EUR 1,539 USD 1,840 EUR 1,409 USD 1,859 EUR 1,404 USD 1,907 EUR 1,401 USD 2,029 EUR 1,482 USD 2,073 EUR 1,512 USD 2,311 EUR 1,744 Ag 33 Au 1,691 Ag 29 Au 1,609 Ag 30 Au 1,652 Ag 33 Au 1,720 Ag 30 Au 1,632 Ag 23 Au 1,415 Ag 21 Au 1,326 Ag 21 Au 1,274 Ag 20 Au 1,293 Ag 20 Au 1,288 Ag 20 Au 1,284

Improving zinc price conditions; near term trading volatility remains

Second Interim Management Statement 2014

slide-6
SLIDE 6

6

1,400 1,200 1,000 800 600 400 200 kt 2,500 2,400 2,300 2,200 2,100 2,000 1,900 1,800 1,700 USD/mt Jul ’14 Jan ’14 Jul ’13 Jan ’13 Jul ’12 Jan ’12 Oct ’14 LME zinc price + zinc premium LME zinc price, cash settlement LME warehouse volume 140 155 115 100 110 120 130 140 150 160 170 180 190 2′450 2′400 2′350 2′300 2′250 2′200 2′150 2′100 2′050 2′000 1′950 1′900 Sep ’14 Jul ’14 Aug ’14 2′410 May ’14 Jun ’14 2′121 Mar ’14 Apr ’14 Feb ’14 USD/kg USD/mt Oct ’14 2′336 Jan ’14 MB Shanghai premium MB Rotterdam premium LME 3 months zinc price

  • LME zinc stocks peaked in December 2012 at 1.235 Mmt

and have since fallen 46%

  • Questions around off-warrant inventories remain

YTD zinc prices vs. premia evolution

  • Zinc price climbed significantly above last year’s level,

with the market anticipating a widening supply-demand gap

  • Outlook for premia going forward is positive

LME zinc warehouse volumes vs. price

LME zinc inventories continue to decline while zinc prices improve in anticipation of a growing supply deficit

Second Interim Management Statement 2014

slide-7
SLIDE 7

7

Source: Economist; Financial Times

Expectations of global business confidence by region

Balance of Respondents Expecting Conditions to Improve, %, Q3 2014

Expectations of global business confidence over time Market sentiment (Source: August Economist/Financial Times “Global Business Barometer survey”)

  • In Q3 2014, 36% of respondent’s believed the

global economy would improve – down from > 50% in Q1 2014

  • 46% believed it would stay the same and 18%

saying it would get worse By Region

  • Growth in Asia and Africa remains strong
  • Improving confidence in North America and

Europe

  • Conflict in Eastern Europe and the Middle

East negatively impacted sentiment By End-use market

  • Automotive and manufacturing sectors

expected to show the most improvement

  • Construction and consumer goods growth

solid

  • Energy & resource sector remains positive
  • Chemicals industry softening in light of

increasing energy costs

Global economic outlook: underlying fundamentals remain positive particularly for markets that drive metal demand

Second Interim Management Statement 2014

slide-8
SLIDE 8

8

Metals Processing: delivering solid operational performance

Lead Production

kt 54 43 49 +26% +10% Q3 2014 Q2 2014 Q1 2014

Zinc Production

kt 780 779 808 821 +4% +2% 9M 2014 13 9M 2013 801 22 9M 2012 803 23 MP Total (excl. Pirie) Port Pirie kt 147 127 113

+16%

+30% 9M 2014 9M 2013 9M 2012 272 267 269 6 +1% Q2 2014 280 8 269

  • 4%

Q3 2014 Q1 2014 272 Port Pirie MP Total (excl. Pirie)

Second Interim Management Statement 2014

kt

Quarter on Quarter Year on Year

slide-9
SLIDE 9

9

1.0 0.9 1.0 +3% Q3 2014 Q2 2014 Q1 2014 +15% kt

Copper cathode

3.6 3.7 3.5 Q2 2014 Q1 2014

  • 3%

+3% Q3 2014 m toz

Silver

8 13 7

  • 38%

+3% Q3 2014 Q2 2014 Q1 2014 k toz

Gold

9 13 10

  • 31%
  • 14%

Q3 2014 Q2 2014 Q1 2014 t

Indium

2.9 3.0 2.3

  • 4%

+26% 9M 2014 9M 2013 9M 2012 kt

Copper cathode

10.7 13.1 8.9

  • 18%

+21% 9M 2014 9M 2013 9M 2012 m toz

Silver

28 54 42

  • 48%
  • 33%

9M 2014 9M 2013 9M 2012 k toz

Gold

32 25 4 +28% +780% 9M 2014 9M 2013 9M 2012 t

Indium Second Interim Management Statement 2014

Metals Processing: delivering solid operational performance

Quarter on Quarter Year on Year

slide-10
SLIDE 10

Port Pirie: total capital costs of AUD 514m unchanged; on track for commissioning during 2016

Second Interim Management Statement 2014 10

  • Construction
  • Completion of site offices to accommodate construction

management personnel

  • Completion of site earthworks and service installation ahead of

starting the first stage of the construction of a temporary accommodation camp for 400 contractors

  • Commencement of new site workshop enabling existing building to

be demolished to make way for the new oxidation furnace

  • Procurement and contracting
  • A significant number of key contracts were awarded including

agreements for the construction of the temporary accommodation camp and the new site workshop; general and furnace piling; sulphuric acid plant piling and the sulphuric acid plant design and supply; as well as the blast furnace and copper crossing furnace (“CDF”) engineering design services contract

  • A review was also conducted on the furnace design and supply

contract, and work remains on schedule

  • Engineering
  • Nearly 50% of the engineering work for the project was completed

by the end of September; includes work on the site layout and equipment specifications

  • A number of significant layout design reviews were conducted;

includes work on the feed preparation area, infrastructure and furnace area

  • A number of HAZOP reviews were also completed

Q3 highlights Temporary accommodation for contractors Start of floor replacement for new workshop Geotechnical drilling underway for oxygen plant

slide-11
SLIDE 11

Port Pirie: total capital costs of AUD 514m unchanged; on track for commissioning during 2016

Second Interim Management Statement 2014 11

Q4 Targets

  • Construction
  • First stage of the temporary accommodation camp is expected to be completed as is the new site workshop
  • Demolition of the existing workshop in preparation for the installation of the new oxidation furnace
  • Preparation of the construction area for the oxygen plant will commence
  • Piling works for the sea water cooling system, water and gas services and infrastructure buildings will

commence

  • Installation of the Redevelopment plant connections will be completed during the planned blast furnace shut in

November

  • On procurement and contracts
  • Significant number of additional contracts are expected to be awarded including those for the oxygen plant

(Build-Own-Operate); high voltage electrical recirculation; furnace waste heat boiler supply; evaporative cooling tower supply; electro static precipitator supply; coal grinding plant supply; furnace fans supply; coal injection plant supply; demineralised water plant supply; heat exchangers supply; and conveyor systems supply contract

  • On procurement and contracts
  • Around 75% of the engineering work for the project is expected to be complete by year-end
slide-12
SLIDE 12

12

Other growth projects: SSR on track and on budget

Q3 highlights

  • Post Century projects enter

implementation phase: on track for completion in H1 2015

  • Other deconstraining projects

move into implementation phase;

  • n track for completion in H1 2015

Q4 targets

  • Post Century demolition & plant modification

works at Hobart & Budel

  • Plant modifications at Auby to allow

increased indium throughput & recovery

  • Complete test campaign with respect to

installation of oxygen enrichment in roasting

  • Port Pirie (post-Redevelopment) projects to

move from feasibility to development phase, and others to enter feasibility phase Q3 highlights

  • Work continued on redevelopment
  • f Hoyanger fumer: on track to be

completed by the end of 2014

  • Continued evaluating options for

additional fuming capacity in Europe; feasibility report on track to be completed by the end of 2014 Q4 targets

  • Commission redeveloped Hoyanger fumer
  • Complete final feasibility report for

additional fuming capacity in Europe and for this project to move into development phase

Expanding minor metals

Q3 highlights

  • Zinc plant at Port Pirie closed on

schedule; shipments of fumes to both Hobart and Auby received and successfully processed

  • Expansion of indium metal

production at Auby moved into implementation phase; on track to be completed by H2 2015

  • Other projects progressed as

scheduled Q4 targets

  • Continue works with respect to the

implementation phase of the expansion of indium metal production at Auby

  • At Clarksville, complete final feasibility

report for new facility to enable recovery of valuable historical residues for treatment at Nyrstar’s fumers

Adding fuming capacity Deconstraining smelters

Second Interim Management Statement 2014

slide-13
SLIDE 13

13 Year on Year Zinc in concentrate production

73 67 70 17 5 75 +4% +4% Q3 2014 Q2 2014 84 Q1 2014 73

Other metals in concentrate production

15.7

  • 10%
  • 23%

Gold (’000 oz) 12.1 13.5 1,318 +14% +3% Silver (’000 oz) 1,354 1,185 4.1 3.8 4.6 +22% +13% Lead (’000 t) 3.3 2.9 2.9 0%

  • 11%

Copper (’000 t)

Mining: improving operational performance

Second Interim Management Statement 2014

Quarter on Quarter

209 203 210 22 22 9M 2013 214 11 9M 2012 230 232 +3% +1% 9M 2014 Own mine production Talvivaara

  • 39%

Gold (’000 oz) 41.3 51.1 67.4

  • 19%

3,541 3,856 Silver (’000 oz)

  • 6%

4,098 +9% +1% 12.5 Lead (’000 t) 12.4 11.1 +13% 9.7 9.1 9.1 Copper (’000 t)

  • 6%

0% kt kt

slide-14
SLIDE 14

14 Ore Milled Volume

  • 3%
  • 9%

Q2 2014 1,671 Q3 2014 1,717 Q1 2014 1,836

Mill head grades

Mining: improving operational performance

Second Interim Management Statement 2014

Quarter on Quarter Year on Year

+5% Q3 2014 Q2 2014 4.43 4.66 Q1 2014 4.39 Q3 2014 1.16 Q2 2014

  • 3%

Q1 2014 1.19 1.31 Q3 2014 71.70 Q2 2014 +13% 63.70 Q1 2014 69.90 Q3 2014 1.17 Q2 2014 +21% 0.97 Q1 2014 1.05 Q3 2014 0.67 Q2 2014 +3% 0.65 Q1 2014 0.83 Zinc % Lead % Copper % Silver g/t Gold g/t 9M 2014 4.49 9M 2013 9M 2012 4.66 4.41 +2% 9M 2013 9M 2014 1.23 1.68

  • 27%

1.99 9M 2012 68.48 9M 2013 +3% 9M 2014 9M 2012 66.45 71.30 1.07 9M 2013 +11% 9M 2014 0.96 9M 2012 1.06

  • 9%

9M 2014 0.67 9M 2013 0.74 9M 2012 0.86 +4% 5,193 5,225 9M 2013 9M 2014 +1% 5,007 9M 2012 Zinc % Lead % Copper % Silver g/t Gold g/t kt kt

slide-15
SLIDE 15

15 15

Second Interim Management Statement 2014

Completed debut high yield EUR 350 million Notes Offering Successfully completed EUR 252 million Rights Offering Successfully completed

  • ca. EUR 600 million

targeted capital raise

 EUR 350 million Senior Unsecured Notes maturing in 2019 priced at 98.018% with a coupon of 8½% per year  Notes received credit rating "B3 (stable)" by Moody’s and "B- (stable)" by Standard & Poor’s ratings services  Extension of debt maturity profile  Access to new capital market established  Raised new equity in successful 1:1 fully-underwritten Rights Offering  New shares with preferential subscription rights for existing shareholders  Nyrstar's share capital increased to EUR 34,004,508.80, and the number of shares representing Nyrstar's share capital increased to 340,045,088 shares  Strengthen Nyrstar’s balance sheet and fund investment needs  Use of proceeds:  EUR 147 million used to repurchase part of the outstanding 2015 retail bonds  EUR 100 million used to repurchase a portion of 2016 retail bonds  EUR 200 million CAPEX requirement over next 2 years for Nyrstar’s continued transformation through SSR investments  EUR 68 million for Nyrstar’s direct contribution to Port Pirie Redevelopment  Reduce Net debt (towards a medium term targeted Net debt / EBITDA ratio of 2.5x), and for general corporate purposes

Comprehensive Strategic Financing: completed

slide-16
SLIDE 16

OCTOBER 2014

Questions

slide-17
SLIDE 17

17

2014 Guidance

Metal in concentrate Range

Zinc (own mines)1 280,000 – 310,000 tonnes Lead 15,000 – 18,000 tonnes Copper 12 ,000– 14,000 tonnes Silver2 4,750,000 – 5,250, 000 troy ounces Gold 65,000 – 70,000 troy ounces

1 Excluding zinc deliveries under the Talvivaara Streaming Agreement. 2 75% of the silver produced by Campo Morado is subject to a streaming agreement with Silver Wheaton Corporation whereby only USD 3.90/oz is payable. In Q3 2014,

Campo Morado produced approximately 270,000 troy ounces of silver.

Production

EURm

Mining

105–115 Sustaining 40 – 45 Exploration and Development and Growth 65 – 70

Metals Processing

155–180 Sustaining 75 – 80 Growth (SSR investment) 20 - 30 Port Pirie Redevelopment 60 -70

Group

260-295

CAPEX

Smelter & production step impacted Timing and duration Estimated impact

Auby – roaster Q4: 2 weeks nil Port Pirie – lead plant Q4: 4 weeks 4200-6000t

Smelter planned maintenance shuts Mining Metals processing

Metal Range Zinc 1.0–1.1 million tonnes

  • Production guidance based on maximising EBITDA

and free cash flow by targeting optimal balance between production and Sustaining CAPEX

  • Estimated impact of maintenance shuts on 2014

production, have been taken into account when determining zinc metal guidance for 2014

  • Disciplined CAPEX approach
  • Non-growth CAPEX in 2014 expected to be flat or

lower year on year

Second Interim Management Statement 2014

slide-18
SLIDE 18

18

xxxx

Investor Relations Amy Rajendran Head of Investor Relations D: +41 (0)44 745 81 03 E: amy.rajendran@nyrstar.com Corporate Communications Greg Morsbach Head of Corporate Communications D: +41 44 745 8295 E: greg.morsbach@nyrstar.com www.nyrstar.com

Second Interim Management Statement 2014

slide-19
SLIDE 19

OCTOBER 2014

Appendix

slide-20
SLIDE 20
  • Calculated by modeling Nyrstar’s H1 2014 underlying operating performance. Each parameter is based on an

average value observed during that period and is varied in isolation to determine the annual EBITDA impact

  • Particular care needs to be taken when applying the sensitivities.

Parameter Variable Estimated annualised EBITDA impact EURm Estimated annual EBITDA impact EURm H1 2014 FY 2013 Zinc price +/- USD100/t +30 / -29 +28 / -28 Lead price +/- USD100/t +2 / -2 +2 / -2 Copper price +/- USD500/t +6 / -6 +6 / -6 Silver Price +/- USD1/troy ounce +4 / -4 +4 / -4 Gold Price +/- USD100/troy ounce +5 / -5 +6 / -6 USD / EUR +/- EUR0.01 +18 / -18 +18 / -18 AUD / EUR

  • /+ EUR0.01
  • 3 / +3
  • 3 / +3

Zinc TC +/- USD25/dmt1 +29 / -29 +28 / -28 Lead TC +/- USD25/dmt1 +5 / -5 +5 / -5

20

1 dmt = dry metric tonne.

EBITDA sensitivity

Second Interim Management Statement 2014

slide-21
SLIDE 21

21

Auby Zinc Balen/Overpelt Zinc Budel Zinc

Metals Processing: performance by site

42 42 43

0%

  • 2%

Q3 2014 Q2 2014 Q1 2014 127 112 121

+13% +5%

9M 2014 9M 2013 9M 2012 62 66 68

  • 6%
  • 9%

Q3 2014 Q2 2014 Q1 2014 196 183 186

+7% +5%

9M 2014 9M 2013 9M 2012 73 73 70

0% +4%

Q3 2014 Q2 2014 Q1 2014 217 203 186

+7% +16%

9M 2014 9M 2013 9M 2012

Second Interim Management Statement 2014

Quarter on Quarter Year on Year

kt kt kt kt kt kt

slide-22
SLIDE 22

22

Clarksville Zinc Hobart Zinc Port Pirie Lead

Metals Processing: operational performance by site

24 29 28

  • 17%
  • 15%

Q3 2014 Q2 2014 Q1 2014 81 83 79 +3%

  • 3%

9M 2014 9M 2013 9M 2012 68 57 63

+19% +7%

Q3 2014 Q2 2014 Q1 2014 188 202 204

  • 7%
  • 8%

9M 2014 9M 2013 9M 2012 54 43 49

+26%

+10% Q3 2014 Q2 2014 Q1 2014 147 127 113

+16%

+30% 9M 2014 9M 2013 9M 2012

Second Interim Management Statement 2014

Quarter on Quarter Year on Year

kt kt kt kt kt kt

slide-23
SLIDE 23

23 Campo Morado Contonga El Mochito El Toqui

Zinc in concentrate kt Silver in concentrate k toz Zinc in concentrate kt Silver in concentrate k toz Zinc in concentrate kt Silver in concentrate k toz Gold in concentrate k toz Zinc in concentrate kt

Mining: operational performance by site

5.8 6.5 6.4 +12% 0% Q3 2014 Q2 2014 Q1 2014 270 230 248 +17% +9% Q3 2014 Q2 2014 Q1 2014 8.0 6.5 6.0 +23% +33% Q3 2014 Q2 2014 Q1 2014 415 338 421 +23%

  • 1%

Q3 2014 Q2 2014 Q1 2014 3.3 3.4 3.3

  • 3%

0% Q3 2014 Q2 2014 Q1 2014 100 85 81 +18% +23% Q3 2014 Q2 2014 Q1 2014 9.7 9.4 8.3 +3% +17% Q3 2014 Q2 2014 Q1 2014 2.8 5.6 6.5

  • 49%
  • 57%

Q3 2014 Q2 2014 Q1 2014

Second Interim Management Statement 2014

Quarter on Quarter

slide-24
SLIDE 24

24 Langlois Myra Falls

Zinc in concentrate kt Silver in concentrate k toz Gold in concentrate k toz Zinc in concentrate kt Zinc in concentrate kt Zinc in concentrate kt

Mining: operational performance by site

9.1 10.2 9.3 Q3 2014 Q2 2014 Q1 2014

  • 11%
  • 2%

117 143 127 Q3 2014 Q2 2014 Q1 2014

  • 8%
  • 18%

8.4 6.7 7.9 Q1 2014 Q3 2014 Q2 2014 +27% +6% 7.4 5.7 6.4 Q2 2014 Q3 2014 Q1 2014 +16% +29% 13.4 16.0 17.5 Q3 2014 Q2 2014 Q1 2014

  • 23%
  • 16%

11.4 9.2 13.7 Q2 2014 Q3 2014 Q1 2014 +24%

  • 17%

East Tennessee mines Middle Tennessee mines

Second Interim Management Statement 2014

Quarter on Quarter

slide-25
SLIDE 25

25 Campo Morado Contonga El Mochito El Toqui

Zinc in concentrate kt Silver in concentrate k toz Zinc in concentrate kt Silver in concentrate k toz Zinc in concentrate kt Silver in concentrate k toz Gold in concentrate k toz Zinc in concentrate kt

Mining: operational performance by site

18.8 17.7 30.9 +6%

  • 39%

9M 2014 9M 2013 9M 2012 748 871

  • 14%
  • 44%

9M 2014 9M 2013 9M 2012 1.329 20.5 19.3 19.4 +6% +6% 9M 2014 9M 2013 9M 2012 1.175

  • 6%
  • 3%

9M 2014 9M 2013 1.246 9M 2012 1.209 10.1 9.7 10.7 +4%

  • 6%

9M 2014 9M 2013 9M 2012 265 227 325

  • 18%

9M 2014 +17% 9M 2013 9M 2012 27.4 15.6 18.4 9M 2013 9M 2014 +50% +76% 9M 2012 15.0 25.5 33.7 9M 2013 9M 2014 9M 2012

  • 41%
  • 55%

Second Interim Management Statement 2014

Year on Year

slide-26
SLIDE 26

26 Langlois Myra Falls

Zinc in concentrate kt Silver in concentrate k toz Gold in concentrate k toz Zinc in concentrate kt Zinc in concentrate kt Zinc in concentrate kt

Mining: operational performance by site

28.6 27.5 29.4

  • 3%

+4% 9M 2014 9M 2013 9M 2012 386 408 389

  • 5%
  • 1%

9M 2014 9M 2013 9M 2012 23.0 18.2 25.1 +28%

  • 8%

9M 2014 9M 2013 9M 2012 19.5 11.8 10.9 +65% +79% 9M 2014 9M 2013 9M 2012 46.9 53.3 42.5

  • 12%

+10% 9M 2014 9M 2013 9M 2012 34.2 38.0 33.9 9M 2014

  • 11%

+1% 9M 2013 9M 2012

East Tennessee mines Middle Tennessee mines

Second Interim Management Statement 2014

Year on Year