SH 7 Bus Rapid Transit Study Project Update April 23, 2015 7:30am - - PowerPoint PPT Presentation

sh 7 bus rapid transit study
SMART_READER_LITE
LIVE PREVIEW

SH 7 Bus Rapid Transit Study Project Update April 23, 2015 7:30am - - PowerPoint PPT Presentation

SH 7 Bus Rapid Transit Study Project Update April 23, 2015 7:30am 9:00am Outline 1. Grant application 2. Technical Advisory Group 3. Draft Scope of Work 4. Timeline 1. Grant Application Submitted September 2014; Awarded April 15, 2015


slide-1
SLIDE 1

SH 7 Bus Rapid Transit Study

Project Update April 23, 2015 7:30am – 9:00am

slide-2
SLIDE 2

Outline

  • 1. Grant application
  • 2. Technical Advisory Group
  • 3. Draft Scope of Work
  • 4. Timeline
slide-3
SLIDE 3
  • 1. Grant Application

‐Submitted September 2014; Awarded April 15, 2015 ‐Total: $250,000 ‐Federal: $200,000, Boulder County: $25,000, Adams County: $25,000 ‐Planning and Environmental Linkages: 75th Street to SH 287 ‐Bus Rapid Transit Study: City of Boulder to City of Brighton

slide-4
SLIDE 4
  • 1. Grant Application

‐Submitted September 25, 2014; Awarded April 15, 2015 ‐Total: $250,000 ‐Federal: $200,000, Boulder County: $25,000, Adams County: $25,000

slide-5
SLIDE 5
  • 2. Technical Advisory Committee

Purpose: Provide detailed feedback on project direction and makes project recommendations to the Policy Advisory Committee Composed of: Transportation experts from local agencies in the corridor and DRCOG, RTD, CDOT, FHWA and FTA.

slide-6
SLIDE 6
  • 2. Technical Advisory Committee

Boulder County: Marc Ambrosi, Scott McCarey Adams County: Jeanne Shreve RTD: Chris Quinn City of Brighton: Kimberly Dall City and County of Broomfield: Debra Baskett City of Boulder: Kathleen Bracke City of Lafayette: Paul Rayl City of Thornton: Kent Moorman CDOT Region 4: Karen Schneiders CDOT Region 1: Danny Herman & Markos Atamo Town of Erie: Gary Bahlen DRCOG: Metthew Helfant FHWA: Stephanie Gibson (not yet contacted) FTA: David Beckhouse (not yet contacted)

slide-7
SLIDE 7
  • 3. Draft Scope of Work: Part 1

Continuation of efforts from the Planning and Environmental Linkages Study & Envision East Arapahoe State Highway 7 PEL Envision East Arapahoe

slide-8
SLIDE 8

The PEL for the area between 75th Street and US 287 will include: Analysis of current and future travel patterns Identification of current and future land use

slide-9
SLIDE 9

Draft Scope of Work: Part 2

Bus Rapid Transit: Feasibility, Operations, Cost And findings from the

  • ngoing Northeast

Area Transit Evaluation (NATE), Building off BRT findings from the Northwest Area Mobility Study (NAMS)

slide-10
SLIDE 10
  • Density requirements necessary to support BRT
  • Running way (curb running, center running)
  • Locations of stops and stations

The BRT component of this study will investigate:

  • Transit fleet needs
  • Station Amenities
  • Opening Day and Future Costs
  • Integration with other elements of the RTD system
  • Infrastructure improvements necessary to run BRT
slide-11
SLIDE 11
  • 4. Timeline and Next Steps
  • 1. Continue to refine the consultant scope of work.
  • 2. Develop procurement procedures
  • 3. Release RFP
  • 4. Retain consultant and finalize scope of work and budget
  • 5. Finalize all grant funding agreements
  • 6. Consultant notice to proceed
slide-12
SLIDE 12

April July October Refine SOW Release RFP Develop selection criteria Select Consultant May June Aug Sep Nov Dec Notice to Proceed Finalize funding SH7 Policy Advisory Meeting