SHIMLA ZONE AEs TRAINING July 29,2020 (Wednesday) Presentation by Er.Lalit Bhushan EinC(Project) HPPWD, Shimla HPPWD TRAINING CELL AT SHIMLA TRAINING OF AEs OF SHIMLA ZONE IN CONFERENCE HALL AT NIRMAN BHAWAN SHIMLA Description of Course


  1. SHIMLA ZONE AEs TRAINING July 29,2020 (Wednesday) Presentation by Er.Lalit Bhushan EinC(Project) HPPWD, Shimla

  2. HPPWD TRAINING CELL AT SHIMLA TRAINING OF AEs OF SHIMLA ZONE IN CONFERENCE HALL AT NIRMAN BHAWAN SHIMLA Description of Course Quality control in PMGSY roads and Bridges Course Er.Lalit Grover Co-ordinator Executive Engineer (QC & D) Mobile 9418232111 Participation level AEs under Rampur Circle/Divisions Rampur, Kumarsain,Nirmand, Karcham, Kalpa,Kaza Duration of Course 1 day 9:45 AM to 5:00 PM Date 29-07-2020

  3. My Self Appraisal • B.E. CIVIL from NIT, Tiruchirapalli under Madras University in June,1984. • Graduate JE on 28-03-1985 • Assitant Engineer on 24-06-1986 • Executive Engineer on 30-01-2003 • Superintending Engineer on 20-05-2013 • Chief Engineer on 29-10-2018 • Engineer in Chief (Project) on 2-03-2020

  4. Sanctioned/Existing Strength and Vacancy position as on date Category Sanctioned Strength Existing Strength Engineer in Chief 2 2 Chief Engineer 7 7 Superintending Engineer 30 30 Executive Engineer 113 106 Assistant Engineer(Civil) 358 313 Junior Engineer 1054 998 Jr. Tech(Work Inspector) 1797 1059 Mate 2478 2067 Beldar 23539 16794

  5. TOPICS IN PRESENTATION • Training of AEs in HPPWD • PRADHAN MANTRI GRAM SADAK YOJANA Online Management, Monitoring and Accounting System (OMMAS) • Quality Control PMGSY works • CPWD Manual 2019 • Indian Roads Congress (IRC) • Start of e Office in HPPWD • Video conference with all CEs on 20-07-2020

  6. Training of AEs in HPPWD • Training of AEs at Nirman Bhawan shimla, JEs at Zonal Level will be started from July,2020. • It was agreed that Regular weekly One day Training for AEs at Nirman Bhawan and for JEs at Zonal level will be started from July,2020. • Organizational Structure at Zonal level will be 1.Executive Engineer(Training) 2. Assistant Engineer(Training) 3.Junior Engineer (Training) which will be decided by CEs at Zonal Level from among the staff available with them.In the beginning all Newly appointed JEs and JEs with Unsatisfactory Gradings by NQM/SQM be called for this 1 day Training at Zonal level with FN session for Quality related matters and AN session for all other important issues in Roads, Buildings and Bridges.

  7. Training of AEs in HPPWD • Objective • To train each and every employee from his induction into the department till the end of his career with an endeavour to ensure that the employees get a chance to participate in a properly structured training process to realize their full potential. • To ensure that the officers are kept abreast with the changing technological scenario through refresher training courses to update their knowledge base towards emerging technologies & innovative materials. • Enable HPPWD to implement and execute it’s Human Resources strategic objectives. • Develop skills and competence in the workplace.

  8. PRADHAN MANTRI GRAM SADAK YOJANA Online Management, Monitoring and Accounting System (OMMAS) • Home • Core Network • Proposals • Progress Monitoring • Quality • Other Reports • Habitation

  9. PRADHAN MANTRI GRAM SADAK YOJANA – Quality – Quality Monitor Work Wise Details – Joint Inspection – Unsatisfactory Work Grading Abstract – Quality (NQM Reports) – Monitorwise Grading Abstract – Quality Grading Abstract – Regraded Grading Abstract – Quality (SQM Reports) – Monitorwise Grading Abstract – Quality Grading Abstract

  10. PRADHAN MANTRI GRAM SADAK YOJANA – Physical Progress – Physical Progress of Works – Physical and Financial Project Summary – Physical Financial Monitoring – National Projects Summary – Completed Roads – Road wise progress of Work – State Road Completion Report – Layer Wise Length - Inprogress Road – Balance Habitations to be Connected – Schemewise Sanction & Completed Road Works

  11. PRADHAN MANTRI GRAM SADAK YOJANA – Financial Progress – Monthly Account – Balance Sheet – Final Bill Payment – Final Bill Payment (as per physical completion) – Final Bill Payment Abstract – State Account Monitoring – Fund Position Report – Fund Position Report Live – Fund Position Report for Admin Fund – Physical and Financial Progress – PFMS MIS Dashboard

  12. PRADHAN MANTRI GRAM SADAK YOJANA – State Profile – State Profile – State Profile with Cluster – Habitation Coverage Report – Dynamic Reports – Progress Report – Monthly Progress Reports (MPR) – MPR1 – MPR1 - LWE – State MPR Abstract Report – MPR1 Exclude LWE – Financial Yearwise Achievement

  13. PRADHAN MANTRI GRAM SADAK YOJANA • Circulars / Minutes • Circulars • Publications • Pre-Empowered Committee Minutes • Empowered Committee Minutes • Clearance Letters • Sanction Letters • Dropping Letters

  14. Pradhan Mantri Gram Sadak Yojana Physical and Financial Yearwise Achievements Length Habitation Expenditure Expenditure Financial Year Achievement Achievement as per as per (In Kms) Programme Administrati Fund (In Cr.) ve Fund (In Cr.) 2016-17 1,429.266 100 320.29 1.03 2017-18 1,772.533 57 520.82 0.91 2018-19 1,334.350 83 690.59 0.63 2019-20 1,086.809 94 724.34 0.94 632.228 8 223.69 0.23 2020-21

  15. Quality Control PMGSY works First Tier: - It includes the supervision of works by the field Engineers up to the level of Zonal Chief Engineers. Second Tier: - The function of 2nd tier independent Quality Management is to improve the quality and effectiveness of the Quality enforcement process. The Govt. has appointed 14 No. State Quality Monitors. 3 are Chief Engineers(Retd) and 11 are Superintending Engineers (Retd). Third tier: - National Rural Infrastructure Development Agency (NRIDA) has further appointed National Quality Monitors for ensuring the Quality Assurance in PMGSY works.

  16. Quality Control PMGSY works SQM Grading 2019-20 Work Total Satisfactory SRI Unsatisfactory Category Completed 115 100 12 3 Works Ongoing 781 618 123 40 Works Maintenance 68 47 7 14 Works Bridge Works 26 19 7 0 Total 990 784 149 57

  17. Quality Control PMGSY works NQM Grading 2019-20 Work Total Satisfactory SRI Unsatisfactory Category Completed 36 26 3 7 Works Ongoing 217 168 27 22 Works Maintenance 43 20 9 14 Works Bridge Works 3 3 0 0 Total 299 217 39 43

  18. Quality Control PMGSY works SQM Grading 2020-21 Work Total Satisfactory SRI Unsatisfactory Category Completed 17 17 0 0 Works Ongoing 260 216 30 14 Works Maintenance 2 1 1 0 Works Bridge Works 9 8 1 0 Total 288 242 32 14

  19. Quality Control PMGSY works SQM Unsatisfactory Grading 2020-21 S.No. Package Road Name Inspection Sanction District Date Year 1 HP09443 L102-Bhakhality to Dharech 13 Jun,2020 2016-17 Shimla Gawech 2 HP09401 L097-Jhalta to Giltari road 26 Jun,2020 2016-17 Shimla 3 HP02300 L047-Salwan to Girjindoo 20 Jun,2020 2018-19 Chamba road 4 HP02351 L071-Dandi Barai 20 Jun,2020 2018-19 Chamba 26 Jul 2020 2018-19 5 HP02347 L029-Chakoli road to Dhalla Chamba 6 HP08470 L055-Seri Jalan to Mandar 31 May,2020 2018-19 Mandi Tanda road 7 HP08185 L065-Masar to Banaul road 12 Jun,2020 2018-19 Mandi 8 HP08452 L056-Bhatwari to Rensh road 24 Jun,2020 2018-19 Mandi 9 HP08191 L086-Jhand to Lagdhar road 20 Jun,2020 2016-17 Mandi

  20. Quality Control PMGSY works SQM Unsatisfactory Grading 2020-21 S.No. Package Road Name Inspection Sanction District Date Year 10 HP08363 L062-Sajao to 22 July,2020 2017-18 Mandi Chhatrayana road 11 HP08370 L117-Dhalon to Brehal 22 July,2020 2018-19 Mandi road 12 HP06311 L093-Mahog to Gawala 22 July,2020 2016-17 Mandi 13 HP06138 L044-NH21 to village 22 July,2020 2017-18 Kullu Bran 14 HP04313 L152-Bankhandi 23 July,2020 2019 -20 Kangra toHaripur

  21. Quality Grading Details Sr.No. Item Description Grade 1 Setting Out and Working Drawing Satisfactory 2 Site Clearance and Grubbing Satisfactory 3 Quality Arrangment Satisfactory 4 Geometrics Satisfactory Earth Work and Sub-grade in Embankment/ Not 5 Cutting Applicable Not 6 Earth work Cutting in Hilly/ Rolling Terrain Applicable 7 Sub-Base Satisfactory 8 Base Course - Water Bound Macadam Satisfactory

  22. Quality Grading Details Sr.No. Item Description Grade Bituminous Layer - Premix 9 Satisfactory Carpet(PMC)/Surface Dressing(SD) Not 10 Shoulders Applicable Cross Drainage Works - Causeways of all Not 11 spans and Culverts upto 6 m span Applicable 12 Side Drain and Catch Water Drain Satisfactory CC/ Semi Rigid Pavements and Associated Not 13 Pukka Drains Applicable 14 Road Furniture and Markings Satisfactory 15 Overall Grading Satisfactory

  23. Quality Control PMGSY works NQM Grading 2020-21 Work Total Satisfactory SRI Unsatisfactory Category Completed 0 0 0 0 Works Ongoing 0 0 0 0 Works Maintenance 0 0 0 0 Works Bridge Works 0 0 0 0 Total 0 0 0 0

  24. Quality Control PMGSY works SQM Inspection Target for 2020-21 Work Category Inspection Target /Achievement On going works 859/260 (as on 1/04/2020) Projects cleared but 268/0 Unawarded (as on 1/04/2020) Total 1127/260

  25. Pradhan Mantri Gram Sadak Yojana Works Not Inspected by SQM Commenced < 2 86 Months Commenced 2-6 57 Months Commenced 6-12 45 Months Commenced >12 28 Months Total 217

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.