Southwest Area Transmission Subregional Planning Group Overview March 27, 2015 Western Regional Partnership Energy Committee 1 Agenda What is SWAT? (mission and history) SWAT Planning footprint Maps of existing transmission projects


slide-1
SLIDE 1

Southwest Area Transmission Subregional Planning Group Overview March 27, 2015

Western Regional Partnership Energy Committee

1

slide-2
SLIDE 2

Agenda

What is SWAT? (mission and history) SWAT Planning footprint Maps of existing transmission projects Transmission projects under development Current SWAT study work How to get involved in SWAT

2

slide-3
SLIDE 3

What is SWAT?

3

Southwest Area Transmission (SWAT) is a voluntary and open study group comprised of regulators, governmental entities, transmission users, transmission owners, transmission operators, environmental entities, and other stakeholders. The goal of SWAT is to promote collaborative regional transmission planning in the Desert Southwest. http://www.westconnect.com/planning_swat. php

slide-4
SLIDE 4

History of SWAT

Utilities have always been engaged in regional cooperation to ensure the reliability

  • f the grid (Western Systems Coordinating Council formed 1967).

In the mid- grid and encouraged formation of regional transmission groups (Southwest Regional Transmission Association formed 1994). Local voluntary study groups formed in Arizona when the Arizona Corporation Commission began conducting Biennial Transmission Assessments in 2000 (e.g. Southeast Arizona Transmission Study and Central Arizona Transmission Study).

  • Organizations. Many planning groups realigned, but RTOs never became
  • mandatory. (SWRTA merged with WSCC in 2002 to form WECC, while

WestConnect prepared to become an RTO in the Southwest) In 2004, CATS expanded its voluntary group to form SWAT. SWAT has coordinated with Sierra Subregional and Colorado Coordinated Planning Groups since 2007 to meet increased FERC regional planning requirements (WestConnect Agreement for Subregional Transmission Planning). SWAT will continue to define its role through the future as regional transmission planning needs change (e.g. FERC Order No. 1000).

4

slide-5
SLIDE 5

SWAT in Relation to

  • ther Planning

Regions

5

slide-6
SLIDE 6

SWAT in Relation to WestConnect

6

WestConnect SSPG CCPG SWAT Contractual entity funded by Transmission Owners and other stakeholders Performs simulations to identify regional needs and projects that address those needs Creates a ten year transmission plan for the region Selects specific transmission projects for development and cost-allocation Quasi-subcommittees of

  • WestConnect. Some

administrative support from WestConnect (e.g. website) Charter groups with no funding mechanism. No authority or role in selecting specific projects for development Address sub-regional coordination needs and report to WestConnect

slide-7
SLIDE 7

SWAT Subcommittee Footprints

Arizona Nevada California Utah Colorado New Mexico

SWAT NM AZ

Saguaro Rudd SWAT Southwest Area Transmission AZ Arizona Transmission System NM New Mexico Transmission EVSG Eldorado Valley Study Group Footprint wide work groups: Short Circuit, Transmission Corridor, California Interface, Coal Reduction Assessment Task Force 500kV 345kV

Web Sites WestConnect: http://www.westconnect.com/ SWAT: http://www.westconnect.com/planning_swat.php

Browning Kyrene Pinnacle Peak McKinley Springerville Silver King Greenlee Tortolita W W Luna Coronado Cholla Moenkopi South Vail Hidalgo Diablo Afton Caliente Newman Arroyo Amrad Artesia Blackwater BA Taos Ojo San Juan Four Corners West Mesa Glen Canyon Mead Crystal Shiprock Navajo Devers Palo Verde Hub Perkins Liberty North Gila Norton Sandia Winchester Market Place McCullough Eldorado Mira Loma Colorado River Red Bluff Lugo

EVSG

Victorville Harry Allen

7

slide-8
SLIDE 8
  • r greater. It is the power system used

for wholesale transactions, and it is regulated by the Federal Energy Regulatory Commission. kV and rules are often defined by state, local utility, or Tribe. SWAT focuses on the transmission level

8

slide-9
SLIDE 9

Major Transmission Utilities in SWAT

Arizona Public Service El Paso Electric Imperial Irrigation District NV Energy Los Angeles Department of Water and Power Public Service Company of New Mexico Salt River Project Southwest Transmission Cooperative Tucson Electric Power Company Western Area Power Administration Desert Southwest Region

9

slide-10
SLIDE 10

10

C C C C CO O O O OL L L L LO O O O OR R R R RA A A A AD D D D DO O O O O U U U U UT T T T TA A A A AH H H H H C C C C CA A A A AL L L L LI I I I IF F F F FO O O O OR R R R RN N N N NI I I I IA A A A A N N N N NE E E E EW W W W W M M M M ME E E E EX X X X XI I I I IC C C C CO O O O O A A A A AR R R R RI I I I IZ Z Z Z ZO O O O ON N N N NA A A A A T T T T TE E E E EX X X X XA A A A AS S S S S

SDG & E 13Mi

TO MEXICO

SDG & E 9Mi

TO MEXICO

SDG & E 81Mi

IMPERIAL VALLEY

SDG & E 84Mi

TO IID

MIGUEL

SCE 238Mi

VALLEY

SCE 38Mi

DEVERS

SCE 39Mi

SERRANO

SCE 19Mi SCE 50Mi SCE 30Mi

MIRA LOMA LUGO

LADWP/SCE 15Mi

SCE TO VINCENT TO RINALDI LADWP TO TOLUCA ADELANTO

LADWP 7.5Mi

VICTORVILLE

SCPPA/MSR LADWP/WAPA 202Mi LADWP 162Mi

SCE 50Mi MOHAVE McCULLOUGH ELDORADO MARKETPLACE TO ROBINSON SUMMIT TO DELTA INTERMOUNTAIN POWER PROJECT

+500KV DC 500KV 345KV

WAPA 70Mi

HOOVER MEAD

230KV

DAVIS YUMA NORTH GILA

ANPP 44Mi

PARKER LIBERTY SOUTH

NAVAJO 274.4Mi

GLEN CANYON TO SIGURD

PAC 159Mi WAPA 124Mi APS 258.5Mi NAVAJO 182.5Mi

NEW WADDELL 45MW

WAPA 10.5Mi WAPA 114Mi NAVAJO 76Mi

NAVAJO

WAPA APS 179Mi WAPA 8Mi PAC 259.7Mi

SHIPROCK TO HUNTINGTON MOENKOPI

APS APS 159Mi APS 62Mi APS 68Mi

FLAGSTAFF PREACHER CANYON

SRP 180.2Mi SRP 73.6Mi

WESTWING PINNACLE PEAK PHOENIX KYRENE SAGUARO

TEP 22Mi SRP

CHOLLA CORONADO SPRINGERVILLE

APS 206Mi TEP 112Mi

SILVERKING GREENLEE GREENLEE

TEP TEP TEP

TORTOLITA NORTH LOOP TUCSON VAIL

TEP 14Mi SWTC 23.6Mi

BICKNELL

SWTC 40Mi

PANTANO

SWTC 36Mi SWTC 16Mi

BUTTERFIELD

SWTC 24Mi

APACHE RED TAIL

TEP 128Mi TEP 240Mi

DOS CONDADOS

PNM/EPE/TNP 60Mi WAPA

TO LOST CANYON

138KV 115KV

TO RIFLE

PNM 10.4Mi PNM 157Mi 1

SAN JUAN OJO

PNM 104Mi PNM 156Mi TEP 90Mi

McKINLEY

TEP 103Mi

AMBROSIA WEST MESA

PNM 69Mi EPE (SP MS) 210Mi EPE 202Mi EPE 87Mi

HIDALGO

PNM/TNP/EPE 50Mi

LUNA

EPE 87Mi

DIABLO

EPE 30Mi

ARROYO

EPE 23Mi

CALIENTE NEWMAN

EPE 56Mi

AMRAD ARTESIA

EPE/TNP 125Mi

(D.C. Terminal) TAIBAN MESA

PNM 90Mi

B-A

PNM 132Mi PNM 43Mi

NORTON

PNM 159Mi

SWAT Major Transmission and Generation

N N N N NE E E E EV V V V VA A A A AD D D D DA A A A A

POWER PLANT SUBSTATION

RED HAWK

APS 2Mi

RUDD

ANPP 20Mi ANPP 35.4Mi

PALO VERDE/HASSAYAMPA MORENCI HACKBERRY WINCHESTER

SWTC 20.9Mi SWTC 7.5Mi SWTC 33Mi SWTC 27.2Mi SWTC 6.4Mi SWTC .44Mi

AFTON YAH-TA-HEY ESCALANTE BLACKWATER TAOS TO WALSENBURG GLADSTONE

EPE 87Mi

MACHO SPRINGS JOJOBA

ANPP 51.9Mi

GILA RIVER Pinal West FOUR CORNERS REID GARDNER HARRY ALLEN CRYSTAL

Last Update: 8/26/2014

COLORADO RIVER DUKE PINAL CENTRAL Browning

slide-11
SLIDE 11

11

APACHE CHOLLA SAN JUAN ESCALANTE REID GARDNER NAVAJO

C C C C CA A A A AL L L L LI I I I IF F F F FO O O O OR R R R RN N N N NI I I I IA A A A A N N N N NE E E E EW W W W W M M M M ME E E E EX X X X XI I I I IC C C C CO O O O O A A A A AR R R R RI I I I IZ Z Z Z ZO O O O ON N N N NA A A A A T T T T TE E E E EX X X X XA A A A AS S S S S

CORONADO FOUR CORNERS

SDG & E 9Mi

TO MEXICO

SDG & E 81Mi

IMPERIAL VALLEY

IID

SCE 238Mi

SCE 50Mi MOHAVE McCULLOUGH ELDORADO MARKETPLACE TO ROBINSON SUMMIT TO DELTA INTERMOUNTAIN POWER PROJECT

KV DC

WAPA 70Mi

HOOVER MEAD DAVIS YUMA NORTH GILA

ANPP 44Mi

PARKER LIBERTY SOUTH

NAVAJO 274.4Mi

GLEN CANYON TO SIGURD

PAC 159Mi WAPA 124Mi APS 258.5Mi NAVAJO 182.5Mi

NEW WADDELL 45MW

WAPA 10.5Mi WAPA 114Mi NAVAJO 76Mi WAPA APS 179Mi WAPA 8Mi PAC 259.7Mi

SHIPROCK TO HUNTINGTON MOENKOPI

APS APS 159Mi APS 62Mi APS 68Mi

FLAGSTAFF PREACHER CANYON

SRP 180.2Mi SRP 73.6Mi

WESTWING PINNACLE PEAK PHOENIX KYRENE SAGUARO

TEP 22Mi

SPRINGERVILLE

APS 206Mi TEP 112Mi

SILVERKING GREENLEE GREENLEE

TEP TEP TEP

TORTOLITA NORTH LOOP TUCSON VAIL

TEP 14Mi SWTC 23.6Mi

BICKNELL SWTC

40Mi

PANTANO

SWTC 36Mi SWTC 16Mi

BUTTERFIELD

SWTC 24Mi

RED TAIL

TEP 128Mi TEP 240Mi

DOS CONDADOS

PNM/EPE/TNP 60Mi WAPA

TO LOST CANYON TO RIFLE

PNM 10.4Mi PNM 157Mi

OJO

PNM 104Mi PNM 156Mi TEP 90Mi

McKINLEY

TEP 103Mi

AMBROSIA WEST MESA

PNM 69Mi EPE (SP MS) 210Mi EPE 202Mi EPE 87Mi

HIDALGO

PNM/TNP/EPE 50Mi

LUNA

EPE 87Mi

DIABLO

EPE 30Mi

ARROYO

EPE 23Mi

CALIENTE NEWMAN

EPE 56Mi

AMRAD ARTESIA

EPE/TNP 125Mi

(D.C. Terminal) TAIBAN MESA

PNM 90Mi

B-A

PNM 132Mi PNM 43Mi

NORTON

PNM 159Mi

RED HAWK

APS 2Mi

RUDD

ANPP 20Mi ANPP 35.4Mi

PALO VERDE/HASSAYAMPA MORENCI HACKBERRY WINCHESTER

SWTC 20.9Mi SWTC 7.5Mi SWTC 33Mi SWTC 27.2Mi SWTC 6.4Mi SWTC .44Mi

AFTON YAH-TA-HEY BLACKWATER TAOS TO WALSENBURG GLADSTONE

EPE 87Mi

MACHO SPRINGS JOJOBA

ANPP 51.9Mi

GILA RIVER Pinal West HARRY ALLEN CRYSTAL COLORADO RIVER DUKE PINAL CENTRAL Browning

Connecting Coal Plants to Load Centers

slide-12
SLIDE 12

Exporting Power to California

12

C C C C CA A A A AL L L L LI I I I IF F F F FO O O O OR R R R RN N N N NI I I I IA A A A A A A A A AR R R R RI I I I IZ Z Z Z ZO O O O ON N N N NA A A A A

SDG & E 13Mi SDG & E 9Mi SDG & E 81Mi

IMPERIAL VALLEY

SDG & E 84Mi

TO IID

MIGUEL

SCE 238Mi

VALLEY

SCE 38Mi

DEVERS

SCE 39Mi

SERRANO

SCE 19Mi SCE 50Mi SCE 30Mi

MIRA LOMA LUGO

LADWP/SCE 15Mi

SCE TO VINCENT TO RINALDI LADWP TO TOLUCA ADELANTO

LADWP 7.5Mi

VICTORVILLE

SCPPA/MSR LADWP/WAPA 202Mi LADWP 162Mi

SCE 50Mi MOHAVE McCULLOUGH ELDORADO MARKETPLACE HOOVER MEAD YUMA NORTH GILA

ANPP 44Mi

LIBERTY

NAVAJO 274.4Mi

NAVAJO MOENKOPI WESTWING PHOENIX

N N N N NE E E E EV V V V VA A A A AD D D D DA A A A A

RED HAWK

APS 2Mi ANPP 20Mi ANPP 35.4Mi

PALO VERDE/HASSAYAMPA JOJOBA GILA RIVER FOUR CORNERS HARRY ALLEN CRYSTAL COLORADO RIVER

slide-13
SLIDE 13

Accessing Federal Hydropower (WAPA-DSW System)

13

slide-14
SLIDE 14

Integrating Renewables (Projects Under Development)

14

slide-15
SLIDE 15

SunZia Wind Resources

15

slide-16
SLIDE 16

SunZia Solar Resources

16

slide-17
SLIDE 17

Southline - Renewables

17

slide-18
SLIDE 18

Current SWAT Study Work

Arizona Corporation Commission 9th Biennial Transmission Assessment coordination

Some contingency analysis on ten year plan filings Reliability Must Run studies in local pockets

Assisting WestConnect in FERC Order No. 1000 Planning Process

Used SWAT forum to develop a draft power flow simulation case for WestConnect planning study Will use the SWAT forum as needed to review WestConnect study results

Coal reduction study

First phase completed in 2014 Second phase will be completed by January 2016. (Focuses on EPA 111(d) scenarios and identifying conceptual transmission needs to address reliability concerns)

18

slide-19
SLIDE 19

19

Baseline

Reference case without coal plant shutdowns Simulated a Heavy Summer 2019 condition

Two Scenarios (about 20% coal retirement)

Expected Coal Reduction with Planned new Gas Expected Coal Reduction replaced by Renewables

Two Sensitivities (about 50% coal retirement)

High Coal Reduction with High Renewables High Coal Reduction with Renewables and Planned new Gas

Specific generating units and locations identified to replace retired units to the extent information was available

slide-20
SLIDE 20

20

The High Coal Reduction with High Renewables scenario demonstrated widespread cascading after single contingencies. Other scenarios demonstrated fairly acceptable system performance. There is a limit to the amount of coal plants that may be shut down while maintaining reliable system operation

Unsure of exactly where the limit falls, especially as dispatch scenarios change in different times of the day or year. The limit seems to be influenced the amount of gas fired replacement capacity, which could be due to its reactive power capability. The amount of renewable resources that may be integrated is dependent upon addition of gas fueled generation or other resources that compensate for loss of inertia and dynamic reactive capability No analysis to show what transmission system upgrades could resolve system cascading (e.g. capacitors, synchronous condensers, new transmission lines)

Ongoing studies are needed

slide-21
SLIDE 21

How To Get Involved In SWAT

Upcoming quarterly SWAT meetings:

May, webinar August, Westminster, CO November, Phoenix, AZ

Various subcommittee calls/webinars throughout the year (Arizona, Eldorado Valley, New Mexico) Email distribution lists for each of these groups. Contact Patrick Harwood (harwood@wapa.gov)

21

slide-22
SLIDE 22

Questions or More Information About SWAT Patrick Harwood Western Area Power Administration harwood@wapa.gov 602-605-2883

22

slide-23
SLIDE 23

Maps of Existing and Future Transmission Projects

Arizona Utility Ten Year Plans and Biennial Transmission Assessment filings

http://edocket.azcc.gov/Docket/DocketDetailSearch?docket Id=18827

TEPPC

https://www.wecc.biz/TransmissionExpansionPlanning/Pag es/Project-Information-Portal2.aspx

WestConnect Ten Year Plan

http://www.westconnect.com/final_reports_2015.php

SWAT Planning Map

http://www.westconnect.com/documents_results.php?categ

  • ryid=83

23

slide-24
SLIDE 24

Land Resource Maps for Development of New Generation and Transmission

US Bureau of Land Management, Arizona Office

http://www.blm.gov/az/st/en/prog/energy/arra_solar.ht ml

Open Energy Information

http://en.openei.org/wiki/Gateway:Transmission

TEPPC Environmental Data Viewer

https://www.wecc.biz/TransmissionExpansionPlanning/ Pages/Environmental-and-Cultural- Considerations.aspx