STAGE 3 April 23, 2018 SM T MEETING M ARCH 21, 2018 Agenda - - PowerPoint PPT Presentation

STAGE 3 Executive Committee STAGE 3 April 23, 2018 SM T MEETING M ARCH 21, 2018 Agenda Project Status Packaging the Plan Strategies and Action Plans Walking Cycling Transit Streets Emerging T echnologies


slide-1
SLIDE 1

STAGE 3

SM T MEETING M ARCH 21, 2018

STAGE 3 Executive Committee April 23, 2018

slide-2
SLIDE 2

Agenda

TRANSPORTATION & TRANSIT

  • Project Status
  • Packaging the Plan
  • Strategies and Action Plans
  • Walking
  • Cycling
  • Transit
  • Streets
  • Emerging T

echnologies

  • Next Steps
slide-3
SLIDE 3

April – September 2017 October - December 2017 J anuary – April 2018 M ay – J une 2018

  • Further Technical

Analysis

  • Refine and Finalize

Long-Term Concepts

  • Public Engagement
  • Develop Short, Medium,

and Long-Term Priorities

  • Draft Plan
  • Present to Council

(April 2018)

Study Process

slide-4
SLIDE 4

February 2018 Engagement

Four public events with

  • ver 160 interactions
  • Abbotsford Centre: 76
  • MCA: 22
  • Library: 45
  • Highstreet: 18
slide-5
SLIDE 5

Plan Themes

slide-6
SLIDE 6

a. Expanded Network of Sidewalks and Pathways b. Enhanced Street Treatments for Major Destinations c. Safety and Accessibility Improvements d. Support Programs

Walking Strategies

slide-7
SLIDE 7

a. Expanded Network of Sidewalks and Pathways b. Enhanced Street Treatments for Major Destinations c. Safety and Accessibility Improvements d. Support Programs

Walking Strategies

FOCUS FOR TODAY

slide-8
SLIDE 8
  • a. Expanded Network of Sidewalks

Coverage Standard:

  • Arterials (2 sides)
  • Collectors (2 sides)
  • Local streets (1 side)

Potential Expansion

  • 100km of sidewalks
slide-9
SLIDE 9
  • a. Expanded Network of Sidewalks
slide-10
SLIDE 10

Phasing Plan

  • a. Expanded Network of Sidewalks

Phasing

slide-11
SLIDE 11
  • Long-Term Sidewalk Expansion: $40-50M*
  • Short-Term Priorities (<5 year):

a. Implement approximately 4 to 6 km of new sidewalks at existing levels of funding ($500,000/ yr). b. Encourage additional new sidewalks to be constructed through redevelopment. c. Consider additional dedicated funding for:

  • Enhanced street treatments
  • Safety and accessibility improvements (ie crosswalks, curb letdowns)
  • Support programs (ie Safe Routes to School)

Implementation Plan – Walking

* Costs in 2018 dollars

slide-12
SLIDE 12

Financing Plan – Walking

Potential Funding Increases for M edium- and Long-term Status Quo: $12.5 million / 25 years à approx. 30 km of new sidewalks Incremental Increase: $17.5 million / 25 years à approx. 40 km of new sidewalks

$0 $250,000 $500,000 $750,000 $1,000,000

S tatus Quo Incremental Increase

Short- term Medium- term Long- term

slide-13
SLIDE 13

Cycling Strategies

a. Complete, connected bicycle network b. Support Facilities c. Support Programs

slide-14
SLIDE 14

Cycling Strategies

a. Complete, connected bicycle network (Long-term) b. Support Facilities c. Support Programs

FOCUS FOR TODAY

slide-15
SLIDE 15

a. Complete Connected Network

Long-term Network Plan (270km)

Facility Types \

S ignature Bike Corridor (6km) AAA Bike Facilities (107km) S upporting Bike Facilities (160km) 400m AAA Network buffer

slide-16
SLIDE 16

a. Completed Connected Network

Phasing Plan

Phasing

slide-17
SLIDE 17
  • Long-Term Cycling Network: $50-60M*
  • Short-Term Priorities (<5 years):

a. Construct high priority bicycle routes at existing funding levels

($300,000/ yr).

b. Leverage and maximize grant funding (Bike BC, Federal Funding). c. Coordinate with development to provide AAA network. d. Consider additional dedicated funding for support facilities and programs.

Implementation Plan - Cycling

* Costs in 2018 dollars

slide-18
SLIDE 18

Financing Plan - Cycling

Potential Funding Increases for M edium- and Long-term Status Quo: $7.5 million / 25 years à approx. 30 km of new bike routes* Incremental Increase: $12.5 million / 25 years à approx. 50 km of new bike routes*

* assuming grant opportunities leverage City spending with an additional 40% funding

$0 $250,000 $500,000 $750,000 $1,000,000

Status Quo Incremental Increase

Short- term Medium- term Long- term

slide-19
SLIDE 19

a. Enhanced transit network

  • Long-term Vision (25 year)
  • Short-term (2019-2024)

b. Transit priority measures c. Transit customer experience

Transit Strategies

slide-20
SLIDE 20

a. Enhanced transit network

  • Long-term Vision (25 year)
  • Short-term (2019-2024)

b. Transit priority measures c. Transit customer experience

Transit Strategies

FOCUS FOR TODAY

slide-21
SLIDE 21

TRANSPORTATION & TRANSIT

  • a. Enhanced Transit Network

Long-T erm Vision

Regional Transit Improvements Local Transit Improvements

slide-22
SLIDE 22

Improving Transit in Stages

Short-term (5 years)

TRANSPORTATION & TRANSIT

Phase 1 (2019) Address Core Area Phase 2 (2020-2024) Increase Service Levels

Highstreet UDistrict City Centre Historic Downtown

slide-23
SLIDE 23

Implementation Strategy

  • Re-alignment of the

Routes 1, 2 and 3 in year 1

  • Opening of new transit

centre

  • First phase of

expansion to improve service reliability, improve service on key corridors

  • Introduction of

Highstreet Transit hub

  • Bourquin Exchange

phased out

  • Expand capacity at UFV
  • Downtown hub gets

significant on-street enhancements

  • New transit hub

introduced at Whatcom with associated service changes

  • Increased connectivity at

Highstreet hub

  • Continued service

reliability improvements, investments in core transit network, possible expansions to new service areas

  • Improve service

reliability and continue to invest in the frequent transit routes

  • Identify and develop a

more comprehensive plan for the Rapid Transit Corridor and the associated service integration

  • Consider opportunities

for LRT over long-term

slide-24
SLIDE 24

TRANSPORTATION & TRANSIT

Implementation Plan - Transit

Long-Term: $10M* Short-Term

  • No additional resources in Y

ear 1 with focus on realigning existing routes

  • Increased operating funding over short-term
  • Continue to increase service hours and funding over the medium- and long-

term

  • Shelters and accessibility improvements (2 bus stops per year)

* Costs in 2018 dollars

slide-25
SLIDE 25

TRANSPORTATION & TRANSIT

Financing Plan – Transit

$0 $250,000 $500,000 $750,000 $1,000,000 $1,250,000 $1,500,000 $1,750,000 $2,000,000 $2,250,000 $2,500,000

Status Quo Incremental Increase Transit Hubs

M edium-Term and Long-Term:

  • Increased funding for shelters and accessibility
  • Downtown hub (estimated $2M over short-term)
  • UFV, Highstreet and Whatcom exchanges ($1-2M each over medium-term)

Downtown Hub Other Exchanges

slide-26
SLIDE 26

a. Street Network Improvements

I. Major Network Improvements II. Other Network Improvements

b. Goods Movement c. Emerging T echnologies

Streets Strategies

FOCUS FOR TODAY

slide-27
SLIDE 27

a. Street Improvements

Major Network & Intersections

M ajor Intersections M ajor Network

slide-28
SLIDE 28

a. Street Improvements

Major Network & Intersections

Phasing Plan

Phasing

slide-29
SLIDE 29

TRANSPORTATION & TRANSIT

Implementation Plan - Streets

  • Long-Term Street Improvements: $250M*
  • Short-Term Priorities (<5 years):

a. Implement committed works (South Fraser Way, Vye Road, Mt Lehman Road and King-M arshall Connector) b. Support provincial highway investments to widen Highway 1 and improve interchanges c. Work towards South Fraser Way reconfiguration through development d. Begin planning for M cKee Connector e. Signals and minor intersection improvements

* Costs in 2018 dollars

slide-30
SLIDE 30

TRANSPORTATION & TRANSIT

Financing Plan - Streets

$0 $5,000,000 $10,000,000 $15,000,000 $20,000,000 $25,000,000 $30,000,000 $35,000,000 $40,000,000

Traffic Signals Other Improvements Rail Crossing Improvements Major Projects Interchanges and Overpasses

GFW Widening + SFW Whatcom Road M acLure Connector Fraser Highway (Phase 2) Fraser Highway (Phase 3)

Sample projects with illustrative project phasing for discussion

City contribution to M OTI interchanges

slide-31
SLIDE 31

TRANSPORTATION & TRANSIT

Funding Sources

  • Long-term affordable plan
  • Costs are distributed over time
  • M ajor projects expected to be funded

2/ 3 by grants

Funding Sources

DEBT*

* (only if required)

GRANTS COM M UNITY WORKS FUND DEVELOPM ENT COST CHARGES (DCCs) RESERVES

slide-32
SLIDE 32
  • c. Emerging Technologies
  • 1. Intelligent Transportation Systems

§

Real time information to drivers

§

Dynamic corridor signal coordination

§

Transit signal prioritization

§

Connected vehicles and vehicle-to- infrastructure applications

  • 2. Electric Vehicles

§

Additional public charging stations

§

Consider residential parking requirements to include electric

  • utlets

§

Consider more electric and alternative energy vehicles into the City’s fleet

Existing Private / Public Charging Station Locations

slide-33
SLIDE 33
  • c. Emerging Technologies
  • 3. New M obility / M obility Service

Choosing different modes for each trip segment such as:

§

Bike Share

§

Car Share

§

Ride Hailing

§

Transit

  • 4. Autonomous Vehicles

§

Implications of autonomous vehicles: accessibility, safety, mobility, parking demand, public transit, multi-modality, and land-use.

§

Long-range vision to leverage the technology.

§

Recognize potential changes to TMP priorities and phasing.

slide-34
SLIDE 34

Next Steps

J anuary – April 2018 M ay – J une 2018

  • Further Technical

Analysis

  • Refine and Finalize Long-

Term Concepts

  • Public Engagement
  • Develop Short, Medium,

and Long-Term Priorities

  • Draft Plan
  • Present to Council

(April 2018)

  • Final Plan
  • Present to Council

(June 2018)

slide-35
SLIDE 35

RECOM M ENDATIONS

THAT the Parks, Recreation and Culture Master Plan Stage 3 – Draft Plan, be received for information; and THAT staff be directed to proceed to Stage 4 – Final Plan of the Parks, Recreation and Culture Master Plan.